5411 N NORWICH AVE 91411

Certificate Information: 5411 N NORWICH AVE 91411

Application / Permit
19014-20000-06996
Plan Check / Job No.
B19VN22260
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION AND REMODEL TO (E) SFD , CONVERT (E) ATT GARAGE TO ADU.
Permit Issued
Issued on 3/3/2020
Issuing Office
West Los Angeles
Current Status
CofO Issued on 3/9/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/23/2019 APPLICANT
Assigned to Plan Check Engineer 1/23/2020 JOE VO
Green Plans Picked Up 1/28/2020 APPLICANT
Corrections Issued 1/31/2020 JOE VO
Quality Review Completed 2/3/2020 KEN GILL
Building Plans Picked Up 2/7/2020 APPLICANT
Plan Check Approved 2/28/2020 JOE VO
Issued 3/3/2020 LADBS
CofO in Progress 12/16/2021 JACK KARGODORIAN
Permit Finaled 3/9/2022 MICHAEL SMITH
CofO Issued 3/9/2022 MICHAEL SMITH
Permit Finaled 3/9/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 2/11/2020 ERIK BEASLEY
CPC Cleared 2/13/2020 TERRI OSBORNE
Hydrant and Access approval Cleared 2/20/2020 GEORGE SUCHAND
Sewer availability Cleared 2/20/2020 EMIL KYUPELYAN
Eng Process Fee Ord 176,300 Cleared 2/25/2020 THOMAS LANG
Green Code Cleared 2/25/2020 AARON COSTA
Low Impact Development Cleared 2/25/2020 MITESH PATEL
Roof/Waste drainage to street Cleared 2/25/2020 ERIK BEASLEY

Contact Information

Contractor Owner-Builder       ,
Engineer Chen,, Yeshen Jason; Lic. No.: C40169 20601 ALDA CT      WALNUT, CA 91789

Inspector Information

DAVID ANDERSON, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI
RAUL OLAGI, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/23/2020 Corrections Issued MISAEL ESPARZA
Footing/Foundation/Slab 4/28/2020 Approved BRENDAN LOONEY
Floor/Roof Diaphrgm/Shear Wall 7/2/2020 Partial Inspection WILLIAM KUEHN
Wood Frame 7/2/2020 Not Ready for Inspection WILLIAM KUEHN
Floor/Roof Diaphrgm/Shear Wall 9/15/2020 Corrections Issued DANIEL ORRANTE
HVAC-Rough 9/15/2020 Approved DANIEL ORRANTE
Pre-Inspection 9/15/2020 Partial Inspection DANIEL ORRANTE
ELECTRICAL-Rough 9/28/2020 Corrections Issued CHARLES POWELL
PLUMBING-Rough 9/28/2020 Corrections Issued CHARLES POWELL
Wood Frame 9/28/2020 Not Ready for Inspection CHARLES POWELL
ELECTRICAL-Rough 10/1/2020 Partial Approval CHARLES POWELL
PLUMBING-Rough 10/1/2020 Not Ready for Inspection CHARLES POWELL
Service/Power Release 10/1/2020 Not Ready for Inspection CHARLES POWELL
Wood Frame 10/1/2020 Corrections Issued CHARLES POWELL
BUILDING-Rough-Frame 10/5/2020 Approved WILLIAM KUEHN
ELECTRICAL-Rough 10/5/2020 Approved WILLIAM KUEHN
Gas Test 10/5/2020 Approved WILLIAM KUEHN
PLUMBING-Rough 10/5/2020 Approved WILLIAM KUEHN
Service/Power Release 10/9/2020 Not Ready for Inspection MISAEL ESPARZA
Insulation 12/7/2020 Approved MICHEL ABAJAN
Interior/Exterior Lathing 12/7/2020 Partial Approval MICHEL ABAJAN
Interior/Exterior Lathing 1/15/2021 Partial Approval JENNIFER RABUCHIN
Service/Power Release 1/15/2021 Corrections Issued JENNIFER RABUCHIN
Drywall Nailing 3/3/2021 Partial Approval CHARLES POWELL
Drywall Nailing 3/10/2021 Approved DANIEL ORRANTE
HVAC-Rough 3/15/2021 Not Ready for Inspection CHARLES POWELL
Pre-Inspection 3/15/2021 Partial Approval CHARLES POWELL
Drywall Nailing 3/23/2021 Approved ARTHUR SARGSYAN
Gas Test 3/25/2021 Approved CHARLES POWELL
Interior/Exterior Lathing 5/12/2021 Partial Approval CHARLES POWELL
Shower Pan 5/12/2021 Approved CHARLES POWELL
Shower Pan 5/24/2021 Approved CHARLES POWELL
ELECTRICAL-Final 10/29/2021 Corrections Issued MARK JOHNSON
PLUMBING-Final 10/29/2021 Partial Approval MARK JOHNSON
ELECTRICAL-Final 11/19/2021 Not Ready for Inspection JACK KARGODORIAN
HVAC-Final 11/19/2021 Not Ready for Inspection JACK KARGODORIAN
PLUMBING-Final 11/19/2021 Not Ready for Inspection JACK KARGODORIAN
Service/Power Release 11/19/2021 Corrections Issued JACK KARGODORIAN
ELECTRICAL-Final 11/30/2021 Approved JACK KARGODORIAN
HVAC-Final 11/30/2021 Approved JACK KARGODORIAN
PLUMBING-Final 11/30/2021 Approved JACK KARGODORIAN
Service/Power Release 11/30/2021 Not Required JACK KARGODORIAN
BUILDING-Rough-Frame 12/16/2021 Approved JACK KARGODORIAN
Final 12/16/2021 OK to Issue CofO JACK KARGODORIAN
Green Building Final 12/16/2021 Approved JACK KARGODORIAN
Green Building Rough 12/16/2021 Approved JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 12/16/2021 SGSOV Approved JACK KARGODORIAN
Smoke Detectors 12/16/2021 Approved JACK KARGODORIAN