15570 W OTSEGO ST 91436

Certificate Information: 15570 W OTSEGO ST 91436

Application / Permit
19014-20000-06839
Plan Check / Job No.
B19VN21885
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
29'-0"X 52'-0" IRREGULAR SHAPE 2ND FLOOR ADDITION & ADD 41 SF ON 1ST FLOOR & ADD 255 SF PATIO COVER ON BACKYARD, REMODEL (E) SINGLE FAMILY DWELLING. ALL WORK PER ENGINEERING. PROVIDE FIRE SPRINKLER NFPA13D.
Permit Issued
Issued on 2/21/2020
Issuing Office
West Los Angeles
Current Status
CofO Issued on 4/28/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/17/2019 APPLICANT
Assigned to Plan Check Engineer 1/9/2020 PARISA ZAHABI
Corrections Issued 1/16/2020 PARISA ZAHABI
Green Plans Picked Up 1/22/2020 APPLICANT
Quality Review Completed 1/27/2020 OMID HEDAYAT
Building Plans Picked Up 1/28/2020 APPLICANT
Applicant returned to address corrections 2/13/2020 PARISA ZAHABI
Applicant returned to address corrections 2/20/2020 PARISA ZAHABI
Plan Check Approved 2/21/2020 PARISA ZAHABI
Issued 2/21/2020 LADBS
CofO in Progress 3/30/2022 WILL MCCONNAUGHY
CofO Issued 4/28/2022 MICHAEL SMITH
Permit Finaled 4/28/2022 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 2/6/2020 APEKSHYA BAJRACHARYA
Hydrant and Access approval Cleared 2/6/2020 GEORGE SUCHAND
Low Impact Development Cleared 2/6/2020 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 2/6/2020 APEKSHYA BAJRACHARYA
Sewer availability Cleared 2/6/2020 APEKSHYA BAJRACHARYA
Green Code Cleared 2/12/2020 PARISA ZAHABI

Contact Information

Contractor Orange Innovation Inc; Lic. No.: 832810-B 16478 BEACH BLVD #294      WESTMINSTER, CA 92683
Engineer Chu,, Tien Manh; Lic. No.: C72324 9542 PACIFIC AVE      ANAHEIM, CA 92804

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/17/2020 Not Ready for Inspection RONALD COWAN
Deputy Drilled-In Anchors 6/18/2020 Approved RONALD COWAN
Excavation/Setback/Form/Re-Bar 6/18/2020 Approved RONALD COWAN
Floor/Roof Diaphrgm/Shear Wall 7/7/2020 Partial Approval RONALD COWAN
Deputy Wood Construction 7/29/2020 Approved RONALD COWAN
Floor/Roof Diaphrgm/Shear Wall 8/3/2020 Corrections Issued RONALD COWAN
BUILDING-Rough-Frame 8/20/2020 Approved RONALD COWAN
ELECTRICAL-Rough 8/20/2020 Approved RONALD COWAN
Green Building Rough 8/20/2020 Approved RONALD COWAN
HVAC-Rough 8/20/2020 Approved RONALD COWAN
MERV13>=Rough 8/20/2020 Approved RONALD COWAN
PLUMBING-Rough 8/20/2020 Approved RONALD COWAN
Drywall Nailing 9/8/2020 Approved RONALD COWAN
Interior/Exterior Lathing 9/30/2020 Approved RONALD COWAN
Shower Pan 9/30/2020 Approved RONALD COWAN
Final 2/18/2021 Corrections Issued RONALD COWAN
Footing/Foundation/Slab 2/18/2021 Approved RONALD COWAN
Green Building Final 2/18/2021 Corrections Issued RONALD COWAN
MERV13>=Final 2/18/2021 Not Ready for Inspection RONALD COWAN
SGSOV-Seismic Gas S/O Valve 2/18/2021 SGSOV Approved RONALD COWAN
Smoke Detectors 2/18/2021 Approved RONALD COWAN
Final 1/12/2022 Not Ready for Inspection DAVID SANDOVAL
Green Building Final 1/12/2022 Partial Approval DAVID SANDOVAL
MERV13>=Final 1/12/2022 Partial Approval DAVID SANDOVAL
Final 3/3/2022 No Access for Inspection VINCENT HANLEY
Green Building Final 3/3/2022 No Access for Inspection VINCENT HANLEY
MERV13>=Final 3/3/2022 No Access for Inspection VINCENT HANLEY
Final 3/29/2022 OK to Issue CofO VINCENT HANLEY
Green Building Final 3/29/2022 Approved VINCENT HANLEY
MERV13>=Final 3/29/2022 Approved VINCENT HANLEY