13322 W CHANDLER BLVD 91401
Certificate Information: 13322 W CHANDLER BLVD 91401
- Application / Permit
- 19014-20000-06814
- Plan Check / Job No.
- B19VN21809
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADDITION TO AND CONVERT THE (E) GARAGE INTO A (N) ACCESSORY DWELLING UNIT Irregular shape ( 69'-9"x26'-0") ( fire sprinklers reqrd )
- Permit Issued
- Issued on 5/13/2020
- Issuing Office
- Current Status
- CofO Issued on 11/17/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/27/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 1/30/2020 | MOHAMMAD ESMAILI |
| Corrections Issued | 2/4/2020 | MOHAMMAD ESMAILI |
| Quality Review Completed | 2/5/2020 | OMID HEDAYAT |
| Building Plans Picked Up | 2/10/2020 | APPLICANT |
| Green Plans Picked Up | 2/10/2020 | APPLICANT |
| Applicant returned to address corrections | 3/11/2020 | MOHAMMAD ESMAILI |
| Applicant returned to address corrections | 4/24/2020 | MOHAMMAD ESMAILI |
| Plan Check Approved | 5/13/2020 | MOHAMMAD ESMAILI |
| Issued | 5/13/2020 | APPLICANT |
| CofO in Progress | 10/7/2021 | MICHAEL PELHAM |
| CofO Issued | 11/17/2021 | MICHAEL SMITH |
| Permit Finaled | 11/17/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 2/14/2020 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 2/14/2020 | GUILLERMO PETRA |
| Sewer availability | Cleared | 2/14/2020 | GUILLERMO PETRA |
| Hydrant and Access approval | Cleared | 3/5/2020 | GEORGE SUCHAND |
| Green Code | Cleared | 3/10/2020 | AARON COSTA |
| Low Impact Development | Cleared | 4/10/2020 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 5/6/2020 | GUILLERMO PETRA |
Contact Information
| Contractor | Bellagio Design Build Corporation; Lic. No.: 935571-B | 19336 CALVERT STREET TARZANA, CA 91335 |
| Engineer | Rhee,, Kyle; Lic. No.: C78215 | 2753 WAVERLY DR 403 LOS ANGELES, CA 90039 |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/15/2020 | Partial Approval | CHARLES POWELL |
| Excavation/Setback/Form/Re-Bar | 5/18/2020 | Partial Approval | CHARLES POWELL |
| Footing/Foundation/Slab | 5/18/2020 | Partial Approval | CHARLES POWELL |
| BUILDING-Rough-Frame | 6/15/2020 | Corrections Issued | CHARLES POWELL |
| Green Building Rough | 6/15/2020 | Not Ready for Inspection | CHARLES POWELL |
| Insulation | 6/23/2020 | Partial Approval | DANIEL DREW |
| ELECTRICAL-Rough | 7/15/2020 | Approved | CHARLES POWELL |
| HVAC-Rough | 7/15/2020 | Approved | CHARLES POWELL |
| PLUMBING-Rough | 7/15/2020 | Approved | CHARLES POWELL |
| Floor/Roof Diaphrgm/Shear Wall | 7/28/2020 | Partial Approval | ARAM AVEDISIAN |
| Deputy Wood Construction | 7/29/2020 | Partial Approval | CHARLES POWELL |
| BUILDING-Rough-Frame | 8/7/2020 | Corrections Issued | CHARLES POWELL |
| Floor/Roof Diaphrgm/Shear Wall | 8/7/2020 | Approved | CHARLES POWELL |
| Green Building Rough | 8/7/2020 | Not Ready for Inspection | CHARLES POWELL |
| BUILDING-Rough-Frame | 8/11/2020 | Approved | CHARLES POWELL |
| Interior/Exterior Lathing | 8/11/2020 | Approved | CHARLES POWELL |
| Insulation | 8/24/2020 | Approved | DANIEL DREW |
| Interior/Exterior Lathing | 8/24/2020 | Approved | DANIEL DREW |
| Shower Pan | 8/24/2020 | Approved | DANIEL DREW |
| Drywall Nailing | 9/1/2020 | Approved | DANIEL DREW |
| Service/Power Release | 10/1/2020 | Not Ready for Inspection | CHARLES POWELL |
| Sewer | 10/1/2020 | Partial Approval | CHARLES POWELL |
| Underground Mechanical | 10/1/2020 | Approved | CHARLES POWELL |
| BUILDING-Rough-Frame | 11/16/2020 | Partial Inspection | THOMAS FINNILA |
| Final | 11/16/2020 | Partial Inspection | THOMAS FINNILA |
| Footing/Foundation/Slab | 11/16/2020 | Partial Inspection | THOMAS FINNILA |
| Green Building Rough | 11/16/2020 | Approved | THOMAS FINNILA |
| ELECTRICAL-Final | 11/24/2020 | Corrections Issued | ARAM AVEDISIAN |
| HVAC-Final | 11/24/2020 | Corrections Issued | ARAM AVEDISIAN |
| PLUMBING-Final | 11/24/2020 | Approved | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 1/15/2021 | Approved | CHARLES POWELL |
| Final | 1/15/2021 | Corrections Issued | CHARLES POWELL |
| Footing/Foundation/Slab | 1/15/2021 | Approved | CHARLES POWELL |
| Green Building Final | 1/15/2021 | Approved | CHARLES POWELL |
| SGSOV-Seismic Gas S/O Valve | 1/15/2021 | SGSOV Approved | CHARLES POWELL |
| Smoke Detectors | 1/15/2021 | Approved | CHARLES POWELL |
| Final | 1/26/2021 | Partial Approval | CHARLES POWELL |