15036 W FRIAR ST 91411
Certificate Information: 15036 W FRIAR ST 91411
- Application / Permit
- 19014-20000-07035
- Plan Check / Job No.
- B19VN22347
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 27' X 22' ADDITION & CONVERT GARAGE TO ACCESSORY DWELLING UNIT PER AB 494 & SB 229
- Permit Issued
- Issued on 5/26/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 1/16/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/24/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/26/2019 | JEFFREY TANGONAN |
| Corrections Issued | 12/26/2019 | JEFFREY TANGONAN |
| Building Plans Picked Up | 1/10/2020 | APPLICANT |
| Plan Check Approved | 4/29/2020 | JEFFREY TANGONAN |
| Issued | 5/26/2020 | LADBS |
| CofO in Progress | 11/9/2020 | MICHAEL TEMPLE |
| Permit Finaled | 1/16/2021 | MICHAEL SMITH |
| CofO Issued | 1/16/2021 | MICHAEL SMITH |
| Permit Finaled | 1/16/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 1/10/2020 | MARKOS PEREZ-BRAN |
| Eng Process Fee Ord 176,300 | Cleared | 1/10/2020 | MARKOS PEREZ-BRAN |
| Roof/Waste drainage to street | Cleared | 1/10/2020 | MARKOS PEREZ-BRAN |
| Sewer availability | Cleared | 1/10/2020 | MARKOS PEREZ-BRAN |
| Construction near power lines | Cleared | 3/6/2020 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/6/2020 | Partial Inspection | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 7/24/2020 | Approved | WILLIAM KUEHN |
| METHANE-Barrier | 7/24/2020 | Approved | WILLIAM KUEHN |
| METHANE-Subgrade | 7/24/2020 | Approved | WILLIAM KUEHN |
| Floor/Roof Diaphrgm/Shear Wall | 7/31/2020 | Partial Inspection | WILLIAM KUEHN |
| PLUMBING-Rough | 7/31/2020 | Partial Inspection | WILLIAM KUEHN |
| Floor/Roof Diaphrgm/Shear Wall | 8/13/2020 | Approved | DANIEL DREW |
| BUILDING-Rough-Frame | 8/31/2020 | Conditional Approval | WILLIAM KUEHN |
| Rough-Elec/Plmb/HVAC | 8/31/2020 | Approved | WILLIAM KUEHN |
| Sewer | 8/31/2020 | Approved | WILLIAM KUEHN |
| Underground Mechanical | 8/31/2020 | Partial Inspection | WILLIAM KUEHN |
| Insulation | 9/3/2020 | Approved | DANIEL ORRANTE |
| Interior/Exterior Lathing | 9/3/2020 | Approved | DANIEL ORRANTE |
| Drywall Nailing | 9/9/2020 | Approved | WILLIAM KUEHN |
| Green Building Rough | 9/9/2020 | Approved | WILLIAM KUEHN |
| BUILDING-Rough-Frame | 10/22/2020 | Not Ready for Inspection | MATTHEW NELSON |
| Final | 10/22/2020 | Corrections Issued | MATTHEW NELSON |
| Green Building Final | 10/22/2020 | Not Ready for Inspection | MATTHEW NELSON |
| METHANE-Final | 10/22/2020 | Not Ready for Inspection | MATTHEW NELSON |
| METHANE-Rough | 10/22/2020 | Not Ready for Inspection | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 10/22/2020 | SGSOV Not Ready | MATTHEW NELSON |
| Smoke Detectors | 10/22/2020 | Not Ready for Inspection | MATTHEW NELSON |
| BUILDING-Rough-Frame | 10/30/2020 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 10/30/2020 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 10/30/2020 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 10/30/2020 | Corrections Issued | JENNIFER RABUCHIN |
| METHANE-Final | 10/30/2020 | Approved | JENNIFER RABUCHIN |
| METHANE-Rough | 10/30/2020 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 10/30/2020 | SGSOV Approved | JENNIFER RABUCHIN |
| Smoke Detectors | 10/30/2020 | Approved | JENNIFER RABUCHIN |
| Final | 11/6/2020 | OK to Issue CofO | WILLIAM KUEHN |
| Green Building Final | 11/6/2020 | Approved | WILLIAM KUEHN |