9540 N COLUMBUS AVE 91343
Certificate Information: 9540 N COLUMBUS AVE 91343
- Application / Permit
- 19014-20000-06731
- Plan Check / Job No.
- B19VN21550
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMOVE (E)ATT. PORCH AND ADD 6'-0" x 29'-11" TO THE (E) SFD. ADD 23'-0" x 13'-0" ATTACHED CARPORT TO (E)SFD.
- Permit Issued
- Issued on 12/20/2019
- Issuing Office
- Valley
- Current Status
- Issued on 12/20/2019
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/12/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/12/2019 | SARKIS HARABEDIAN |
| Corrections Issued | 12/12/2019 | SARKIS HARABEDIAN |
| Plan Check Approved | 12/18/2019 | PINANK PATEL |
| Issued | 12/20/2019 | LADBS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 12/18/2019 | APEKSHYA BAJRACHARYA |
| Roof/Waste drainage to street | Cleared | 12/18/2019 | APEKSHYA BAJRACHARYA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Villafana,, Donald Eugene; Lic. No.: C37354 | 1050 STERN LANE OXNARD, CA 93030 |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 7/10/2020 | No Access for Inspection | MARK JOHNSON |
| Special/Order Compliance | 7/14/2020 | Partial Inspection | JENNIFER RABUCHIN |
| Green Building Rough | 8/13/2020 | Approved | PIERRE VEGA |
| Insulation | 8/13/2020 | Approved | PIERRE VEGA |
| BUILDING-Rough-Frame | 9/9/2020 | Partial Inspection | JENNIFER RABUCHIN |
| Drywall Nailing | 9/9/2020 | Partial Inspection | JENNIFER RABUCHIN |
| Final | 9/9/2020 | Partial Inspection | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 9/9/2020 | Partial Inspection | JENNIFER RABUCHIN |
| Green Building Final | 9/9/2020 | Partial Inspection | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 9/9/2020 | SGSOV Not Required | JENNIFER RABUCHIN |
| Smoke Detectors | 9/9/2020 | Partial Inspection | JENNIFER RABUCHIN |