9713 N REMICK AVE 91331

Certificate Information: 9713 N REMICK AVE 91331

Application / Permit
19014-20000-06815
Plan Check / Job No.
B19VN21810
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADD IRREGULAR SHAPE 32.5' X 26.83' TO DETACHED GARAGE AND CONVERT TO ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. ALL WORKS ARE PER WFPP
Permit Issued
Issued on 1/23/2020
Issuing Office
Valley
Current Status
CofO Issued on 4/24/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/17/2019 APPLICANT
Assigned to Plan Check Engineer 12/17/2019 ALDOUS CHIC
Corrections Issued 12/17/2019 ALDOUS CHIC
Plan Check Approved 1/7/2020 MOHAMMAD ESMAILI
Issued 1/23/2020 LADBS
CofO in Progress 3/8/2021 MICHEL ABAJAN
Permit Finaled 4/24/2021 MICHAEL SMITH
CofO Issued 4/24/2021 MICHAEL SMITH
Permit Finaled 4/24/2021 MICHAEL SMITH

Permit Application Clearance Information

Miscellaneous Cleared 12/17/2019 HERMINIGILDO AGUSTIN
Miscellaneous Cleared 12/17/2019 HERMINIGILDO AGUSTIN
Address approval Cleared 1/7/2020 EMIL KYUPELYAN
Eng Process Fee Ord 176,300 Cleared 1/7/2020 EMIL KYUPELYAN
Low Impact Development Cleared 1/7/2020 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 1/7/2020 EMIL KYUPELYAN
Sewer availability Cleared 1/7/2020 EMIL KYUPELYAN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/3/2020 No Access for Inspection MICHEL ABAJAN
Underground Mechanical 3/9/2020 Partial Approval MICHEL ABAJAN
Footing/Foundation/Slab 3/10/2020 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 4/9/2020 No Access for Inspection BRENDAN LOONEY
BUILDING-Rough-Frame 4/24/2020 Approved MICHEL ABAJAN
ELECTRICAL-Rough 4/24/2020 Approved MICHEL ABAJAN
Green Building Rough 4/24/2020 Approved MICHEL ABAJAN
HVAC-Rough 4/24/2020 Approved MICHEL ABAJAN
MERV13>=Rough 4/24/2020 Approved MICHEL ABAJAN
PLUMBING-Rough 4/24/2020 Approved MICHEL ABAJAN
Insulation 4/29/2020 Approved MICHEL ABAJAN
Interior/Exterior Lathing 4/29/2020 Approved MICHEL ABAJAN
Drywall Nailing 5/5/2020 Approved MICHEL ABAJAN
Shower Pan 5/13/2020 Approved MICHEL ABAJAN
Underground Mechanical 6/29/2020 Partial Approval MICHEL ABAJAN
ELECTRICAL-Final 10/26/2020 Approved MICHEL ABAJAN
Final 10/26/2020 Corrections Issued MICHEL ABAJAN
Green Building Final 10/26/2020 Approved MICHEL ABAJAN
HVAC-Final 10/26/2020 Approved MICHEL ABAJAN
MERV13>=Final 10/26/2020 Approved MICHEL ABAJAN
PLUMBING-Final 10/26/2020 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 10/26/2020 SGSOV Approved MICHEL ABAJAN
Service/Power Release 10/26/2020 Corrections Issued MICHEL ABAJAN
Smoke Detectors 10/26/2020 Approved MICHEL ABAJAN
ELECTRICAL-Final 11/4/2020 Approved MICHEL ABAJAN
Final 11/4/2020 Not Ready for Inspection MICHEL ABAJAN
HVAC-Final 11/4/2020 Approved MICHEL ABAJAN
PLUMBING-Final 11/4/2020 Approved MICHEL ABAJAN
Final 3/4/2021 Corrections Issued MICHEL ABAJAN
Final 3/8/2021 OK to Issue CofO MICHEL ABAJAN