5842 N JAMIESON AVE 91316

Certificate Information: 5842 N JAMIESON AVE 91316

Application / Permit
19014-20000-06796
Plan Check / Job No.
B19VN21764
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
49' X 34' IRREGULAR SHAPED ADDITION TO (E) 1-STORY SINGLE FAMILY DWELLING
Permit Issued
Issued on 1/22/2020
Issuing Office
Valley
Current Status
CofO Issued on 10/1/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/16/2019 APPLICANT
Assigned to Plan Check Engineer 12/17/2019 SELLA BENYAMIN
Corrections Issued 12/18/2019 SELLA BENYAMIN
Building Plans Picked Up 12/18/2019 APPLICANT
Issued 1/22/2020 LADBS
CofO in Progress 9/17/2020 VINCENT HANLEY
CofO Issued 10/1/2020 DONALD SUNSERI
Permit Finaled 10/1/2020 DONALD SUNSERI

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/14/2020 JOHN LIN
Low Impact Development Cleared 1/14/2020 SARAH YOUSSEF
Sewer availability Cleared 1/14/2020 JOHN LIN
Roof/Waste drainage to street Cleared 1/15/2020 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,
Engineer Yenjai,, Seree; Lic. No.: C73151 3249 SHADYLAWN DRIVE      DUARTE, CA 91010

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/31/2020 Partial Approval STEVEN BACK
Footing/Foundation/Slab 3/31/2020 Approved STEVEN BACK
BUILDING-Rough-Frame 4/20/2020 Partial Approval STEVEN BACK
PLUMBING-Rough 4/20/2020 Partial Approval STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 4/23/2020 Partial Approval STEVEN BACK
Insulation 4/23/2020 Partial Approval STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 6/5/2020 Partial Approval STEVEN BACK
BUILDING-Rough-Frame 6/15/2020 Approved STEVEN BACK
Green Building Rough 6/15/2020 Not Ready for Inspection STEVEN BACK
Rough-Elec/Plmb/HVAC 6/15/2020 Approved STEVEN BACK
ELECTRICAL-Rough 6/16/2020 Approved STEVEN BACK
HVAC-Rough 6/16/2020 Approved STEVEN BACK
PLUMBING-Rough 6/16/2020 Approved STEVEN BACK
Green Building Rough 6/19/2020 Approved STEVEN BACK
Interior/Exterior Lathing 6/19/2020 Partial Approval STEVEN BACK
Insulation 6/22/2020 Not Ready for Inspection STEVEN BACK
Shower Pan 6/22/2020 Approved STEVEN BACK
Insulation 6/23/2020 Approved STEVEN BACK
Drywall Nailing 6/25/2020 Approved STEVEN BACK
Gas Test 6/25/2020 Partial Approval STEVEN BACK
Interior/Exterior Lathing 6/25/2020 Approved STEVEN BACK
Final 8/17/2020 Corrections Issued STEVEN BACK
Green Building Final 8/17/2020 Corrections Issued STEVEN BACK
SGSOV-Seismic Gas S/O Valve 8/17/2020 SGSOV Approved STEVEN BACK
Smoke Detectors 8/17/2020 Corrections Issued STEVEN BACK
Final 8/28/2020 Corrections Issued STEVEN BACK
Green Building Final 8/28/2020 Not Ready for Inspection STEVEN BACK
Smoke Detectors 8/28/2020 Approved STEVEN BACK
Final 9/14/2020 Corrections Issued STEVEN BACK
Green Building Final 9/14/2020 Approved STEVEN BACK
Final 9/17/2020 OK to Issue CofO VINCENT HANLEY