1056 S STEARNS DR 90035
Certificate Information: 1056 S STEARNS DR 90035
- Application / Permit
- 19014-20000-06906
- Plan Check / Job No.
- B19VN22053
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL (E) SFD TO RECONFIGURE KITCHEN/BEDROOMS/BATHROOMS, 14' X 20'-6" ADDITON FOR BEDROOM/ BATHROOM EXPANSION, NEW 4' X 13'-4" ATTACHED PATIO COVER. WORK PER ENGINEERING.
- Permit Issued
- Issued on 5/10/2021
- Issuing Office
- Current Status
- CofO Issued on 12/5/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/19/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/19/2019 | ALDOUS CHIC |
| Corrections Issued | 12/20/2019 | ALDOUS CHIC |
| Building Plans Picked Up | 12/23/2019 | APPLICANT |
| Applicant returned to address corrections | 2/24/2020 | ALDOUS CHIC |
| Applicant returned to address corrections | 7/1/2020 | ROSENDO MEDINA |
| Applicant returned to address corrections | 7/17/2020 | ROSENDO MEDINA |
| Plan Check Approved | 7/21/2020 | ROSENDO MEDINA |
| Issued | 5/10/2021 | APPLICANT |
| CofO in Progress | 6/29/2023 | JOSE AVILA |
| CofO Issued | 12/5/2023 | DEROLD HAUFF |
| Permit Finaled | 12/5/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/24/2020 | JOSHUA DIAZ |
| Roof/Waste drainage to street | Cleared | 2/24/2020 | JOSHUA DIAZ |
| HPOZ | Cleared | 7/7/2020 | JONATHAN KAPLAN |
| Miscellaneous | Cleared | 7/7/2020 | JONATHAN KAPLAN |
| ZI | Cleared | 7/7/2020 | JONATHAN KAPLAN |
Contact Information
| Contractor | K S Construction And Design; Lic. No.: 896510-B | 22100 BURBANK BL #226C WOODLAND HILLS, CA 91367 |
| Engineer | Standley,, Craig Erick; Lic. No.: C87675 | 6631 MURIETTA AVE LOS ANGELES, CA 91405 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/12/2021 | Approved | JOAQUIN GREENOUGH |
| Deputy Drilled-In Anchors | 8/25/2021 | Conditional Approval | STUART CHAPMAN |
| Special/Order Compliance | 9/13/2021 | Corrections Issued | CALEB MEISTER |
| Excavation/Setback/Form/Re-Bar | 1/11/2022 | Approved | JOSE AVILA |
| Footing/Foundation/Slab | 1/11/2022 | Approved | JOSE AVILA |
| METHANE-Barrier | 1/11/2022 | Approved | JOSE AVILA |
| METHANE-Subgrade | 1/11/2022 | Approved | JOSE AVILA |
| Deputy Reinf. Concrete | 1/13/2022 | Conditional Approval | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 1/21/2022 | Corrections Issued | JOSE AVILA |
| Insulation | 1/21/2022 | Not Ready for Inspection | JOSE AVILA |
| Wood Frame | 1/27/2022 | Approved | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 3/31/2022 | Corrections Issued | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 5/10/2022 | Partial Approval | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 5/26/2022 | Corrections Issued | JOSE AVILA |
| Deputy Wood Construction | 6/8/2022 | Conditional Approval | JOSE AVILA |
| METHANE-Rough | 6/22/2022 | Approved | JOSE AVILA |
| PLUMBING-Rough | 6/29/2022 | Partial Approval | JOSE AVILA |
| Interior/Exterior Lathing | 7/8/2022 | Approved | JOSE AVILA |
| ELECTRICAL-Rough | 8/11/2022 | Approved | JOSE AVILA |
| Gas Test | 8/11/2022 | Partial Approval | JOSE AVILA |
| HVAC-Rough | 8/11/2022 | Approved | JOSE AVILA |
| PLUMBING-Rough | 8/11/2022 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 10/17/2022 | Approved | JOSE AVILA |
| Green Building Rough | 10/17/2022 | Approved | JOSE AVILA |
| Wood Frame | 10/17/2022 | Approved | JOSE AVILA |
| Insulation | 10/19/2022 | Approved | JOSE AVILA |
| Drywall Nailing | 11/1/2022 | Approved | JOSE AVILA |
| Pre-Inspection | 2/1/2023 | Approved | JOSE AVILA |
| Final | 5/5/2023 | Corrections Issued | JOSE AVILA |
| Green Building Final | 5/5/2023 | Approved | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 5/5/2023 | SGSOV Approved | JOSE AVILA |
| Smoke Detectors | 5/5/2023 | Approved | JOSE AVILA |
| Final | 6/16/2023 | Not Ready for Inspection | JOSE AVILA |
| Final | 6/29/2023 | OK to Issue CofO | JOSE AVILA |