4411 N TEPOCA ROAD 91364
Certificate Information: 4411 N TEPOCA ROAD 91364
- Application / Permit
- 19014-20000-06905
- Plan Check / Job No.
- B19VN22051
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED (28'-4" X 23'-6") IRREGULAR SHAPED ADDITION TO (E) SFD. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 8/21/2020
- Issuing Office
- Current Status
- CofO Issued on 6/26/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/19/2019 | APPLICANT |
| Green Plans Picked Up | 12/31/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 1/2/2020 | RAPHAEL ROSAS |
| Corrections Issued | 1/2/2020 | RAPHAEL ROSAS |
| Quality Review Completed | 1/7/2020 | CHON CHIO KUO |
| Building Plans Picked Up | 1/8/2020 | APPLICANT |
| Plan Check Approved | 8/7/2020 | RAPHAEL ROSAS |
| Issued | 8/21/2020 | APPLICANT |
| CofO in Progress | 6/26/2021 | MICHAEL PELHAM |
| CofO Issued | 6/26/2021 | MICHAEL SMITH |
| Permit Finaled | 6/26/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Sewer availability | Cleared | 1/16/2020 | APEKSHYA BAJRACHARYA |
| Miscellaneous | Cleared | 2/14/2020 | DOMINICK ORTIZ |
| Specific Plan | Cleared | 2/14/2020 | DOMINICK ORTIZ |
| Specific Plan | Cleared | 2/14/2020 | DOMINICK ORTIZ |
| ZI | Cleared | 2/14/2020 | DOMINICK ORTIZ |
| ZI | Cleared | 2/14/2020 | DOMINICK ORTIZ |
| Construction near power lines | Cleared | 4/8/2020 | RIDWAN HARDY |
| Disturb/Remove Protected Trees | Cleared | 4/16/2020 | STEPHEN DUPREY |
| Green Code | Cleared | 5/14/2020 | AARON COSTA |
| Eng Process Fee Ord 176,300 | Cleared | 6/18/2020 | GUILLERMO PETRA |
| Roof/Waste drainage to street | Cleared | 6/18/2020 | GUILLERMO PETRA |
| Grading Pre-Inspection | Cleared | 8/7/2020 | RAPHAEL ROSAS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Garcia, Zelada, Eddy Alexander; Lic. No.: S6159 | 17958 LULL ST RESEDA, CA 91335 |
| Engineer | Shubeck,, Christopher Robert; Lic. No.: C66775 | 23705 VANOWEN ST 101 WEST HILLS, CA 91307 |
Inspector Information
| JOHN HAYES, (818) 774-4302 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Grading Pre-Inspection | 8/25/2020 | Not Ready for Inspection | PAUL CHOPP |
| Footing/Foundation/Slab | 10/2/2020 | Corrections Issued | HENRY KIM |
| Footing/Foundation/Slab | 10/6/2020 | Not Ready for Inspection | PAUL CHOPP |
| Footing/Foundation/Slab | 10/15/2020 | Corrections Issued | PAUL CHOPP |
| Footing/Foundation/Slab | 11/6/2020 | Approved | DAVID SANDOVAL |
| BUILDING-Rough-Frame | 11/23/2020 | Partial Approval | VINCENT HANLEY |
| Insulation | 11/23/2020 | Partial Approval | VINCENT HANLEY |
| PLUMBING-Rough | 11/23/2020 | Partial Approval | VINCENT HANLEY |
| Special/Order Compliance | 12/10/2020 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 12/15/2020 | Corrections Issued | VINCENT HANLEY |
| Drywall Nailing | 12/15/2020 | Not Ready for Inspection | VINCENT HANLEY |
| Final | 12/15/2020 | Corrections Issued | VINCENT HANLEY |
| Green Building Final | 12/15/2020 | Not Ready for Inspection | VINCENT HANLEY |
| Rough-Elec/Plmb/HVAC | 12/15/2020 | Corrections Issued | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 12/15/2020 | SGSOV Not Ready | VINCENT HANLEY |
| Smoke Detectors | 12/15/2020 | Not Ready for Inspection | VINCENT HANLEY |
| Special/Order Compliance | 1/5/2021 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 3/9/2021 | Corrections Issued | DAVID SANDOVAL |
| ELECTRICAL-Rough | 3/9/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| Floor/Roof Diaphrgm/Shear Wall | 3/9/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| Green Building Rough | 3/9/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| PLUMBING-Rough | 3/9/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| Deputy Wood Construction | 3/11/2021 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 3/19/2021 | Approved | DAVID SANDOVAL |
| ELECTRICAL-Rough | 3/19/2021 | Corrections Issued | DAVID SANDOVAL |
| Floor/Roof Diaphrgm/Shear Wall | 3/19/2021 | Approved | DAVID SANDOVAL |
| Green Building Rough | 3/19/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| PLUMBING-Rough | 3/19/2021 | Approved | DAVID SANDOVAL |
| ELECTRICAL-Rough | 3/27/2021 | Approved | JEFFREY PARD |
| ELECTRICAL-Rough | 3/27/2021 | Off-Hour Fees Due | |
| Floor/Roof Diaphrgm/Shear Wall | 3/27/2021 | Not Ready for Inspection | JEFFREY PARD |
| Floor/Roof Diaphrgm/Shear Wall | 3/27/2021 | Off-Hour Fees Due | |
| Interior/Exterior Lathing | 3/27/2021 | Approved | JEFFREY PARD |
| Interior/Exterior Lathing | 3/27/2021 | Off-Hour Fees Due | |
| Insulation | 4/1/2021 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 4/1/2021 | Approved | VINCENT HANLEY |
| Shower Pan | 4/1/2021 | Approved | VINCENT HANLEY |
| Drywall Nailing | 4/8/2021 | Approved | VINCENT HANLEY |
| Green Building Rough | 4/8/2021 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 4/8/2021 | Approved | VINCENT HANLEY |
| Final | 5/21/2021 | Corrections Issued | DAVID SANDOVAL |
| Green Building Final | 5/21/2021 | Approved | DAVID SANDOVAL |
| SGSOV-Seismic Gas S/O Valve | 5/21/2021 | SGSOV Approved | DAVID SANDOVAL |
| Smoke Detectors | 5/21/2021 | Approved | DAVID SANDOVAL |
| Final | 6/4/2021 | Corrections Issued | DAVID SANDOVAL |
| Final | 6/25/2021 | Conditional Approval | MICHAEL PELHAM |