6518 N ZELZAH AVE 91335

Certificate Information: 6518 N ZELZAH AVE 91335

Application / Permit
19014-20000-06794
Plan Check / Job No.
B19VN21754
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 18' X 20' DETACHED GARAGE AND ADD 10' X 20' TO CREATE (N) ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 1/8/2020
Issuing Office
Valley
Current Status
CofO Issued on 7/21/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/16/2019 APPLICANT
Assigned to Plan Check Engineer 12/17/2019 RAPHAEL ROSAS
Corrections Issued 12/17/2019 RAPHAEL ROSAS
Building Plans Picked Up 12/19/2019 APPLICANT
Issued 1/8/2020 LADBS
CofO in Progress 7/16/2020 VINCENT HANLEY
Permit Finaled 7/21/2020 DONALD SUNSERI
CofO Issued 7/21/2020 DONALD SUNSERI
Permit Finaled 7/21/2020 DONALD SUNSERI

Permit Application Clearance Information

Address approval Cleared 12/20/2019 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 12/20/2019 GUILLERMO PETRA
Roof/Waste drainage to street Cleared 12/20/2019 GUILLERMO PETRA
Sewer availability Cleared 12/20/2019 GUILLERMO PETRA
Construction near power lines Cleared 12/22/2019 RIDWAN HARDY

Contact Information

Architect Santiago-Dieppa,, Rafael Angel; Lic. No.: C10361 17116 RAYMER STREET      NORTHRIDGE, CA 91325
Contractor Owner-Builder       ,

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 2/6/2020 Approved VINCENT HANLEY
Underground Mechanical 2/6/2020 Partial Approval VINCENT HANLEY
Deputy Drilled-In Anchors 2/11/2020 Approved VINCENT HANLEY
PLUMBING-Rough 2/19/2020 Partial Approval VINCENT HANLEY
Excavation/Setback/Form/Re-Bar 2/24/2020 Approved VINCENT HANLEY
Footing/Foundation/Slab 2/24/2020 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 4/14/2020 Approved VINCENT HANLEY
BUILDING-Rough-Frame 4/23/2020 Partial Approval VINCENT HANLEY
BUILDING-Rough-Frame 4/28/2020 Approved VINCENT HANLEY
ELECTRICAL-Rough 4/28/2020 Approved VINCENT HANLEY
Green Building Rough 4/28/2020 Approved VINCENT HANLEY
HVAC-Rough 4/28/2020 Approved VINCENT HANLEY
PLUMBING-Rough 4/28/2020 Approved VINCENT HANLEY
Underground Mechanical 4/28/2020 Approved VINCENT HANLEY
Wood Frame 4/28/2020 Approved VINCENT HANLEY
Insulation 4/30/2020 Approved VINCENT HANLEY
Drywall Nailing 5/7/2020 Not Ready for Inspection VINCENT HANLEY
Interior/Exterior Lathing 5/7/2020 Partial Approval VINCENT HANLEY
Drywall Nailing 5/28/2020 Approved VINCENT HANLEY
Interior/Exterior Lathing 5/28/2020 Approved VINCENT HANLEY
Shower Pan 5/28/2020 Approved VINCENT HANLEY
Gas Test 6/26/2020 Approved VINCENT HANLEY
ELECTRICAL-Final 7/9/2020 Corrections Issued DONALD SUNSERI
Final 7/9/2020 Not Ready for Inspection DONALD SUNSERI
Green Building Final 7/9/2020 Not Ready for Inspection DONALD SUNSERI
HVAC-Final 7/9/2020 Corrections Issued DONALD SUNSERI
PLUMBING-Final 7/9/2020 Corrections Issued DONALD SUNSERI
SGSOV-Seismic Gas S/O Valve 7/9/2020 SGSOV Not Ready DONALD SUNSERI
Service/Power Release 7/9/2020 Not Ready for Inspection DONALD SUNSERI
Smoke Detectors 7/9/2020 Approved DONALD SUNSERI
ELECTRICAL-Final 7/16/2020 Approved VINCENT HANLEY
Final 7/16/2020 OK to Issue CofO VINCENT HANLEY
Green Building Final 7/16/2020 Approved VINCENT HANLEY
HVAC-Final 7/16/2020 Approved VINCENT HANLEY
PLUMBING-Final 7/16/2020 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 7/16/2020 SGSOV Approved VINCENT HANLEY
Service/Power Release 7/16/2020 Approved VINCENT HANLEY