8250 N MORSE AVE 91605
Certificate Information: 8250 N MORSE AVE 91605
- Application / Permit
- 19014-20000-06730
- Plan Check / Job No.
- B19VN21547
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADDITION OF NEW 48' X 32'3" TWO STORY ACCESSORY DWELLING UNIT TO (E) 20' X 18' DETACHED GARAGE AS PER LAMC 12.22.A.33(C) AND (D) , NEW 7'6" X 5' PORCH ADDITION , NEW 3'6" X 14'6" GARAGE ADDITION TO ENLARGE (E) GARAGE , ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 6/13/2023
- Issuing Office
- Valley
- Current Status
- Issued on 6/13/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/12/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 1/7/2020 | RARES BODEA |
| Corrections Issued | 1/23/2020 | RARES BODEA |
| Green Plans Picked Up | 1/24/2020 | APPLICANT |
| Quality Review Completed | 1/27/2020 | STEVEN KIM |
| Building Plans Picked Up | 2/13/2020 | APPLICANT |
| Applicant returned to address corrections | 4/3/2023 | RARES BODEA |
| Plan Check Approved | 6/13/2023 | RARES BODEA |
| Issued | 6/13/2023 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 2/13/2020 | ADRIAN CASTRO |
| Construction near power lines | Cleared | 12/4/2020 | RIDWAN HARDY |
| Construction within easement | Cleared | 12/4/2020 | RIDWAN HARDY |
| Eng Process Fee Ord 176,300 | Cleared | 6/15/2022 | CARLOS AGUILERA |
| Low Impact Development | Cleared | 3/2/2023 | LUIS LUVANO |
| Roof/Waste drainage to street | Cleared | 3/20/2023 | CARLOS AGUILERA |
| Sewer availability | Cleared | 3/21/2023 | CARLOS AGUILERA |
Contact Information
| Contractor | International Construction Enterprises; Lic. No.: 972594-B | 8252 MORSE AVE NORTH HOLLYWOOD, CA 91605 |
| Engineer | Papazyan,, Andranik; Lic. No.: C56824 | 635 W COLORADO ST STE 104 GLENDALE, CA 91204 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/20/2023 | Not Ready for Inspection | DAVID MATSON |
| Footing/Foundation/Slab | 7/24/2023 | Corrections Issued | GREGG CUMMINGS |
| ELECTRICAL-Rough | 7/28/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Excavation/Setback/Form/Re-Bar | 7/28/2023 | Approved | GREGG CUMMINGS |
| Footing/Foundation/Slab | 7/28/2023 | Approved | GREGG CUMMINGS |
| Sewer | 7/28/2023 | Approved | GREGG CUMMINGS |
| Underground Mechanical | 7/28/2023 | Partial Approval | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 8/3/2023 | Partial Approval | GREGG CUMMINGS |
| Insulation | 8/3/2023 | Partial Approval | GREGG CUMMINGS |
| Wood Frame | 8/7/2023 | Partial Approval | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 8/11/2023 | Corrections Issued | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 8/12/2023 | Partial Approval | GREGG CUMMINGS |
| ELECTRICAL-Rough | 9/5/2023 | Approved | DAVID MATSON |
| HVAC-Rough | 9/5/2023 | Not Ready for Inspection | DAVID MATSON |
| PLUMBING-Rough | 9/5/2023 | Approved | DAVID MATSON |
| Posting Pre-Inspection | 9/5/2023 | Not Ready for Inspection | DAVID MATSON |
| Pre-Inspection | 9/5/2023 | Not Ready for Inspection | DAVID MATSON |
| ELECTRICAL-Rough | 9/6/2023 | Approved | DAVID MATSON |
| HVAC-Rough | 9/6/2023 | Approved | DAVID MATSON |
| Underground Mechanical | 9/6/2023 | Partial Approval | DAVID MATSON |
| Floor/Roof Diaphrgm/Shear Wall | 9/14/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 9/19/2023 | Conditional Approval | GREGG CUMMINGS |
| Green Building Rough | 9/19/2023 | Approved | GREGG CUMMINGS |
| Insulation | 9/27/2023 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 9/27/2023 | Approved | MICHEL ABAJAN |
| Shower Pan | 9/27/2023 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 10/12/2023 | Approved | GREGG CUMMINGS |
| Interior/Exterior Lathing | 10/12/2023 | Partial Approval | GREGG CUMMINGS |
| ELECTRICAL-Final | 3/5/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| ELECTRICAL-Rough | 3/5/2024 | Partial Approval | GREGG CUMMINGS |
| Interior/Exterior Lathing | 3/6/2024 | Partial Approval | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 3/14/2024 | Approved | GREGG CUMMINGS |
| Final | 3/14/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Green Building Final | 3/14/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 3/14/2024 | SGSOV Not Ready | GREGG CUMMINGS |
| Smoke Detectors | 3/14/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Final | 3/18/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| Green Building Final | 3/18/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Pre-Inspection | 3/18/2024 | Partial Approval | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 3/18/2024 | SGSOV Not Ready | CHRISTOPHER ROJAS |
| Smoke Detectors | 3/18/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |