4127 W 22ND PL 90018

Certificate Information: 4127 W 22ND PL 90018

Application / Permit
19014-20000-07046
Plan Check / Job No.
B19VN22366
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMOVE (E) PORCH/STAIRS IN FRONT AND PATIO COVER IN REAR, ADD 17' X 23' 8" MASTER BEDROOM/BATHROOM TO REAR, ADD 6' X 18' 1" LIVING ROOM EXTENSION AND 6' X 9' 6" PORCH TO FRONT OF (E) SFD. ALL WORK DONE PER STRUCTURAL ENGINEERING.
Permit Issued
Issued on 11/9/2020
Issuing Office
Current Status
CofO Issued on 9/16/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/24/2019 APPLICANT
Assigned to Plan Check Engineer 12/24/2019 GURUNATH NESARAJAH
Corrections Issued 12/24/2019 GURUNATH NESARAJAH
Plan Check Approved 10/9/2020 GURUNATH NESARAJAH
Issued 11/9/2020 APPLICANT
Building Plans Picked Up 11/13/2020 APPLICANT
CofO in Progress 8/26/2021 STUART CHAPMAN
Permit Finaled 9/16/2021 DEROLD HAUFF
CofO Issued 9/16/2021 DEROLD HAUFF
Permit Finaled 9/16/2021 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 12/24/2019 LEE GUILBEAUX
Sewer availability Cleared 12/24/2019 LEE GUILBEAUX
Low Impact Development Cleared 6/1/2020 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 7/15/2020 WALLIE JONG
Community Plan Implem. Overlay Cleared 9/2/2020 KYLE WINSTON

Contact Information

Contractor Licg; Lic. No.: 1042051-B 756 S BROADWAY STE 409      LOS ANGELES, CA 90014
Engineer Cooke,, Conway Cecil; Lic. No.: S5524 34658 LINDA ROSEA RD      TEMECULA, CA 92592

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/24/2020 Approved STUART CHAPMAN
Excavation/Setback/Form/Re-Bar 11/30/2020 Corrections Issued STUART CHAPMAN
Footing/Foundation/Slab 11/30/2020 Not Ready for Inspection STUART CHAPMAN
METHANE-Barrier 11/30/2020 Approved STUART CHAPMAN
METHANE-Subgrade 11/30/2020 Approved STUART CHAPMAN
Piling/Pier/Caisson 11/30/2020 Not Ready for Inspection STUART CHAPMAN
Excavation/Setback/Form/Re-Bar 12/7/2020 Approved STUART CHAPMAN
Pre-Inspection 12/15/2020 Approved STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 12/21/2020 Partial Approval STUART CHAPMAN
Pre-Inspection 1/27/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
Wood Frame 1/27/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 2/9/2021 Corrections Issued STUART CHAPMAN
ELECTRICAL-Rough 2/9/2021 Approved STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 2/9/2021 Not Ready for Inspection STUART CHAPMAN
Green Building Rough 2/9/2021 Not Ready for Inspection STUART CHAPMAN
MERV13>=Rough 2/9/2021 Approved STUART CHAPMAN
METHANE-Rough 2/9/2021 Approved STUART CHAPMAN
PLUMBING-Rough 2/9/2021 Approved STUART CHAPMAN
BUILDING-Rough-Frame 2/18/2021 Approved STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 2/18/2021 Approved STUART CHAPMAN
Green Building Rough 2/18/2021 Approved STUART CHAPMAN
Interior/Exterior Lathing 2/18/2021 Partial Approval STUART CHAPMAN
Pre-Inspection 2/18/2021 Approved STUART CHAPMAN
Wood Frame 2/18/2021 Approved STUART CHAPMAN
Shower Pan 2/19/2021 Approved STUART CHAPMAN
Insulation 2/24/2021 Approved KATHRYN BUTTERWORTH
Drywall Nailing 2/25/2021 Approved STUART CHAPMAN
ELECTRICAL-Final 4/23/2021 Not Ready for Inspection STUART CHAPMAN
Final 4/23/2021 Corrections Issued STUART CHAPMAN
Footing/Foundation/Slab 4/23/2021 Approved STUART CHAPMAN
Green Building Final 4/23/2021 Approved STUART CHAPMAN
MERV13>=Final 4/23/2021 Approved STUART CHAPMAN
PLUMBING-Final 4/23/2021 Approved STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 4/23/2021 SGSOV Not Ready STUART CHAPMAN
Smoke Detectors 4/23/2021 Approved STUART CHAPMAN
ELECTRICAL-Final 5/6/2021 Not Ready for Inspection STUART CHAPMAN
Final 5/6/2021 Not Ready for Inspection STUART CHAPMAN
HVAC-Final 5/6/2021 Not Ready for Inspection STUART CHAPMAN
PLUMBING-Final 5/6/2021 Approved STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 5/6/2021 SGSOV Not Ready STUART CHAPMAN
ELECTRICAL-Final 8/16/2021 Approved STUART CHAPMAN
Final 8/16/2021 Partial Approval STUART CHAPMAN
HVAC-Final 8/16/2021 Approved STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 8/16/2021 SGSOV Approved STUART CHAPMAN
Smoke Detectors 8/16/2021 Approved STUART CHAPMAN