11810 S ATHENS WAY 90061
Certificate Information: 11810 S ATHENS WAY 90061
- Application / Permit
- 19014-20000-06921
- Plan Check / Job No.
- B19VN22082
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONSTRUCTION OF DETACHED ACCESSORY DWELLING UNIT. CONVENTIONAL FRAMING PER WOOD FRAME PRESCRIPTIVE PROVISIONS.
- Permit Issued
- Issued on 12/29/2020
- Issuing Office
- Current Status
- CofO Issued on 1/3/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/19/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 1/21/2020 | ALBERT SERVIN |
| Corrections Issued | 1/29/2020 | ALBERT SERVIN |
| Quality Review Completed | 1/29/2020 | KEN GILL |
| Green Plans Picked Up | 1/29/2020 | APPLICANT |
| Building Plans Picked Up | 2/3/2020 | APPLICANT |
| Plan Check Approved | 12/18/2020 | ALBERT SERVIN |
| Issued | 12/29/2020 | APPLICANT |
| CofO in Progress | 12/23/2021 | EUGENE CASSIDY |
| Permit Finaled | 1/3/2022 | DEROLD HAUFF |
| CofO Issued | 1/3/2022 | DEROLD HAUFF |
| Permit Finaled | 1/3/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Community Plan Implem. Overlay | Cleared | 2/5/2020 | HELEN JADALI |
| Green Code | Cleared | 8/17/2020 | AARON COSTA |
| Low Impact Development | Cleared | 10/15/2020 | MARTIN FRAGOSO |
| Address approval | Cleared | 10/26/2020 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 10/26/2020 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 10/26/2020 | JEANIE LAM |
| Sewer availability | Cleared | 10/26/2020 | JEANIE LAM |
Contact Information
| Contractor | P S Construction Group Inc; Lic. No.: 940599-B | 12233 CREWE STREET NORWALK, CA 90650 |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/22/2021 | Corrections Issued | EUGENE CASSIDY |
| METHANE-Barrier | 3/22/2021 | Approved | EUGENE CASSIDY |
| METHANE-Subgrade | 3/22/2021 | Approved | EUGENE CASSIDY |
| Footing/Foundation/Slab | 4/5/2021 | Corrections Issued | JOHN KLARIN |
| Footing/Foundation/Slab | 4/15/2021 | Approved | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 4/28/2021 | Partial Approval | EUGENE CASSIDY |
| PLUMBING-Rough | 4/28/2021 | Partial Approval | EUGENE CASSIDY |
| Insulation | 4/30/2021 | Partial Approval | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 7/9/2021 | Corrections Issued | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 7/14/2021 | Partial Approval | EUGENE CASSIDY |
| ELECTRICAL-Rough | 7/23/2021 | Approved | JOHN KLARIN |
| HVAC-Rough | 7/23/2021 | Approved | JOHN KLARIN |
| Interior/Exterior Lathing | 7/23/2021 | Approved | JOHN KLARIN |
| PLUMBING-Rough | 7/23/2021 | Approved | JOHN KLARIN |
| Wood Frame | 7/23/2021 | Approved | JOHN KLARIN |
| Insulation | 7/28/2021 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 7/28/2021 | Partial Approval | EUGENE CASSIDY |
| Drywall Nailing | 8/5/2021 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 8/5/2021 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Rough | 8/26/2021 | Partial Approval | EUGENE CASSIDY |
| Interior/Exterior Lathing | 8/26/2021 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 10/28/2021 | Conditional Approval | JOHN KLARIN |
| Final | 10/28/2021 | Corrections Issued | JOHN KLARIN |
| Green Building Final | 10/28/2021 | Corrections Issued | JOHN KLARIN |
| Green Building Rough | 10/28/2021 | Approved | JOHN KLARIN |
| MERV13>=Final | 10/28/2021 | Corrections Issued | JOHN KLARIN |
| MERV13>=Rough | 10/28/2021 | Corrections Issued | JOHN KLARIN |
| METHANE-Final | 10/28/2021 | Approved | JOHN KLARIN |
| METHANE-Rough | 10/28/2021 | Approved | JOHN KLARIN |
| SGSOV-Seismic Gas S/O Valve | 10/28/2021 | SGSOV Not Ready | JOHN KLARIN |
| Service/Power Release | 10/28/2021 | Not Ready for Inspection | JOHN KLARIN |
| Smoke Detectors | 10/28/2021 | Approved | JOHN KLARIN |
| Verify Sprinkler Sign Off | 10/28/2021 | Approved | JOHN KLARIN |
| BUILDING-Rough-Frame | 11/5/2021 | Approved | EUGENE CASSIDY |
| Final | 11/5/2021 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 11/5/2021 | Approved | EUGENE CASSIDY |
| MERV13>=Final | 11/5/2021 | Approved | EUGENE CASSIDY |
| MERV13>=Rough | 11/5/2021 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 11/5/2021 | SGSOV Not Ready | EUGENE CASSIDY |
| Service/Power Release | 11/5/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| Final | 12/21/2021 | OK to Issue CofO | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 12/21/2021 | SGSOV Approved | EUGENE CASSIDY |
| Service/Power Release | 12/21/2021 | Approved | EUGENE CASSIDY |