15218 W BLACKHAWK ST 91345

Certificate Information: 15218 W BLACKHAWK ST 91345

Application / Permit
19014-20000-06988
Plan Check / Job No.
B19VN22236
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED ADDN (25'8'X12'5") TO ENLARGE EX KITCHEN & ADD DINING RM. AND NEW FRONT PORCH.
Permit Issued
Issued on 2/14/2020
Issuing Office
Valley
Current Status
CofO Issued on 9/23/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/23/2019 APPLICANT
Assigned to Plan Check Engineer 12/23/2019 HAYATO TSUCHIYA
Corrections Issued 12/23/2019 HAYATO TSUCHIYA
Issued 2/14/2020 LADBS
CofO in Progress 8/17/2020 JENNIFER RABUCHIN
Permit Finaled 9/23/2020 MICHAEL SMITH
CofO Issued 9/23/2020 MICHAEL SMITH
Permit Finaled 9/23/2020 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 12/23/2019 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 12/23/2019 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,
Engineer Khatchadourian,, Vicken; Lic. No.: S3141 1221 N CEDAR ST      GLENDALE, CA 92107

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/20/2020 Partial Approval JENNIFER RABUCHIN
Footing/Foundation/Slab 3/24/2020 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 4/6/2020 Partial Approval JENNIFER RABUCHIN
ELECTRICAL-Rough 4/6/2020 Partial Approval JENNIFER RABUCHIN
Insulation 4/6/2020 Partial Approval JENNIFER RABUCHIN
BUILDING-Rough-Frame 4/24/2020 Corrections Issued JENNIFER RABUCHIN
Drywall Nailing 4/24/2020 Not Ready for Inspection JENNIFER RABUCHIN
ELECTRICAL-Rough 4/24/2020 Corrections Issued JENNIFER RABUCHIN
Green Building Rough 4/24/2020 Not Ready for Inspection JENNIFER RABUCHIN
HVAC-Rough 4/24/2020 Corrections Issued JENNIFER RABUCHIN
Insulation 4/30/2020 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 4/30/2020 Partial Approval JENNIFER RABUCHIN
Drywall Nailing 5/5/2020 Approved JENNIFER RABUCHIN
Green Building Rough 5/5/2020 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 8/4/2020 Approved MICHAEL TEMPLE
ELECTRICAL-Final 8/4/2020 Corrections Issued MICHAEL TEMPLE
Final 8/4/2020 Corrections Issued MICHAEL TEMPLE
Green Building Final 8/4/2020 Not Ready for Inspection MICHAEL TEMPLE
HVAC-Final 8/4/2020 Corrections Issued MICHAEL TEMPLE
PLUMBING-Final 8/4/2020 Corrections Issued MICHAEL TEMPLE
SGSOV-Seismic Gas S/O Valve 8/4/2020 SGSOV Not Ready MICHAEL TEMPLE
Smoke Detectors 8/4/2020 Approved MICHAEL TEMPLE
Final 8/12/2020 Not Ready for Inspection PIERRE VEGA
Green Building Final 8/12/2020 Not Ready for Inspection PIERRE VEGA
SGSOV-Seismic Gas S/O Valve 8/12/2020 SGSOV Not Ready PIERRE VEGA
Final 8/14/2020 Corrections Issued MICHAEL TEMPLE
Green Building Final 8/14/2020 Approved MICHAEL TEMPLE
SGSOV-Seismic Gas S/O Valve 8/14/2020 SGSOV Approved MICHAEL TEMPLE
ELECTRICAL-Final 8/17/2020 Approved JENNIFER RABUCHIN
Final 8/17/2020 OK to Issue CofO JENNIFER RABUCHIN
HVAC-Final 8/17/2020 Approved JENNIFER RABUCHIN
PLUMBING-Final 8/17/2020 Approved JENNIFER RABUCHIN