6313 N CRANER AVE 91606
Certificate Information: 6313 N CRANER AVE 91606
- Application / Permit
- 19014-20000-06798
- Plan Check / Job No.
- B19VN21772
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 8'-2" X 12'-3" ADDITION TO AND CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER AB 494 AND SB 229
- Permit Issued
- Issued on 1/8/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/23/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/16/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/16/2019 | JEROME MAGAT PALMA |
| Corrections Issued | 12/16/2019 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 12/18/2019 | APPLICANT |
| Plan Check Approved | 1/8/2020 | JEROME MAGAT PALMA |
| Issued | 1/8/2020 | LADBS |
| CofO in Progress | 6/16/2020 | RAYMOND KEHOE |
| Permit Finaled | 9/23/2020 | MICHAEL SMITH |
| CofO Issued | 9/23/2020 | MICHAEL SMITH |
| Permit Finaled | 9/23/2020 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 1/7/2020 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 1/7/2020 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 1/7/2020 | LEE GUILBEAUX |
| Sewer availability | Cleared | 1/7/2020 | LEE GUILBEAUX |
| Construction near power lines | Cleared | 1/8/2020 | WALTER RAMIREZ |
Contact Information
| Contractor | 1 Stop Builders; Lic. No.: 1033108-B | 10117 SEPULVEDA BLVD STE 204 MISSION HILLS, CA 91345 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 1/17/2020 | Approved | MISAEL ESPARZA |
| Footing/Foundation/Slab | 1/17/2020 | Partial Approval | MISAEL ESPARZA |
| PLUMBING-Rough | 1/24/2020 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Rough | 1/30/2020 | Approved | RAYMOND KEHOE |
| BUILDING-Rough-Frame | 2/26/2020 | Not Ready for Inspection | RAYMOND KEHOE |
| ELECTRICAL-Rough | 2/26/2020 | Partial Approval | RAYMOND KEHOE |
| Green Building Rough | 2/26/2020 | Approved | RAYMOND KEHOE |
| HVAC-Rough | 2/26/2020 | Not Ready for Inspection | RAYMOND KEHOE |
| PLUMBING-Rough | 2/26/2020 | Approved | RAYMOND KEHOE |
| BUILDING-Rough-Frame | 3/4/2020 | Approved | RAYMOND KEHOE |
| HVAC-Rough | 3/4/2020 | Approved | RAYMOND KEHOE |
| Interior/Exterior Lathing | 3/4/2020 | Partial Approval | RAYMOND KEHOE |
| Insulation | 3/10/2020 | Conditional Approval | BEAU COLLINS |
| Drywall Nailing | 3/13/2020 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 3/13/2020 | Approved | JENNIFER RABUCHIN |
| Final | 4/22/2020 | Corrections Issued | JEFFREY PARD |
| Footing/Foundation/Slab | 4/22/2020 | Approved | JEFFREY PARD |
| Green Building Final | 4/22/2020 | Approved | JEFFREY PARD |
| SGSOV-Seismic Gas S/O Valve | 4/22/2020 | SGSOV Approved | JEFFREY PARD |
| Smoke Detectors | 4/22/2020 | Approved | JEFFREY PARD |
| ELECTRICAL-Final | 6/15/2020 | Approved | RAYMOND KEHOE |
| Final | 6/15/2020 | OK to Issue CofO | RAYMOND KEHOE |
| HVAC-Final | 6/15/2020 | Approved | RAYMOND KEHOE |
| PLUMBING-Final | 6/15/2020 | Approved | RAYMOND KEHOE |