15036 W FRIAR ST 91411

Certificate Information: 15036 W FRIAR ST 91411

Application / Permit
19014-20000-07035
Plan Check / Job No.
B19VN22347
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
27' X 22' ADDITION & CONVERT GARAGE TO ACCESSORY DWELLING UNIT PER AB 494 & SB 229
Permit Issued
Issued on 5/26/2020
Issuing Office
Valley
Current Status
CofO Issued on 1/16/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/24/2019 APPLICANT
Assigned to Plan Check Engineer 12/26/2019 JEFFREY TANGONAN
Corrections Issued 12/26/2019 JEFFREY TANGONAN
Building Plans Picked Up 1/10/2020 APPLICANT
Plan Check Approved 4/29/2020 JEFFREY TANGONAN
Issued 5/26/2020 LADBS
CofO in Progress 11/9/2020 MICHAEL TEMPLE
Permit Finaled 1/16/2021 MICHAEL SMITH
CofO Issued 1/16/2021 MICHAEL SMITH
Permit Finaled 1/16/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 1/10/2020 MARKOS PEREZ-BRAN
Eng Process Fee Ord 176,300 Cleared 1/10/2020 MARKOS PEREZ-BRAN
Roof/Waste drainage to street Cleared 1/10/2020 MARKOS PEREZ-BRAN
Sewer availability Cleared 1/10/2020 MARKOS PEREZ-BRAN
Construction near power lines Cleared 3/6/2020 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/6/2020 Partial Inspection JENNIFER RABUCHIN
Footing/Foundation/Slab 7/24/2020 Approved WILLIAM KUEHN
METHANE-Barrier 7/24/2020 Approved WILLIAM KUEHN
METHANE-Subgrade 7/24/2020 Approved WILLIAM KUEHN
Floor/Roof Diaphrgm/Shear Wall 7/31/2020 Partial Inspection WILLIAM KUEHN
PLUMBING-Rough 7/31/2020 Partial Inspection WILLIAM KUEHN
Floor/Roof Diaphrgm/Shear Wall 8/13/2020 Approved DANIEL DREW
BUILDING-Rough-Frame 8/31/2020 Conditional Approval WILLIAM KUEHN
Rough-Elec/Plmb/HVAC 8/31/2020 Approved WILLIAM KUEHN
Sewer 8/31/2020 Approved WILLIAM KUEHN
Underground Mechanical 8/31/2020 Partial Inspection WILLIAM KUEHN
Insulation 9/3/2020 Approved DANIEL ORRANTE
Interior/Exterior Lathing 9/3/2020 Approved DANIEL ORRANTE
Drywall Nailing 9/9/2020 Approved WILLIAM KUEHN
Green Building Rough 9/9/2020 Approved WILLIAM KUEHN
BUILDING-Rough-Frame 10/22/2020 Not Ready for Inspection MATTHEW NELSON
Final 10/22/2020 Corrections Issued MATTHEW NELSON
Green Building Final 10/22/2020 Not Ready for Inspection MATTHEW NELSON
METHANE-Final 10/22/2020 Not Ready for Inspection MATTHEW NELSON
METHANE-Rough 10/22/2020 Not Ready for Inspection MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 10/22/2020 SGSOV Not Ready MATTHEW NELSON
Smoke Detectors 10/22/2020 Not Ready for Inspection MATTHEW NELSON
BUILDING-Rough-Frame 10/30/2020 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 10/30/2020 Corrections Issued JENNIFER RABUCHIN
Final 10/30/2020 Corrections Issued JENNIFER RABUCHIN
Green Building Final 10/30/2020 Corrections Issued JENNIFER RABUCHIN
METHANE-Final 10/30/2020 Approved JENNIFER RABUCHIN
METHANE-Rough 10/30/2020 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 10/30/2020 SGSOV Approved JENNIFER RABUCHIN
Smoke Detectors 10/30/2020 Approved JENNIFER RABUCHIN
Final 11/6/2020 OK to Issue CofO WILLIAM KUEHN
Green Building Final 11/6/2020 Approved WILLIAM KUEHN