13838 W LANARK ST 91402

Certificate Information: 13838 W LANARK ST 91402

Application / Permit
19014-20000-06816
Plan Check / Job No.
B19VN21812
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 18'-4" X 20'-2" DETACHED GARAGE AND ADD 16'-11" X 18'-0" FOR (N) ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. ALL WORK PER WFPP.
Permit Issued
Issued on 7/21/2020
Issuing Office
Current Status
CofO Issued on 12/4/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/17/2019 APPLICANT
Assigned to Plan Check Engineer 12/19/2019 JENNIFER LEE
Corrections Issued 12/19/2019 JENNIFER LEE
Plan Check Approved 5/14/2020 JEROME MAGAT PALMA
Issued 7/21/2020 APPLICANT
CofO in Progress 10/10/2023 LUCIANO GAUNA
Permit Finaled 12/4/2023 DAVID JAMES
CofO Issued 12/4/2023 DAVID JAMES
Permit Finaled 12/4/2023 DAVID JAMES

Permit Application Clearance Information

Address approval Cleared 3/2/2020 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 3/2/2020 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 3/2/2020 LEE GUILBEAUX
Sewer availability Cleared 3/2/2020 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 3/2/2020 LEE GUILBEAUX
Public Works-Sewers Cleared 3/2/2020 LEE GUILBEAUX
Construction near power lines Cleared 5/2/2020 RIDWAN HARDY
Construction within easement Cleared 5/2/2020 RIDWAN HARDY

Contact Information

Contractor Munoz Carlos Enrique; Lic. No.: 908224-B 2027 PHILLIPPI STREET      SAN FERNANDO, CA 91340

Inspector Information

ARA SINANIAN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
HASANTHA WEERASEKARA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
SCOTT SHUSTER, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOEL GUARDADO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARIYA MIHALEVA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOSE RUBIO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
DAVID JAMES, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
DAVID HICKMAN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOHN HAMILTON, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOHN STEPHENS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
PIERRE VEGA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARK VAN SLOOTEN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MICKEY YAMASHITA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
KIM BEAUCHAMP, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARK DOVICO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
THOMAS WOODS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
RAUL VASQUEZ, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
AUGUSTUS ALBAS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
LEO MILBAUER, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARIO CUEVAS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 8/3/2020 Not Ready for Inspection PIERRE VEGA
Underground Mechanical 8/3/2020 Corrections Issued PIERRE VEGA
Sewer 8/13/2020 Approved MICKEY YAMASHITA
Underground Mechanical 8/13/2020 Not Ready for Inspection MICKEY YAMASHITA
Deputy Drilled-In Anchors 10/13/2021 No Access for Inspection DAVID JAMES
Footing/Foundation/Slab 10/13/2021 Corrections Issued MICKEY YAMASHITA
PLUMBING-Rough 10/13/2021 Corrections Issued MICKEY YAMASHITA
Footing/Foundation/Slab 10/14/2021 Approved MICKEY YAMASHITA
PLUMBING-Rough 10/14/2021 Partial Approval MICKEY YAMASHITA
BUILDING-Rough-Frame 1/26/2022 Corrections Issued MICKEY YAMASHITA
Floor/Roof Diaphrgm/Shear Wall 1/26/2022 Partial Approval MICKEY YAMASHITA
Floor/Roof Diaphrgm/Shear Wall 2/17/2022 Corrections Issued MICKEY YAMASHITA
ELECTRICAL-Rough 5/10/2022 Not Ready for Inspection MICKEY YAMASHITA
HVAC-Rough 5/10/2022 Not Ready for Inspection MICKEY YAMASHITA
Interior/Exterior Lathing 5/10/2022 Not Ready for Inspection MICKEY YAMASHITA
PLUMBING-Rough 5/10/2022 Not Ready for Inspection MICKEY YAMASHITA
Wood Frame 5/10/2022 Corrections Issued MICKEY YAMASHITA
ELECTRICAL-Rough 5/11/2022 Corrections Issued MICKEY YAMASHITA
PLUMBING-Rough 5/11/2022 Corrections Issued MICKEY YAMASHITA
ELECTRICAL-Rough 5/16/2022 Corrections Issued MICKEY YAMASHITA
HVAC-Rough 5/16/2022 Corrections Issued MICKEY YAMASHITA
PLUMBING-Rough 5/16/2022 Conditional Approval MICKEY YAMASHITA
BUILDING-Rough-Frame 5/25/2022 Approved MICKEY YAMASHITA
ELECTRICAL-Rough 5/25/2022 Approved MICKEY YAMASHITA
Gas Test 5/25/2022 Partial Approval MICKEY YAMASHITA
Green Building Rough 5/25/2022 Approved MICKEY YAMASHITA
HVAC-Rough 5/25/2022 Approved MICKEY YAMASHITA
Insulation 5/25/2022 Approved MICKEY YAMASHITA
PLUMBING-Rough 5/25/2022 Approved MICKEY YAMASHITA
Wood Frame 5/25/2022 Approved MICKEY YAMASHITA
Drywall Nailing 6/9/2022 Approved THOMAS WOODS
Interior/Exterior Lathing 6/9/2022 Approved THOMAS WOODS
ELECTRICAL-Final 10/2/2023 Not Ready for Inspection LUCIANO GAUNA
HVAC-Final 10/2/2023 Not Ready for Inspection LUCIANO GAUNA
PLUMBING-Final 10/2/2023 Approved LUCIANO GAUNA
Smoke Detectors 10/2/2023 Not Ready for Inspection LUCIANO GAUNA
ELECTRICAL-Final 10/4/2023 Approved LUCIANO GAUNA
Final 10/4/2023 Conditional Approval LUCIANO GAUNA
Green Building Final 10/4/2023 Approved LUCIANO GAUNA
HVAC-Final 10/4/2023 Approved LUCIANO GAUNA
SGSOV-Seismic Gas S/O Valve 10/4/2023 SGSOV Approved LUCIANO GAUNA
Smoke Detectors 10/4/2023 Approved LUCIANO GAUNA