647 S HUDSON AVE 90005

Certificate Information: 647 S HUDSON AVE 90005

Application / Permit
19014-20000-07016
Plan Check / Job No.
B19VN22318
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
4'-9" X 16'-8" ADDITION AND INTERIOR REMODEL TO EXISTING SINGLE FAMILY DWELLING;
Permit Issued
Issued on 2/18/2020
Issuing Office
Valley
Current Status
CofO Issued on 11/17/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/23/2019 APPLICANT
Assigned to Plan Check Engineer 1/2/2020 SELLA BENYAMIN
Corrections Issued 1/7/2020 SELLA BENYAMIN
Green Plans Picked Up 1/7/2020 APPLICANT
Quality Review Completed 1/8/2020 STEVEN KIM
Building Plans Picked Up 1/8/2020 APPLICANT
Plan Check Approved 2/12/2020 SELLA BENYAMIN
Issued 2/18/2020 LADBS
CofO in Progress 1/18/2022 ARTHUR SARGSYAN
Permit Finaled 11/17/2022 DEROLD HAUFF
Permit Finaled 11/17/2022 DEROLD HAUFF
CofO Issued 11/17/2022 DEROLD HAUFF

Permit Application Clearance Information

HPOZ Cleared 1/27/2020 SUKI GERSHENHORN
ZI Cleared 1/27/2020 SUKI GERSHENHORN
Eng Process Fee Ord 176,300 Cleared 1/29/2020 GUILLERMO PETRA
Green Code Cleared 1/29/2020 DAVID MATSON
Roof/Waste drainage to street Cleared 1/29/2020 GUILLERMO PETRA
Sewer availability Cleared 1/29/2020 GUILLERMO PETRA
Specific Plan Cleared 2/3/2020 RUBEN VASQUEZ
ZI Cleared 2/3/2020 RUBEN VASQUEZ

Contact Information

Contractor Ceilbright Services Inc; Lic. No.: 957706-B 9230 W OLYMPIC BLVD      BEVERLY HILLS, CA 90212
Engineer Halvorson,, Keith Raymond; Lic. No.: C29232 20 DUDLEY CT      PLEASANT HILL, CA 94523

Inspector Information

RONNIE MINDANAO, (213) 202-3252 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/6/2020 Partial Approval JUSTIN CURTIS
METHANE-Barrier 4/6/2020 Not Ready for Inspection JUSTIN CURTIS
METHANE-Subgrade 4/6/2020 Not Ready for Inspection JUSTIN CURTIS
PLUMBING-Rough 4/15/2020 Partial Approval CHRIS CHRISTENSEN
Deputy Drilled-In Anchors 4/20/2020 Approved ARTHUR SARGSYAN
Footing/Foundation/Slab 5/12/2020 Approved ARTHUR SARGSYAN
METHANE-Barrier 5/12/2020 Approved ARTHUR SARGSYAN
METHANE-Subgrade 5/12/2020 Approved ARTHUR SARGSYAN
PLUMBING-Rough 5/12/2020 Approved ARTHUR SARGSYAN
Deputy Reinf. Concrete 5/14/2020 Conditional Approval CHRISTOPHER DELLEFIELD
Floor/Roof Diaphrgm/Shear Wall 5/18/2020 No Access for Inspection ARTHUR SARGSYAN
Masonry Wall/Backfill 5/18/2020 No Access for Inspection ARTHUR SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 5/21/2020 Approved ARTHUR SARGSYAN
Masonry Wall/Backfill 5/21/2020 Approved ARTHUR SARGSYAN
Deputy Drilled-In Anchors 6/11/2020 Approved ARTHUR SARGSYAN
Deputy Drilled-In Anchors 7/2/2020 Approved ARTHUR SARGSYAN
Deputy Steel/Welding 7/2/2020 Approved ARTHUR SARGSYAN
BUILDING-Rough-Frame 8/11/2020 Partial Approval ARTHUR SARGSYAN
Green Building Rough 8/11/2020 Not Ready for Inspection ARTHUR SARGSYAN
METHANE-Rough 8/11/2020 Not Ready for Inspection ARTHUR SARGSYAN
Wood Frame 8/31/2020 Not Ready for Inspection ARTHUR SARGSYAN
Wood Frame 9/3/2020 Not Ready for Inspection ARTHUR SARGSYAN
ELECTRICAL-Rough 11/18/2020 Not Ready for Inspection JOSEPH MCGARRY
HVAC-Rough 11/18/2020 Conditional Approval JOSEPH MCGARRY
ELECTRICAL-Rough 11/24/2020 Approved CHRIS CHRISTENSEN
BUILDING-Rough-Frame 12/3/2020 Approved JOSEPH MCGARRY
Green Building Rough 12/3/2020 Approved JOSEPH MCGARRY
HVAC-Rough 12/3/2020 Approved JOSEPH MCGARRY
METHANE-Rough 12/3/2020 Approved JOSEPH MCGARRY
Drywall Nailing 1/21/2021 Conditional Approval JOAQUIN GREENOUGH
Shower Pan 4/7/2021 Approved JOSEPH MCGARRY
Interior/Exterior Lathing 4/29/2021 Partial Approval CHRIS CHRISTENSEN
Insulation 7/12/2021 Approved CHRIS CHRISTENSEN
Gas Test 11/2/2021 Approved ARTHUR SARGSYAN
ELECTRICAL-Final 11/12/2021 Not Ready for Inspection ARTHUR SARGSYAN
Final 12/1/2021 Not Ready for Inspection ARTHUR SARGSYAN
Green Building Final 12/1/2021 Not Ready for Inspection ARTHUR SARGSYAN
SGSOV-Seismic Gas S/O Valve 12/1/2021 SGSOV Not Ready ARTHUR SARGSYAN
Smoke Detectors 12/1/2021 Not Ready for Inspection ARTHUR SARGSYAN
Final 12/10/2021 Corrections Issued ARTHUR SARGSYAN
Green Building Final 12/10/2021 Not Ready for Inspection ARTHUR SARGSYAN
SGSOV-Seismic Gas S/O Valve 12/10/2021 SGSOV Approved ARTHUR SARGSYAN
Smoke Detectors 12/10/2021 Not Ready for Inspection ARTHUR SARGSYAN
Final 1/14/2022 OK to Issue CofO ARTHUR SARGSYAN
Green Building Final 1/14/2022 Approved ARTHUR SARGSYAN
Smoke Detectors 1/14/2022 Approved ARTHUR SARGSYAN
Special/Order Compliance 11/17/2022 Approved RONALD MYRICK