4411 N TEPOCA ROAD 91364

Certificate Information: 4411 N TEPOCA ROAD 91364

Application / Permit
19014-20000-06905
Plan Check / Job No.
B19VN22051
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED (28'-4" X 23'-6") IRREGULAR SHAPED ADDITION TO (E) SFD. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 8/21/2020
Issuing Office
Current Status
CofO Issued on 6/26/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/19/2019 APPLICANT
Green Plans Picked Up 12/31/2019 APPLICANT
Assigned to Plan Check Engineer 1/2/2020 RAPHAEL ROSAS
Corrections Issued 1/2/2020 RAPHAEL ROSAS
Quality Review Completed 1/7/2020 CHON CHIO KUO
Building Plans Picked Up 1/8/2020 APPLICANT
Plan Check Approved 8/7/2020 RAPHAEL ROSAS
Issued 8/21/2020 APPLICANT
CofO in Progress 6/26/2021 MICHAEL PELHAM
CofO Issued 6/26/2021 MICHAEL SMITH
Permit Finaled 6/26/2021 MICHAEL SMITH

Permit Application Clearance Information

Sewer availability Cleared 1/16/2020 APEKSHYA BAJRACHARYA
Miscellaneous Cleared 2/14/2020 DOMINICK ORTIZ
Specific Plan Cleared 2/14/2020 DOMINICK ORTIZ
Specific Plan Cleared 2/14/2020 DOMINICK ORTIZ
ZI Cleared 2/14/2020 DOMINICK ORTIZ
ZI Cleared 2/14/2020 DOMINICK ORTIZ
Construction near power lines Cleared 4/8/2020 RIDWAN HARDY
Disturb/Remove Protected Trees Cleared 4/16/2020 STEPHEN DUPREY
Green Code Cleared 5/14/2020 AARON COSTA
Eng Process Fee Ord 176,300 Cleared 6/18/2020 GUILLERMO PETRA
Roof/Waste drainage to street Cleared 6/18/2020 GUILLERMO PETRA
Grading Pre-Inspection Cleared 8/7/2020 RAPHAEL ROSAS

Contact Information

Contractor Owner-Builder       ,
Engineer Garcia, Zelada, Eddy Alexander; Lic. No.: S6159 17958 LULL ST      RESEDA, CA 91335
Engineer Shubeck,, Christopher Robert; Lic. No.: C66775 23705 VANOWEN ST 101      WEST HILLS, CA 91307

Inspector Information

JOHN HAYES, (818) 774-4302 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Grading Pre-Inspection 8/25/2020 Not Ready for Inspection PAUL CHOPP
Footing/Foundation/Slab 10/2/2020 Corrections Issued HENRY KIM
Footing/Foundation/Slab 10/6/2020 Not Ready for Inspection PAUL CHOPP
Footing/Foundation/Slab 10/15/2020 Corrections Issued PAUL CHOPP
Footing/Foundation/Slab 11/6/2020 Approved DAVID SANDOVAL
BUILDING-Rough-Frame 11/23/2020 Partial Approval VINCENT HANLEY
Insulation 11/23/2020 Partial Approval VINCENT HANLEY
PLUMBING-Rough 11/23/2020 Partial Approval VINCENT HANLEY
Special/Order Compliance 12/10/2020 Approved VINCENT HANLEY
BUILDING-Rough-Frame 12/15/2020 Corrections Issued VINCENT HANLEY
Drywall Nailing 12/15/2020 Not Ready for Inspection VINCENT HANLEY
Final 12/15/2020 Corrections Issued VINCENT HANLEY
Green Building Final 12/15/2020 Not Ready for Inspection VINCENT HANLEY
Rough-Elec/Plmb/HVAC 12/15/2020 Corrections Issued VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 12/15/2020 SGSOV Not Ready VINCENT HANLEY
Smoke Detectors 12/15/2020 Not Ready for Inspection VINCENT HANLEY
Special/Order Compliance 1/5/2021 Approved VINCENT HANLEY
BUILDING-Rough-Frame 3/9/2021 Corrections Issued DAVID SANDOVAL
ELECTRICAL-Rough 3/9/2021 Not Ready for Inspection DAVID SANDOVAL
Floor/Roof Diaphrgm/Shear Wall 3/9/2021 Not Ready for Inspection DAVID SANDOVAL
Green Building Rough 3/9/2021 Not Ready for Inspection DAVID SANDOVAL
PLUMBING-Rough 3/9/2021 Not Ready for Inspection DAVID SANDOVAL
Deputy Wood Construction 3/11/2021 Approved VINCENT HANLEY
BUILDING-Rough-Frame 3/19/2021 Approved DAVID SANDOVAL
ELECTRICAL-Rough 3/19/2021 Corrections Issued DAVID SANDOVAL
Floor/Roof Diaphrgm/Shear Wall 3/19/2021 Approved DAVID SANDOVAL
Green Building Rough 3/19/2021 Not Ready for Inspection DAVID SANDOVAL
PLUMBING-Rough 3/19/2021 Approved DAVID SANDOVAL
ELECTRICAL-Rough 3/27/2021 Approved JEFFREY PARD
ELECTRICAL-Rough 3/27/2021 Off-Hour Fees Due
Floor/Roof Diaphrgm/Shear Wall 3/27/2021 Not Ready for Inspection JEFFREY PARD
Floor/Roof Diaphrgm/Shear Wall 3/27/2021 Off-Hour Fees Due
Interior/Exterior Lathing 3/27/2021 Approved JEFFREY PARD
Interior/Exterior Lathing 3/27/2021 Off-Hour Fees Due
Insulation 4/1/2021 Approved VINCENT HANLEY
Interior/Exterior Lathing 4/1/2021 Approved VINCENT HANLEY
Shower Pan 4/1/2021 Approved VINCENT HANLEY
Drywall Nailing 4/8/2021 Approved VINCENT HANLEY
Green Building Rough 4/8/2021 Approved VINCENT HANLEY
Interior/Exterior Lathing 4/8/2021 Approved VINCENT HANLEY
Final 5/21/2021 Corrections Issued DAVID SANDOVAL
Green Building Final 5/21/2021 Approved DAVID SANDOVAL
SGSOV-Seismic Gas S/O Valve 5/21/2021 SGSOV Approved DAVID SANDOVAL
Smoke Detectors 5/21/2021 Approved DAVID SANDOVAL
Final 6/4/2021 Corrections Issued DAVID SANDOVAL
Final 6/25/2021 Conditional Approval MICHAEL PELHAM