6307 N PEACH AVE 91411

Certificate Information: 6307 N PEACH AVE 91411

Application / Permit
19014-20000-06722
Plan Check / Job No.
B19VN21510
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 25'8" X 21'6" IRREGULAR SHAPED 1ST FLOOR ADDITION TO (E) SFD TO ENLARGE MASTER BEDROOM , CREATE NEW MASTER BATHROOM , STAIRCASE AND ENTRY, NEW 24' X 21'6" SECOND FLOOR ADDITION TO CREATE NEW BEDROOM AND NEW BATHROOM , ALL WORK PER ENGINEERING
Permit Issued
Issued on 1/9/2020
Issuing Office
Valley
Current Status
CofO Issued on 7/18/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/11/2019 APPLICANT
Green Plans Picked Up 12/17/2019 APPLICANT
Assigned to Plan Check Engineer 12/19/2019 RARES BODEA
Corrections Issued 12/21/2019 RARES BODEA
Quality Review Completed 12/23/2019 GUANG MIN TUNG
Building Plans Picked Up 12/24/2019 APPLICANT
Plan Check Approved 1/9/2020 RARES BODEA
Issued 1/9/2020 LADBS
CofO in Progress 5/14/2020 MISAEL ESPARZA
CofO Issued 7/18/2020 MICHAEL SMITH
Permit Finaled 7/18/2020 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 12/31/2019 JOHN TRIANTAFYLLOS
Green Code Cleared 12/31/2019 AARON COSTA
Roof/Waste drainage to street Cleared 12/31/2019 JOHN TRIANTAFYLLOS
Sewer availability Cleared 12/31/2019 JOHN TRIANTAFYLLOS
Hydrant and Access approval Cleared 1/3/2020 GEORGE SUCHAND
ZI Cleared 1/3/2020 NELSON RODRIGUEZ

Contact Information

Architect Svalbe,, John W; Lic. No.: C33344 1830 AMARGOSA DRIVE      PALMDALE, CA 93551
Contractor Supreme Construction; Lic. No.: 819659-B 42263 50TH STREET WEST STE 209      QUARTZ HILL, CA 93536

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/22/2020 Partial Approval ARAM AVEDISIAN
PLUMBING-Rough 1/22/2020 Partial Approval ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 2/6/2020 Partial Approval MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 2/20/2020 Partial Approval MISAEL ESPARZA
BUILDING-Rough-Frame 3/2/2020 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Rough 3/2/2020 Approved MISAEL ESPARZA
Green Building Rough 3/2/2020 Not Ready for Inspection MISAEL ESPARZA
PLUMBING-Rough 3/2/2020 Approved MISAEL ESPARZA
Interior/Exterior Lathing 3/9/2020 Partial Approval MISAEL ESPARZA
Insulation 3/13/2020 Approved MICHEL ABAJAN
Shower Pan 3/13/2020 Not Ready for Inspection MICHEL ABAJAN
Drywall Nailing 3/16/2020 Conditional Approval MISAEL ESPARZA
Green Building Rough 3/16/2020 Approved MISAEL ESPARZA
Interior/Exterior Lathing 3/25/2020 Approved MISAEL ESPARZA
Shower Pan 3/25/2020 Corrections Issued MISAEL ESPARZA
Shower Pan 4/2/2020 Approved CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 5/8/2020 Approved MISAEL ESPARZA
Drywall Nailing 5/8/2020 Approved MISAEL ESPARZA
Final 5/8/2020 Corrections Issued MISAEL ESPARZA
Footing/Foundation/Slab 5/8/2020 Approved MISAEL ESPARZA
Green Building Final 5/8/2020 Approved MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 5/8/2020 SGSOV Not Ready MISAEL ESPARZA
Smoke Detectors 5/8/2020 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Final 5/14/2020 Approved MISAEL ESPARZA
Final 5/14/2020 OK to Issue CofO MISAEL ESPARZA
HVAC-Final 5/14/2020 Approved MISAEL ESPARZA
PLUMBING-Final 5/14/2020 Approved MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 5/14/2020 SGSOV Approved MISAEL ESPARZA
Smoke Detectors 5/14/2020 Approved MISAEL ESPARZA