5350 N BAZA AVE 91364
Certificate Information: 5350 N BAZA AVE 91364
- Application / Permit
- 19014-20000-06793
- Plan Check / Job No.
- B19VN21753
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 20'-0" X 23'-3" ADDITION TO AND CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER AB 494 & SB 229. ADD 6'-6" X 15'-11" ATTACHED PATIO COVER.
- Permit Issued
- Issued on 3/3/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 7/17/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/16/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/16/2019 | JEROME MAGAT PALMA |
| Corrections Issued | 12/16/2019 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 12/19/2019 | APPLICANT |
| Plan Check Approved | 3/3/2020 | JEROME MAGAT PALMA |
| Issued | 3/3/2020 | LADBS |
| CofO in Progress | 7/7/2021 | PETER FOLLING |
| CofO in Progress | 7/7/2021 | PETER FOLLING |
| Permit Finaled | 7/17/2021 | MICHAEL SMITH |
| CofO Issued | 7/17/2021 | MICHAEL SMITH |
| Permit Finaled | 7/17/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 2/5/2020 | LEE GUILBEAUX |
| BHO/Hillside ordinance | Cleared | 2/5/2020 | LEE GUILBEAUX |
| BHO/Hillside ordinance | Cleared | 2/5/2020 | LEE GUILBEAUX |
| BHO/Hillside ordinance | Cleared | 2/5/2020 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 2/5/2020 | LEE GUILBEAUX |
| Miscellaneous | Cleared | 2/5/2020 | LEE GUILBEAUX |
| Sewer availability | Cleared | 2/5/2020 | LEE GUILBEAUX |
| Low Impact Development | Cleared | 2/18/2020 | ORVAL HERNANDEZ-MARCIAL |
| Roof/Waste drainage to street | Cleared | 2/21/2020 | APEKSHYA BAJRACHARYA |
| GPI Written Notices | Cleared | 3/3/2020 | JEROME MAGAT PALMA |
| Grading Pre-Inspection | Cleared | 3/3/2020 | JEROME MAGAT PALMA |
Contact Information
| Architect | Fabrocini,, John Joseph; Lic. No.: C12736 | 21319 PROVIDENCIA ST WOODLAND HILLS, CA 91364 |
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN HAYES, (818) 774-4302 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 4/28/2020 | Approved | RONALD COWAN |
| Underground Mechanical | 4/29/2020 | Approved | RONALD COWAN |
| Footing/Foundation/Slab | 4/30/2020 | Approved | RONALD COWAN |
| BUILDING-Rough-Frame | 5/14/2020 | Corrections Issued | RONALD COWAN |
| Green Building Rough | 5/14/2020 | Not Ready for Inspection | RONALD COWAN |
| MERV13>=Rough | 5/14/2020 | Not Ready for Inspection | RONALD COWAN |
| ELECTRICAL-Rough | 8/10/2020 | Approved | RONALD COWAN |
| PLUMBING-Rough | 8/21/2020 | Corrections Issued | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 9/11/2020 | Partial Approval | DAVID SANDOVAL |
| HVAC-Rough | 9/11/2020 | Approved | DAVID SANDOVAL |
| Insulation | 9/29/2020 | Partial Approval | DONALD SUNSERI |
| Interior/Exterior Lathing | 9/29/2020 | Approved | DONALD SUNSERI |
| BUILDING-Rough-Frame | 10/7/2020 | Approved | DAVID SANDOVAL |
| Gas Test | 10/7/2020 | Approved | DAVID SANDOVAL |
| Green Building Rough | 10/7/2020 | Approved | DAVID SANDOVAL |
| MERV13>=Rough | 10/7/2020 | Approved | DAVID SANDOVAL |
| PLUMBING-Rough | 10/7/2020 | Approved | DAVID SANDOVAL |
| Insulation | 10/15/2020 | Approved | PAUL CHOPP |
| Drywall Nailing | 10/23/2020 | Approved | DAVID MATSON |
| Final | 5/12/2021 | Corrections Issued | DAVID SANDOVAL |
| Green Building Final | 5/12/2021 | Approved | DAVID SANDOVAL |
| MERV13>=Final | 5/12/2021 | Approved | DAVID SANDOVAL |
| SGSOV-Seismic Gas S/O Valve | 5/12/2021 | SGSOV Approved | DAVID SANDOVAL |
| Smoke Detectors | 5/12/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| Final | 6/25/2021 | OK to Issue CofO | PETER FOLLING |
| Smoke Detectors | 6/25/2021 | Approved | PETER FOLLING |