17312 W BALLINGER ST 91325

Certificate Information: 17312 W BALLINGER ST 91325

Application / Permit
19014-20000-06835
Plan Check / Job No.
B19VN21875
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED (8' X 17'-2") IRREGULAR SHAPED ADDITION & REMODEL TO (E) SFD. ALL WORK PER ENGINEERING. NFPA 13D FIRE SPRINKLERS THROUGHOUT.
Permit Issued
Issued on 2/21/2020
Issuing Office
Valley
Current Status
Issued on 2/21/2020
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/17/2019 APPLICANT
Assigned to Plan Check Engineer 12/26/2019 RAPHAEL ROSAS
Corrections Issued 12/28/2019 RAPHAEL ROSAS
Quality Review Completed 12/30/2019 CHON CHIO KUO
Building Plans Picked Up 12/31/2019 APPLICANT
Green Plans Picked Up 1/3/2020 APPLICANT
Applicant returned to address corrections 2/13/2020 RAPHAEL ROSAS
Plan Check Approved 2/21/2020 RAPHAEL ROSAS
Issued 2/21/2020 LADBS

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 1/30/2020 JOHN LIN
Eng Process Fee Ord 176,300 Cleared 1/30/2020 JOHN LIN
Grading Pre-Inspection Cleared 1/30/2020 MANUEL TEJADA
Sewer availability Cleared 1/30/2020 JOHN LIN
Green Code Cleared 2/3/2020 DAVID MATSON
Low Impact Development Cleared 2/20/2020 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 2/21/2020 APEKSHYA BAJRACHARYA

Contact Information

Architect Belak-Berger,, Charles Peter; Lic. No.: C13657 521 W. ROSECRANS AVE.      GARDENA, CA 902481514
Contractor Raw Development Inc; Lic. No.: 989611-B 4859 W SLAUSON AVENUE #377      LOS ANGELES, CA 90056

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/20/2020 Approved MARK JOHNSON
Pre-Inspection 7/2/2020 Approved MARK JOHNSON
Underground Mechanical 7/17/2020 Approved MARK JOHNSON
Floor/Roof Diaphrgm/Shear Wall 7/31/2020 Partial Approval MARK JOHNSON
PLUMBING-Rough 7/31/2020 Approved MARK JOHNSON
Deputy Wood Construction 8/12/2020 No Access for Inspection MARK JOHNSON
ELECTRICAL-Rough 8/19/2020 Corrections Issued MICHAEL TEMPLE
HVAC-Rough 8/19/2020 Corrections Issued MICHAEL TEMPLE
BUILDING-Rough-Frame 9/25/2020 Corrections Issued MARK JOHNSON
ELECTRICAL-Rough 9/25/2020 Approved MARK JOHNSON
Green Building Rough 9/25/2020 Approved MARK JOHNSON
HVAC-Rough 9/25/2020 Approved MARK JOHNSON
Interior/Exterior Lathing 1/6/2021 Approved MARK JOHNSON
BUILDING-Rough-Frame 1/8/2021 Approved MARK JOHNSON
Insulation 2/4/2021 Approved MARK JOHNSON
Shower Pan 2/4/2021 Approved MARK JOHNSON
Drywall Nailing 2/25/2021 Approved MARK JOHNSON
Interior/Exterior Lathing 2/25/2021 Approved MARK JOHNSON
Gas Test 2/15/2022 Approved JESUS RODRIGUEZ