5557 N WILLOW CREST AVE 91601

Certificate Information: 5557 N WILLOW CREST AVE 91601

Application / Permit
19014-20000-06964
Plan Check / Job No.
B19VN22187
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
24'-7" x 16'-2" ADDITION TO (E) SINGLE FAMILY DWELLING FOR (2) NEW BEDROOMS. WORK PER WFPP.
Permit Issued
Issued on 3/12/2020
Issuing Office
Valley
Current Status
CofO Issued on 8/28/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/20/2019 APPLICANT
Assigned to Plan Check Engineer 1/7/2020 ROSENDO MEDINA
Corrections Issued 1/15/2020 ROSENDO MEDINA
Quality Review Completed 1/15/2020 CHON CHIO KUO
Building Plans Picked Up 1/17/2020 APPLICANT
Green Plans Picked Up 1/30/2020 APPLICANT
Plan Check Approved 3/9/2020 ROSENDO MEDINA
Issued 3/12/2020 LADBS
CofO in Progress 6/25/2020 RAYMOND KEHOE
CofO Issued 8/28/2020 RONALD MYRICK
Permit Finaled 8/28/2020 RONALD MYRICK

Permit Application Clearance Information

Address approval Cleared 2/14/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 2/14/2020 ADRIAN CASTRO
Roof/Waste drainage to street Cleared 2/14/2020 GUILLERMO PETRA
Sewer availability Cleared 2/14/2020 ADRIAN CASTRO
Green Code Cleared 2/25/2020 AARON COSTA
Redevelopment Project Area Cleared 3/3/2020 DAVID URITA
Tenant Habitability Plan Cleared 3/4/2020 MICHAEL SOTO

Contact Information

Contractor Creative Innovation Developers Inc; Lic. No.: 1035641-B 1812 W BURBANK BLVD STE 1032      BURBANK, CA 91506

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/19/2020 Approved RAYMOND KEHOE
Footing/Foundation/Slab 3/19/2020 Corrections Issued BEAU COLLINS
Footing/Foundation/Slab 4/2/2020 Approved RAYMOND KEHOE
Floor/Roof Diaphrgm/Shear Wall 4/16/2020 Partial Approval RAYMOND KEHOE
BUILDING-Rough-Frame 4/24/2020 Approved RAYMOND KEHOE
ELECTRICAL-Rough 4/24/2020 Approved RAYMOND KEHOE
Green Building Rough 4/24/2020 Approved RAYMOND KEHOE
HVAC-Rough 4/24/2020 Partial Approval RAYMOND KEHOE
PLUMBING-Rough 4/24/2020 Approved RAYMOND KEHOE
Insulation 5/1/2020 Approved RAYMOND KEHOE
Drywall Nailing 5/5/2020 Approved GREGG CUMMINGS
Interior/Exterior Lathing 5/5/2020 Partial Approval GREGG CUMMINGS
HVAC-Rough 5/7/2020 Approved RAYMOND KEHOE
Final 6/3/2020 Not Ready for Inspection THOMAS FINNILA
Green Building Final 6/3/2020 Not Ready for Inspection THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 6/3/2020 SGSOV Not Ready THOMAS FINNILA
Smoke Detectors 6/3/2020 Approved THOMAS FINNILA
Final 6/8/2020 Not Ready for Inspection MISAEL ESPARZA
Green Building Final 6/8/2020 Not Ready for Inspection MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 6/8/2020 SGSOV Approved MISAEL ESPARZA
ELECTRICAL-Final 6/24/2020 Approved RAYMOND KEHOE
Final 6/24/2020 OK to Issue CofO RAYMOND KEHOE
Green Building Final 6/24/2020 Approved RAYMOND KEHOE
HVAC-Final 6/24/2020 Approved RAYMOND KEHOE
PLUMBING-Final 6/24/2020 Approved RAYMOND KEHOE