13817 W HARTSOOK ST 91423

Certificate Information: 13817 W HARTSOOK ST 91423

Application / Permit
19014-20000-06776
Plan Check / Job No.
B19VN21701
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
13'1" X 19'10" AND 15'5" X 5'4" ADDITION AND REMODEL TO (E) SFD. ALL WORK PER ENGINEER.
Permit Issued
Issued on 1/29/2020
Issuing Office
Valley
Current Status
CofO Issued on 12/18/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/13/2019 APPLICANT
Assigned to Plan Check Engineer 12/16/2019 PINANK PATEL
Corrections Issued 12/16/2019 PINANK PATEL
Building Plans Picked Up 12/17/2019 APPLICANT
Plan Check Approved 1/27/2020 PINANK PATEL
Issued 1/29/2020 LADBS
CofO in Progress 12/11/2020 CHRISTOPHE COCHRAN
CofO in Progress 12/11/2020 CHRISTOPHE COCHRAN
CofO Issued 12/18/2021 MICHAEL SMITH
Permit Finaled 12/18/2021 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/24/2020 ADRIAN CASTRO
Roof/Waste drainage to street Cleared 1/24/2020 ADRIAN CASTRO

Contact Information

Contractor Pristine Construction Inc; Lic. No.: 939885-B 14320 VENTURA BL   #320    SHERMAN OAKS, CA 91423
Engineer Basma,, Ali J; Lic. No.: C53080 21500 WYANDOTTE ST 106      CANOGA PARK, CA 91303

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/13/2020 Partial Approval CHARLES POWELL
Deputy Drilled-In Anchors 2/24/2020 Partial Approval CHARLES POWELL
Footing/Foundation/Slab 2/25/2020 Approved CHARLES POWELL
Deputy Reinf. Concrete 3/4/2020 Partial Approval CHARLES POWELL
Floor/Roof Diaphrgm/Shear Wall 3/13/2020 No Access for Inspection CHARLES POWELL
Floor/Roof Diaphrgm/Shear Wall 3/18/2020 Approved CHARLES POWELL
PLUMBING-Rough 3/23/2020 Not Ready for Inspection CHARLES POWELL
BUILDING-Rough-Frame 3/26/2020 Approved CHARLES POWELL
ELECTRICAL-Rough 3/26/2020 Approved CHARLES POWELL
Green Building Rough 3/26/2020 Not Ready for Inspection CHARLES POWELL
Interior/Exterior Lathing 3/26/2020 Approved CHARLES POWELL
PLUMBING-Rough 3/26/2020 Approved CHARLES POWELL
Shower Pan 3/26/2020 Approved CHARLES POWELL
HVAC-Rough 3/27/2020 Not Ready for Inspection CHARLES POWELL
HVAC-Rough 3/31/2020 Approved MATTHEW NUCKOLLS
Insulation 4/2/2020 Corrections Issued PIERRE VEGA
Insulation 4/6/2020 Approved MISAEL ESPARZA
Interior/Exterior Lathing 4/6/2020 Approved MISAEL ESPARZA
Drywall Nailing 4/14/2020 Approved BRENDAN LOONEY
BUILDING-Rough-Frame 6/3/2020 Approved CHARLES POWELL
Final 6/3/2020 Not Ready for Inspection CHARLES POWELL
Green Building Final 6/3/2020 Partial Approval CHARLES POWELL
Green Building Rough 6/3/2020 Approved CHARLES POWELL
SGSOV-Seismic Gas S/O Valve 6/3/2020 SGSOV Approved CHARLES POWELL
Smoke Detectors 6/3/2020 Approved CHARLES POWELL
ELECTRICAL-Final 6/5/2020 Approved CHARLES POWELL
Final 6/5/2020 OK to Issue CofO CHARLES POWELL
Green Building Final 6/5/2020 Approved CHARLES POWELL
HVAC-Final 6/5/2020 Approved CHARLES POWELL
PLUMBING-Final 6/5/2020 Approved CHARLES POWELL