6625 N CANTALOUPE AVE 91405

Certificate Information: 6625 N CANTALOUPE AVE 91405

Application / Permit
19014-20000-06879
Plan Check / Job No.
B19VN22002
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
MAJOR REMODEL - REMOVE (E) SFD W/ 19'-8" PORTION OF WALL TO REMAIN, ADD IRREGULAR 28'-0" X 35'-0", 3'-5" X 11'-7" AND 19'-0" X 31'-8" TO (E) 1-STORY SFD PER ENGINEERING. [NFPA-13D FIRE SPRINKLERS REQUIRED THROUGHOUT]
Permit Issued
Issued on 1/15/2020
Issuing Office
Valley
Current Status
CofO Issued on 10/17/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/18/2019 APPLICANT
Assigned to Plan Check Engineer 12/26/2019 JENNIFER LEE
Corrections Issued 12/30/2019 JENNIFER LEE
Quality Review Completed 12/30/2019 STEVEN KIM
Building Plans Picked Up 12/31/2019 APPLICANT
Plan Check Approved 1/15/2020 JENNIFER LEE
Issued 1/15/2020 LADBS
Green Plans Picked Up 1/15/2020 APPLICANT
CofO in Progress 9/30/2020 WILLIAM KUEHN
CofO Issued 10/17/2020 MICHAEL SMITH
Permit Finaled 10/17/2020 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 12/31/2019 GUILLERMO PETRA
Sewer availability Cleared 12/31/2019 GUILLERMO PETRA
Low Impact Development Cleared 1/9/2020 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 1/9/2020 GABRIEL ROBLES
Green Code Cleared 1/15/2020 MICHAEL AYERS

Contact Information

Contractor Owner-Builder       ,
Engineer Yenjai,, Seree; Lic. No.: C73151 3249 SHADYLAWN DRIVE      DUARTE, CA 91010

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 1/29/2020 Partial Approval MISAEL ESPARZA
Footing/Foundation/Slab 2/5/2020 Approved MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 3/5/2020 Partial Approval MISAEL ESPARZA
Rough-Elec/Plmb/HVAC 3/16/2020 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 3/24/2020 Corrections Issued MISAEL ESPARZA
Green Building Rough 3/24/2020 Not Ready for Inspection MISAEL ESPARZA
Insulation 3/24/2020 Not Ready for Inspection MISAEL ESPARZA
BUILDING-Rough-Frame 3/27/2020 Partial Approval MISAEL ESPARZA
Green Building Rough 3/27/2020 Not Ready for Inspection MISAEL ESPARZA
Insulation 4/1/2020 Approved MISAEL ESPARZA
Interior/Exterior Lathing 4/1/2020 Approved MISAEL ESPARZA
Drywall Nailing 4/8/2020 Approved MISAEL ESPARZA
Green Building Rough 4/8/2020 Approved MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 6/19/2020 SGSOV Not Ready MISAEL ESPARZA
Final 6/25/2020 Not Ready for Inspection MISAEL ESPARZA
BUILDING-Rough-Frame 7/8/2020 Approved MISAEL ESPARZA
Final 7/8/2020 Corrections Issued MISAEL ESPARZA
Green Building Final 7/8/2020 Approved MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 7/8/2020 SGSOV Approved MISAEL ESPARZA
Smoke Detectors 7/8/2020 Approved MISAEL ESPARZA
Final 7/16/2020 No Access for Inspection MISAEL ESPARZA
Final 9/21/2020 No Access for Inspection WILLIAM KUEHN
Final 9/29/2020 OK to Issue CofO WILLIAM KUEHN
Service/Power Release 9/29/2020 Approved WILLIAM KUEHN