6731 N AMIGO AVE 91335

Certificate Information: 6731 N AMIGO AVE 91335

Application / Permit
19014-20000-07005
Plan Check / Job No.
B19VN22287
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
TWO STORY ADDITION AND CONVERSION OF EXISTING DETACHED ACCESSORY STORAGE BUILDING TO ACCESSORY DWELLING UNIT (ADU).
Permit Issued
Issued on 12/10/2020
Issuing Office
Current Status
CofO Issued on 11/29/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/23/2019 APPLICANT
Assigned to Plan Check Engineer 1/23/2020 JOHN FRANCIA
Corrections Issued 2/7/2020 JOHN FRANCIA
Quality Review Completed 2/10/2020 KEN GILL
Green Plans Picked Up 2/18/2020 APPLICANT
Building Plans Picked Up 2/27/2020 APPLICANT
Applicant returned to address corrections 10/9/2020 JOHN FRANCIA
Applicant returned to address corrections 11/4/2020 JOHN FRANCIA
Plan Check Approved 12/10/2020 JOHN FRANCIA
Issued 12/10/2020 APPLICANT
CofO in Progress 11/21/2021 VINCENT HANLEY
Permit Finaled 11/29/2021 MICHAEL SMITH
CofO Issued 11/29/2021 MICHAEL SMITH
Permit Finaled 11/29/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 6/16/2020 GUILLERMO PETRA
Sewer availability Cleared 8/12/2020 GUILLERMO PETRA
Construction near power lines Cleared 8/14/2020 RIDWAN HARDY
Construction within easement Cleared 8/14/2020 RIDWAN HARDY
Green Code Cleared 8/25/2020 AARON COSTA
Hydrant and Access approval Cleared 9/29/2020 MATTHEW CRAIG
Eng Process Fee Ord 176,300 Cleared 11/5/2020 GUILLERMO PETRA
Roof/Waste drainage to street Cleared 11/13/2020 GUILLERMO PETRA

Contact Information

Contractor Owner-Builder       ,
Engineer Manlangit,, Vicente Balingasa; Lic. No.: C75499 20626 HAYNES ST      WINNETKA, CA 91306

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/2/2021 Not Ready for Inspection VINCENT HANLEY
Pre-Inspection 2/2/2021 Approved VINCENT HANLEY
PLUMBING-Rough 2/9/2021 Partial Approval VINCENT HANLEY
Deputy Drilled-In Anchors 2/16/2021 Partial Approval CHRISTOPHER DELLEFIELD
Footing/Foundation/Slab 2/16/2021 Approved VINCENT HANLEY
BUILDING-Rough-Frame 2/24/2021 Partial Approval VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 2/24/2021 Partial Approval VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 3/5/2021 Partial Approval VINCENT HANLEY
PLUMBING-Rough 3/11/2021 Approved VINCENT HANLEY
ELECTRICAL-Rough 3/31/2021 Approved VINCENT HANLEY
HVAC-Rough 3/31/2021 Approved VINCENT HANLEY
BUILDING-Rough-Frame 4/9/2021 Approved VINCENT HANLEY
Gas Test 4/9/2021 Partial Approval VINCENT HANLEY
Green Building Rough 4/9/2021 Approved VINCENT HANLEY
HVAC-Rough 4/9/2021 Approved VINCENT HANLEY
Insulation 4/9/2021 Approved VINCENT HANLEY
Sewer 4/9/2021 Approved VINCENT HANLEY
Drywall Nailing 4/26/2021 Not Ready for Inspection VINCENT HANLEY
Interior/Exterior Lathing 4/26/2021 Partial Approval VINCENT HANLEY
Pre-Inspection 4/26/2021 Approved VINCENT HANLEY
Sewer 4/26/2021 Approved VINCENT HANLEY
Drywall Nailing 5/12/2021 Approved VINCENT HANLEY
Shower Pan 5/12/2021 Approved VINCENT HANLEY
ELECTRICAL-Final 11/19/2021 Approved VINCENT HANLEY
Final 11/19/2021 OK to Issue CofO VINCENT HANLEY
Gas Test 11/19/2021 Approved VINCENT HANLEY
Green Building Final 11/19/2021 Approved VINCENT HANLEY
HVAC-Final 11/19/2021 Approved VINCENT HANLEY
PLUMBING-Final 11/19/2021 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 11/19/2021 SGSOV Approved VINCENT HANLEY
Smoke Detectors 11/19/2021 Approved VINCENT HANLEY