13842 W ALBERS ST 91401

Certificate Information: 13842 W ALBERS ST 91401

Application / Permit
19014-20000-06755
Plan Check / Job No.
B19VN21646
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ALTERATION to include creating a new bedroom, and a new full bathroom and revise floor plan layout to alter restrooms and closets. Dwelling to have four bedrooms, 3 1/2 bath rooms, utility room, living room and kitchen.
Permit Issued
Issued on 1/8/2020
Issuing Office
Valley
Current Status
Permit Finaled on 3/9/2023

Permit Application Status History

Submitted 12/13/2019 APPLICANT
Assigned to Plan Check Engineer 12/13/2019 LUIS RINCON
Corrections Issued 12/15/2019 LUIS RINCON
Building Plans Picked Up 12/18/2019 APPLICANT
Plan Check Approved 1/8/2020 LUIS RINCON
Issued 1/8/2020 LADBS
Permit Finaled 3/8/2023 RYAN SALAZAR

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 12/18/2019 ADRIAN CASTRO
Sewer availability Cleared 12/18/2019 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,
Engineer Maalouf,, Sami; Lic. No.: C53210 15445 VENTURA BLVD STE 367      SHERMAN OAKS, CA 91403

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 8/28/2020 Conditional Approval WILLIAM KUEHN
BUILDING-Rough-Frame 9/17/2020 Partial Approval MICHEL ABAJAN
Footing/Foundation/Slab 9/17/2020 Partial Approval MICHEL ABAJAN
ELECTRICAL-Rough 10/6/2020 Partial Inspection WILLIAM KUEHN
PLUMBING-Rough 10/6/2020 Partial Inspection WILLIAM KUEHN
Insulation 10/28/2020 Approved MATTHEW NELSON
Interior/Exterior Lathing 10/28/2020 Approved MATTHEW NELSON
Drywall Nailing 11/18/2020 Approved WILLIAM KUEHN
BUILDING-Rough-Frame 9/3/2021 Not Ready for Inspection RICHARD DOCKUS
BUILDING-Rough-Frame 10/4/2021 Not Ready for Inspection RICHARD DOCKUS
ELECTRICAL-Rough 10/4/2021 Approved RICHARD DOCKUS
PLUMBING-Rough 10/4/2021 Approved RICHARD DOCKUS
HVAC-Rough 10/19/2021 Approved RICHARD DOCKUS
BUILDING-Rough-Frame 10/22/2021 Conditional Approval RICHARD DOCKUS
Insulation 11/1/2021 Approved RICHARD DOCKUS
Drywall Nailing 11/10/2021 Approved RICHARD DOCKUS
Final 3/8/2023 Permit Finaled RYAN SALAZAR
Footing/Foundation/Slab 3/8/2023 Approved RYAN SALAZAR
Green Building Final 3/8/2023 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 3/8/2023 SGSOV Approved RYAN SALAZAR
Smoke Detectors 3/8/2023 Approved RYAN SALAZAR