5207 N HARTWICK ST 90041
Certificate Information: 5207 N HARTWICK ST 90041
- Application / Permit
- 19014-20000-06821
- Plan Check / Job No.
- B19VN21834
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADD TO & CONVERT STORAGE/ CARPORT TO ACCESSORY DWELLING UNIT PER AB 494 & SB 229
- Permit Issued
- Issued on 6/17/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 5/7/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/17/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/17/2019 | PINANK PATEL |
| Corrections Issued | 12/17/2019 | PINANK PATEL |
| Plan Check Approved | 3/12/2020 | GEORGE ALVAREZ |
| Issued | 6/17/2020 | LADBS |
| Building Plans Picked Up | 6/17/2020 | APPLICANT |
| CofO in Progress | 5/4/2022 | CRAIG VAUGHAN |
| Permit Finaled | 5/7/2022 | DEROLD HAUFF |
| CofO Issued | 5/7/2022 | DEROLD HAUFF |
| Permit Finaled | 5/7/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 1/8/2020 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 1/8/2020 | LEE GUILBEAUX |
| Miscellaneous | Cleared | 1/8/2020 | LEE GUILBEAUX |
| Sewer availability | Cleared | 1/8/2020 | LEE GUILBEAUX |
| Grading Pre-Inspection | Cleared | 1/16/2020 | BRIAN MILLER |
| Construction near power lines | Cleared | 3/12/2020 | OSCAR CASTRO |
| GPI Written Notices | Cleared | 3/12/2020 | PINANK PATEL |
| Low Impact Development | Cleared | 3/12/2020 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 3/12/2020 | THOMAS LANG |
Contact Information
| Architect | Salcedo,, Glen Charles; Lic. No.: C33143 | P O BOX 14202 VAN NUYS, CA 91409 |
| Contractor | Owner-Builder | , |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 7/9/2020 | Partial Approval | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 8/4/2020 | Not Ready for Inspection | CRAIG VAUGHAN |
| Deputy Drilled-In Anchors | 8/17/2020 | Conditional Approval | CHRISTOPHER DELLEFIELD |
| Footing/Foundation/Slab | 8/19/2020 | Corrections Issued | COREY HUPP |
| Footing/Foundation/Slab | 8/31/2020 | Approved | CRAIG VAUGHAN |
| Special/Order Compliance | 8/31/2020 | Partial Approval | RUBEN SALAS |
| Floor/Roof Diaphrgm/Shear Wall | 12/11/2020 | No Access for Inspection | CRAIG VAUGHAN |
| Wood Frame | 12/11/2020 | Not Ready for Inspection | CRAIG VAUGHAN |
| Special/Order Compliance | 1/7/2021 | Partial Approval | CRAIG VAUGHAN |
| Wood Frame | 1/11/2021 | Partial Approval | CRAIG VAUGHAN |
| Underground Mechanical | 2/12/2021 | Partial Approval | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/25/2021 | Partial Approval | CRAIG VAUGHAN |
| Special/Order Compliance | 2/25/2021 | Partial Inspection | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 4/15/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| HVAC-Rough | 4/15/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 4/15/2021 | Approved | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 6/25/2021 | Corrections Issued | CRAIG VAUGHAN |
| HVAC-Rough | 6/25/2021 | Corrections Issued | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 6/30/2021 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 6/30/2021 | Approved | CRAIG VAUGHAN |
| Green Building Rough | 6/30/2021 | Approved | CRAIG VAUGHAN |
| HVAC-Rough | 6/30/2021 | Partial Approval | CRAIG VAUGHAN |
| Insulation | 7/7/2021 | Approved | WILLIAM WREN |
| Drywall Nailing | 8/16/2021 | Approved | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 9/28/2021 | Approved | CRAIG VAUGHAN |
| Shower Pan | 9/28/2021 | Approved | CRAIG VAUGHAN |
| Final | 2/16/2022 | Corrections Issued | CRAIG VAUGHAN |
| Gas Test | 2/16/2022 | Approved | CRAIG VAUGHAN |
| Green Building Final | 2/16/2022 | Approved | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 2/16/2022 | SGSOV Not Ready | CRAIG VAUGHAN |
| Smoke Detectors | 2/16/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| Special/Order Compliance | 2/16/2022 | Partial Inspection | AMY COLIN |
| Final | 4/20/2022 | Corrections Issued | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 4/20/2022 | SGSOV Not Ready | CRAIG VAUGHAN |
| Smoke Detectors | 4/20/2022 | Approved | CRAIG VAUGHAN |
| Final | 4/25/2022 | Conditional Approval | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 4/25/2022 | SGSOV Approved | CRAIG VAUGHAN |
| ELECTRICAL-Final | 5/3/2022 | Approved | CRAIG VAUGHAN |
| Final | 5/3/2022 | OK to Issue CofO | CRAIG VAUGHAN |