5024 E ALMADEN DR 90042

Certificate Information: 5024 E ALMADEN DR 90042

Application / Permit
19014-20000-06919
Plan Check / Job No.
B19VN22078
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
11'6" x 12' 6" ADDITION TO (E) GARAGE AND CONVERSION TO ACCESSORY DWELLING UNIT PER AB 494 AND SB 229
Permit Issued
Issued on 2/7/2020
Issuing Office
Valley
Current Status
CofO Issued on 2/14/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/19/2019 APPLICANT
Assigned to Plan Check Engineer 12/19/2019 PINANK PATEL
Corrections Issued 12/20/2019 PINANK PATEL
Building Plans Picked Up 12/20/2019 APPLICANT
Plan Check Approved 2/7/2020 PINANK PATEL
Issued 2/7/2020 LADBS
CofO in Progress 2/6/2023 CRAIG VAUGHAN
Permit Finaled 2/14/2023 DANIEL ORRANTE
CofO Issued 2/14/2023 DANIEL ORRANTE
Permit Finaled 2/14/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 1/22/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 1/22/2020 ADRIAN CASTRO
Roof/Waste drainage to street Cleared 1/22/2020 ADRIAN CASTRO
Sewer availability Cleared 1/22/2020 ADRIAN CASTRO
Grading Pre-Inspection Cleared 2/7/2020 PINANK PATEL

Contact Information

Contractor Owner-Builder       ,

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/11/2020 Corrections Issued KATHRYN BUTTERWORTH
PLUMBING-Rough 3/11/2020 Corrections Issued KATHRYN BUTTERWORTH
Footing/Foundation/Slab 3/13/2020 Partial Approval ENRIQUE MIRELES
PLUMBING-Rough 3/13/2020 Not Ready for Inspection ENRIQUE MIRELES
Footing/Foundation/Slab 3/19/2020 Approved CRAIG VAUGHAN
BUILDING-Rough-Frame 5/4/2020 Not Ready for Inspection ENRIQUE MIRELES
ELECTRICAL-Rough 5/4/2020 Approved ENRIQUE MIRELES
Green Building Rough 5/4/2020 Approved ENRIQUE MIRELES
HVAC-Rough 5/4/2020 Not Ready for Inspection ENRIQUE MIRELES
PLUMBING-Rough 5/4/2020 Not Ready for Inspection ENRIQUE MIRELES
BUILDING-Rough-Frame 5/6/2020 Approved CRAIG VAUGHAN
Green Building Final 5/6/2020 Not Ready for Inspection CRAIG VAUGHAN
HVAC-Rough 5/6/2020 Approved CRAIG VAUGHAN
PLUMBING-Rough 5/6/2020 Partial Approval CRAIG VAUGHAN
Insulation 5/15/2020 Approved CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 5/15/2020 Partial Approval CHRISTOPHER DELLEFIELD
Shower Pan 5/15/2020 Approved CHRISTOPHER DELLEFIELD
Drywall Nailing 5/21/2020 Approved RUBEN SALAS
Interior/Exterior Lathing 5/21/2020 Approved RUBEN SALAS
Final 7/13/2020 Corrections Issued CRAIG VAUGHAN
Green Building Final 7/13/2020 Corrections Issued CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 7/13/2020 SGSOV Approved CRAIG VAUGHAN
Smoke Detectors 7/13/2020 Approved CRAIG VAUGHAN
Final 7/17/2020 Corrections Issued COREY HUPP
Green Building Final 7/17/2020 Approved COREY HUPP
Sewer 7/17/2020 Approved COREY HUPP
Final 2/3/2023 OK to Issue CofO CRAIG VAUGHAN