202 N JOY ST 90042
Certificate Information: 202 N JOY ST 90042
- Application / Permit
- 19014-20000-06842
- Plan Check / Job No.
- B19VN21888
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) GARAGE & ADD 2-STORY FOR (N) ACCESSORY DWELLING UNIT PER LAMC 12.22A33(c)(d)
- Permit Issued
- Issued on 5/18/2023
- Issuing Office
- Metro
- Current Status
- Issued on 5/18/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/17/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 1/9/2020 | TROY DEGUZMAN |
| Corrections Issued | 1/16/2020 | TROY DEGUZMAN |
| Green Plans Picked Up | 1/24/2020 | APPLICANT |
| Quality Review Completed | 2/3/2020 | CHON CHIO KUO |
| Building Plans Picked Up | 2/4/2020 | APPLICANT |
| Applicant returned to address corrections | 2/23/2023 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 3/10/2023 | NILOOFAR MEHRAIN |
| Plan Check Approved | 3/10/2023 | NILOOFAR MEHRAIN |
| Issued | 5/18/2023 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 5/19/2021 | WALLIE JONG |
| Address approval | Cleared | 6/17/2021 | WALLIE JONG |
| Sewer availability | Cleared | 7/2/2021 | WALLIE JONG |
| Hydrant and Access approval | Cleared | 9/4/2021 | ROBERT DUFF |
| CPC | Cleared | 2/4/2022 | PABLO ESTRADA |
| HPOZ | Cleared | 2/10/2022 | KATIE DEBIASE |
| ZI | Cleared | 2/10/2022 | KATIE DEBIASE |
| Low Impact Development | Cleared | 8/5/2022 | CHRIS VONG |
| Roof/Waste drainage to street | Cleared | 10/25/2022 | TREVOR QUAN |
| Grading Pre-Inspection | Cleared | 2/23/2023 | TROY DEGUZMAN |
| Green Code | Cleared | 2/23/2023 | TROY DEGUZMAN |
Contact Information
| Contractor | A C Enterprises; Lic. No.: 610341-B | 3857 DRYSDALE LOS ANGELES, CA 90032 |
| Engineer | Margarita, Evans; Lic. No.: C88998 | 14428 HAMLIN ST VAN NUYS, CA 91401 |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Grading Pre-Inspection | 1/23/2024 | No Access for Inspection | OSVALDO PARAMO |
| Pre-Inspection | 1/23/2024 | No Access for Inspection | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 12/17/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| Piling/Pier/Caisson | 12/17/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 12/20/2024 | Partial Inspection | OSVALDO PARAMO |
| Piling/Pier/Caisson | 12/20/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 2/27/2025 | Partial Approval | ALIZAH MAYAGOITIA |
| Excavation/Setback/Form/Re-Bar | 3/20/2025 | Partial Approval | ALIZAH MAYAGOITIA |
| Excavation/Setback/Form/Re-Bar | 5/14/2025 | Approved | ALIZAH MAYAGOITIA |
| Deputy Reinf. Concrete | 5/15/2025 | Conditional Approval | ALIZAH MAYAGOITIA |
| Wood Frame | 8/29/2025 | Partial Approval | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 9/30/2025 | Partial Approval | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 10/30/2025 | Partial Approval | ALIZAH MAYAGOITIA |
| Green Building Rough | 10/30/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 12/9/2025 | Corrections Issued | DAVID WILLIAMS |
| Pre-Inspection | 12/9/2025 | Partial Approval | DAVID WILLIAMS |
| Interior/Exterior Lathing | 12/11/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 1/9/2026 | Corrections Issued | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 1/9/2026 | Approved | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 2/24/2026 | Approved | DAVID WILLIAMS |
| HVAC-Rough | 2/25/2026 | Corrections Issued | ALIZAH MAYAGOITIA |
| Gas Test | 3/31/2026 | Partial Approval | ALIZAH MAYAGOITIA |
| Sewer | 3/31/2026 | Approved | ALIZAH MAYAGOITIA |
| Underground Mechanical | 3/31/2026 | Approved | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 4/16/2026 | Corrections Issued | ALIZAH MAYAGOITIA |
| Green Building Rough | 4/16/2026 | Approved | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 4/16/2026 | Approved | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 5/1/2026 | Approved | ALIZAH MAYAGOITIA |
| Insulation | 5/1/2026 | Corrections Issued | ALIZAH MAYAGOITIA |
| Insulation | 5/13/2026 | Approved | OSVALDO PARAMO |
| Special/Order Compliance | 5/13/2026 | Not Ready for Inspection | GEM DE OCAMPO |
| Drywall Nailing | 5/27/2026 | Approved | GEM DE OCAMPO |