20418 W SCHOENBORN ST 91306
Certificate Information: 20418 W SCHOENBORN ST 91306
- Application / Permit
- 19014-20000-06850
- Plan Check / Job No.
- B19VN21915
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 24'-0" X 20'-8" ADDITION TO & CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER AB 494 AND SB 229
- Permit Issued
- Issued on 1/24/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 6/5/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/18/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/18/2019 | JEROME MAGAT PALMA |
| Corrections Issued | 12/18/2019 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 12/24/2019 | APPLICANT |
| Plan Check Approved | 1/22/2020 | JEROME MAGAT PALMA |
| Issued | 1/24/2020 | LADBS |
| CofO in Progress | 6/4/2020 | DAVID STEPANYAN |
| CofO Issued | 6/5/2020 | JOHN JANSON |
| Permit Finaled | 6/5/2020 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 1/16/2020 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 1/16/2020 | JOHN TRIANTAFYLLOS |
| Roof/Waste drainage to street | Cleared | 1/16/2020 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 1/16/2020 | JOHN TRIANTAFYLLOS |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 2/6/2020 | Partial Approval | PETER FOLLING |
| Footing/Foundation/Slab | 2/12/2020 | Corrections Issued | PETER FOLLING |
| Footing/Foundation/Slab | 2/19/2020 | Approved | PETER FOLLING |
| Floor/Roof Diaphrgm/Shear Wall | 3/2/2020 | Partial Inspection | MICHAEL TEMPLE |
| BUILDING-Rough-Frame | 3/23/2020 | Not Ready for Inspection | DAVID STEPANYAN |
| ELECTRICAL-Rough | 3/23/2020 | Approved | DAVID STEPANYAN |
| Green Building Rough | 3/23/2020 | Approved | DAVID STEPANYAN |
| HVAC-Rough | 3/23/2020 | Approved | DAVID STEPANYAN |
| PLUMBING-Rough | 3/23/2020 | Approved | DAVID STEPANYAN |
| Rough-Elec/Plmb/HVAC | 3/23/2020 | Not Ready for Inspection | DAVID STEPANYAN |
| Interior/Exterior Lathing | 3/26/2020 | Approved | DAVID STEPANYAN |
| Shower Pan | 3/26/2020 | Approved | DAVID STEPANYAN |
| Drywall Nailing | 3/31/2020 | Approved | JOHN KIDWELL |
| BUILDING-Rough-Frame | 5/12/2020 | Approved | DAVID STEPANYAN |
| ELECTRICAL-Final | 5/12/2020 | Approved | DAVID STEPANYAN |
| Final | 5/12/2020 | Not Ready for Inspection | DAVID STEPANYAN |
| Gas Test | 5/12/2020 | Partial Approval | DAVID STEPANYAN |
| Green Building Final | 5/12/2020 | Approved | DAVID STEPANYAN |
| Green Building Rough | 5/12/2020 | Approved | DAVID STEPANYAN |
| HVAC-Final | 5/12/2020 | Approved | DAVID STEPANYAN |
| PLUMBING-Final | 5/12/2020 | Corrections Issued | DAVID STEPANYAN |
| SGSOV-Seismic Gas S/O Valve | 5/12/2020 | SGSOV Not Ready | DAVID STEPANYAN |
| Smoke Detectors | 5/12/2020 | Approved | DAVID STEPANYAN |
| Final | 6/4/2020 | OK to Issue CofO | DAVID STEPANYAN |
| PLUMBING-Final | 6/4/2020 | Approved | DAVID STEPANYAN |
| SGSOV-Seismic Gas S/O Valve | 6/4/2020 | SGSOV Approved | DAVID STEPANYAN |