4127 W 22ND PL 90018
Certificate Information: 4127 W 22ND PL 90018
- Application / Permit
- 19014-20000-07046
- Plan Check / Job No.
- B19VN22366
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMOVE (E) PORCH/STAIRS IN FRONT AND PATIO COVER IN REAR, ADD 17' X 23' 8" MASTER BEDROOM/BATHROOM TO REAR, ADD 6' X 18' 1" LIVING ROOM EXTENSION AND 6' X 9' 6" PORCH TO FRONT OF (E) SFD. ALL WORK DONE PER STRUCTURAL ENGINEERING.
- Permit Issued
- Issued on 11/9/2020
- Issuing Office
- Current Status
- CofO Issued on 9/16/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/24/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/24/2019 | GURUNATH NESARAJAH |
| Corrections Issued | 12/24/2019 | GURUNATH NESARAJAH |
| Plan Check Approved | 10/9/2020 | GURUNATH NESARAJAH |
| Issued | 11/9/2020 | APPLICANT |
| Building Plans Picked Up | 11/13/2020 | APPLICANT |
| CofO in Progress | 8/26/2021 | STUART CHAPMAN |
| Permit Finaled | 9/16/2021 | DEROLD HAUFF |
| CofO Issued | 9/16/2021 | DEROLD HAUFF |
| Permit Finaled | 9/16/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 12/24/2019 | LEE GUILBEAUX |
| Sewer availability | Cleared | 12/24/2019 | LEE GUILBEAUX |
| Low Impact Development | Cleared | 6/1/2020 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 7/15/2020 | WALLIE JONG |
| Community Plan Implem. Overlay | Cleared | 9/2/2020 | KYLE WINSTON |
Contact Information
| Contractor | Licg; Lic. No.: 1042051-B | 756 S BROADWAY STE 409 LOS ANGELES, CA 90014 |
| Engineer | Cooke,, Conway Cecil; Lic. No.: S5524 | 34658 LINDA ROSEA RD TEMECULA, CA 92592 |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/24/2020 | Approved | STUART CHAPMAN |
| Excavation/Setback/Form/Re-Bar | 11/30/2020 | Corrections Issued | STUART CHAPMAN |
| Footing/Foundation/Slab | 11/30/2020 | Not Ready for Inspection | STUART CHAPMAN |
| METHANE-Barrier | 11/30/2020 | Approved | STUART CHAPMAN |
| METHANE-Subgrade | 11/30/2020 | Approved | STUART CHAPMAN |
| Piling/Pier/Caisson | 11/30/2020 | Not Ready for Inspection | STUART CHAPMAN |
| Excavation/Setback/Form/Re-Bar | 12/7/2020 | Approved | STUART CHAPMAN |
| Pre-Inspection | 12/15/2020 | Approved | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/21/2020 | Partial Approval | STUART CHAPMAN |
| Pre-Inspection | 1/27/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Wood Frame | 1/27/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 2/9/2021 | Corrections Issued | STUART CHAPMAN |
| ELECTRICAL-Rough | 2/9/2021 | Approved | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/9/2021 | Not Ready for Inspection | STUART CHAPMAN |
| Green Building Rough | 2/9/2021 | Not Ready for Inspection | STUART CHAPMAN |
| MERV13>=Rough | 2/9/2021 | Approved | STUART CHAPMAN |
| METHANE-Rough | 2/9/2021 | Approved | STUART CHAPMAN |
| PLUMBING-Rough | 2/9/2021 | Approved | STUART CHAPMAN |
| BUILDING-Rough-Frame | 2/18/2021 | Approved | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/18/2021 | Approved | STUART CHAPMAN |
| Green Building Rough | 2/18/2021 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 2/18/2021 | Partial Approval | STUART CHAPMAN |
| Pre-Inspection | 2/18/2021 | Approved | STUART CHAPMAN |
| Wood Frame | 2/18/2021 | Approved | STUART CHAPMAN |
| Shower Pan | 2/19/2021 | Approved | STUART CHAPMAN |
| Insulation | 2/24/2021 | Approved | KATHRYN BUTTERWORTH |
| Drywall Nailing | 2/25/2021 | Approved | STUART CHAPMAN |
| ELECTRICAL-Final | 4/23/2021 | Not Ready for Inspection | STUART CHAPMAN |
| Final | 4/23/2021 | Corrections Issued | STUART CHAPMAN |
| Footing/Foundation/Slab | 4/23/2021 | Approved | STUART CHAPMAN |
| Green Building Final | 4/23/2021 | Approved | STUART CHAPMAN |
| MERV13>=Final | 4/23/2021 | Approved | STUART CHAPMAN |
| PLUMBING-Final | 4/23/2021 | Approved | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 4/23/2021 | SGSOV Not Ready | STUART CHAPMAN |
| Smoke Detectors | 4/23/2021 | Approved | STUART CHAPMAN |
| ELECTRICAL-Final | 5/6/2021 | Not Ready for Inspection | STUART CHAPMAN |
| Final | 5/6/2021 | Not Ready for Inspection | STUART CHAPMAN |
| HVAC-Final | 5/6/2021 | Not Ready for Inspection | STUART CHAPMAN |
| PLUMBING-Final | 5/6/2021 | Approved | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 5/6/2021 | SGSOV Not Ready | STUART CHAPMAN |
| ELECTRICAL-Final | 8/16/2021 | Approved | STUART CHAPMAN |
| Final | 8/16/2021 | Partial Approval | STUART CHAPMAN |
| HVAC-Final | 8/16/2021 | Approved | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 8/16/2021 | SGSOV Approved | STUART CHAPMAN |
| Smoke Detectors | 8/16/2021 | Approved | STUART CHAPMAN |