20418 W SCHOENBORN ST 91306

Certificate Information: 20418 W SCHOENBORN ST 91306

Application / Permit
19014-20000-06850
Plan Check / Job No.
B19VN21915
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
24'-0" X 20'-8" ADDITION TO & CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER AB 494 AND SB 229
Permit Issued
Issued on 1/24/2020
Issuing Office
Valley
Current Status
CofO Issued on 6/5/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/18/2019 APPLICANT
Assigned to Plan Check Engineer 12/18/2019 JEROME MAGAT PALMA
Corrections Issued 12/18/2019 JEROME MAGAT PALMA
Building Plans Picked Up 12/24/2019 APPLICANT
Plan Check Approved 1/22/2020 JEROME MAGAT PALMA
Issued 1/24/2020 LADBS
CofO in Progress 6/4/2020 DAVID STEPANYAN
CofO Issued 6/5/2020 JOHN JANSON
Permit Finaled 6/5/2020 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 1/16/2020 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 1/16/2020 JOHN TRIANTAFYLLOS
Roof/Waste drainage to street Cleared 1/16/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 1/16/2020 JOHN TRIANTAFYLLOS

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 2/6/2020 Partial Approval PETER FOLLING
Footing/Foundation/Slab 2/12/2020 Corrections Issued PETER FOLLING
Footing/Foundation/Slab 2/19/2020 Approved PETER FOLLING
Floor/Roof Diaphrgm/Shear Wall 3/2/2020 Partial Inspection MICHAEL TEMPLE
BUILDING-Rough-Frame 3/23/2020 Not Ready for Inspection DAVID STEPANYAN
ELECTRICAL-Rough 3/23/2020 Approved DAVID STEPANYAN
Green Building Rough 3/23/2020 Approved DAVID STEPANYAN
HVAC-Rough 3/23/2020 Approved DAVID STEPANYAN
PLUMBING-Rough 3/23/2020 Approved DAVID STEPANYAN
Rough-Elec/Plmb/HVAC 3/23/2020 Not Ready for Inspection DAVID STEPANYAN
Interior/Exterior Lathing 3/26/2020 Approved DAVID STEPANYAN
Shower Pan 3/26/2020 Approved DAVID STEPANYAN
Drywall Nailing 3/31/2020 Approved JOHN KIDWELL
BUILDING-Rough-Frame 5/12/2020 Approved DAVID STEPANYAN
ELECTRICAL-Final 5/12/2020 Approved DAVID STEPANYAN
Final 5/12/2020 Not Ready for Inspection DAVID STEPANYAN
Gas Test 5/12/2020 Partial Approval DAVID STEPANYAN
Green Building Final 5/12/2020 Approved DAVID STEPANYAN
Green Building Rough 5/12/2020 Approved DAVID STEPANYAN
HVAC-Final 5/12/2020 Approved DAVID STEPANYAN
PLUMBING-Final 5/12/2020 Corrections Issued DAVID STEPANYAN
SGSOV-Seismic Gas S/O Valve 5/12/2020 SGSOV Not Ready DAVID STEPANYAN
Smoke Detectors 5/12/2020 Approved DAVID STEPANYAN
Final 6/4/2020 OK to Issue CofO DAVID STEPANYAN
PLUMBING-Final 6/4/2020 Approved DAVID STEPANYAN
SGSOV-Seismic Gas S/O Valve 6/4/2020 SGSOV Approved DAVID STEPANYAN