6613 N SYLVIA AVE 91335

Certificate Information: 6613 N SYLVIA AVE 91335

Application / Permit
19014-20000-06873
Plan Check / Job No.
B19VN21990
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 21'-5" x 20'-8" DETACHED GARAGE AND ADD IRREGULAR 27'-6" X 36'-10" FOR (N) ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 1/31/2020
Issuing Office
Valley
Current Status
CofO Issued on 1/9/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/18/2019 APPLICANT
Assigned to Plan Check Engineer 12/27/2019 JENNIFER LEE
Corrections Issued 12/27/2019 JENNIFER LEE
Plan Check Approved 1/31/2020 ANGELICA MARTINEZ
Issued 1/31/2020 LADBS
CofO in Progress 1/5/2021 VINCENT HANLEY
CofO Issued 1/9/2021 MICHAEL SMITH
Permit Finaled 1/9/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 1/15/2020 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 1/15/2020 GUILLERMO PETRA
Permit Cleared 1/15/2020 GUILLERMO PETRA
Sewer availability Cleared 1/15/2020 GUILLERMO PETRA
Low Impact Development Cleared 1/16/2020 SARAH YOUSSEF
Trees in Parkway Cleared 1/29/2020 ADRIAN SANCHEZ
Roof/Waste drainage to street Cleared 1/31/2020 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 1/31/2020 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,
Engineer Yenjai,, Seree; Lic. No.: C73151 3249 SHADYLAWN DRIVE      DUARTE, CA 91010

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/10/2020 Not Ready for Inspection JOHN KIDWELL
Underground Mechanical 2/10/2020 Partial Approval JOHN KIDWELL
Footing/Foundation/Slab 2/18/2020 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 2/21/2020 Approved VINCENT HANLEY
Wood Frame 2/21/2020 Partial Approval VINCENT HANLEY
BUILDING-Rough-Frame 2/26/2020 Approved VINCENT HANLEY
Green Building Rough 2/26/2020 Not Ready for Inspection VINCENT HANLEY
Rough-Elec/Plmb/HVAC 2/26/2020 Approved VINCENT HANLEY
Sewer 2/26/2020 Approved VINCENT HANLEY
Underground Mechanical 2/26/2020 Approved VINCENT HANLEY
Gas Test 2/27/2020 Partial Approval VINCENT HANLEY
Interior/Exterior Lathing 2/27/2020 Partial Approval VINCENT HANLEY
BUILDING-Rough-Frame 3/3/2020 Approved VINCENT HANLEY
Drywall Nailing 3/3/2020 Approved VINCENT HANLEY
Green Building Rough 3/3/2020 Approved VINCENT HANLEY
Interior/Exterior Lathing 3/3/2020 Approved VINCENT HANLEY
Shower Pan 3/3/2020 Approved VINCENT HANLEY
Green Building Rough 3/4/2020 Approved VINCENT HANLEY
Interior/Exterior Lathing 3/4/2020 Approved VINCENT HANLEY
Shower Pan 3/4/2020 Approved VINCENT HANLEY
Final 4/8/2020 Corrections Issued VINCENT HANLEY
Green Building Final 4/8/2020 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 4/8/2020 SGSOV Approved VINCENT HANLEY
Service/Power Release 4/8/2020 Approved VINCENT HANLEY
Smoke Detectors 4/8/2020 Approved VINCENT HANLEY
ELECTRICAL-Final 1/5/2021 Approved VINCENT HANLEY
Final 1/5/2021 OK to Issue CofO VINCENT HANLEY
HVAC-Final 1/5/2021 Approved VINCENT HANLEY
PLUMBING-Final 1/5/2021 Approved VINCENT HANLEY