14343-14345 W GERMAIN ST 91345

Certificate Information: 14343-14345 W GERMAIN ST 91345

Application / Permit
19014-20000-06643
Plan Check / Job No.
B19VN21185
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADD 5.5' X 13'8" FOR NEW BATHROOM, REFRAME ROOF OF ATTACHED GARAGE AND CONVERT TO ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. ALL WORKS ARE PER WFPP
Permit Issued
Issued on 12/10/2019
Issuing Office
Valley
Current Status
CofO Issued on 10/19/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/6/2019 APPLICANT
Assigned to Plan Check Engineer 12/6/2019 ALDOUS CHIC
Corrections Issued 12/6/2019 ALDOUS CHIC
Plan Check Approved 12/9/2019 YAQUB MIRZA
Issued 12/10/2019 LADBS
CofO in Progress 9/3/2020 JENNIFER RABUCHIN
CofO in Progress 9/8/2020 JENNIFER RABUCHIN
CofO Issued 10/19/2020 MICHAEL SMITH
Permit Finaled 10/19/2020 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 12/6/2019 JOHN LIN
Eng Process Fee Ord 176,300 Cleared 12/6/2019 JOHN LIN
Roof/Waste drainage to street Cleared 12/6/2019 JOHN LIN
Sewer availability Cleared 12/6/2019 JOHN LIN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Floor/Roof Diaphrgm/Shear Wall 2/24/2020 Not Ready for Inspection JENNIFER RABUCHIN
Footing/Foundation/Slab 2/24/2020 Corrections Issued JENNIFER RABUCHIN
METHANE-Barrier 2/24/2020 Approved JENNIFER RABUCHIN
METHANE-Subgrade 2/24/2020 Approved JENNIFER RABUCHIN
PLUMBING-Rough 2/24/2020 Partial Approval JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 2/28/2020 Partial Approval JENNIFER RABUCHIN
Drywall Nailing 3/6/2020 Not Ready for Inspection JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 3/6/2020 Corrections Issued JENNIFER RABUCHIN
Green Building Rough 3/6/2020 Not Ready for Inspection JENNIFER RABUCHIN
BUILDING-Rough-Frame 3/10/2020 Partial Approval JENNIFER RABUCHIN
BUILDING-Rough-Frame 3/16/2020 Corrections Issued PIERRE VEGA
ELECTRICAL-Rough 3/16/2020 Not Ready for Inspection PIERRE VEGA
Green Building Rough 3/16/2020 Not Ready for Inspection PIERRE VEGA
MERV13>=Rough 3/16/2020 Not Ready for Inspection PIERRE VEGA
METHANE-Rough 3/16/2020 Approved PIERRE VEGA
PLUMBING-Rough 3/16/2020 Corrections Issued PIERRE VEGA
Interior/Exterior Lathing 3/27/2020 Not Ready for Inspection MARK JOHNSON
PLUMBING-Rough 3/27/2020 Partial Inspection MARK JOHNSON
PLUMBING-Rough 4/2/2020 Partial Approval JENNIFER RABUCHIN
BUILDING-Rough-Frame 4/17/2020 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 4/17/2020 Approved JENNIFER RABUCHIN
Green Building Rough 4/17/2020 Approved JENNIFER RABUCHIN
MERV13>=Rough 4/17/2020 Approved JENNIFER RABUCHIN
Insulation 4/21/2020 Partial Approval JENNIFER RABUCHIN
Drywall Nailing 4/28/2020 Approved GREGG CUMMINGS
Interior/Exterior Lathing 4/30/2020 Partial Approval JENNIFER RABUCHIN
Final 6/8/2020 Not Ready for Inspection GREGG CUMMINGS
Footing/Foundation/Slab 6/8/2020 Not Ready for Inspection GREGG CUMMINGS
Green Building Final 6/8/2020 Not Ready for Inspection GREGG CUMMINGS
MERV13>=Final 6/8/2020 Not Ready for Inspection GREGG CUMMINGS
SGSOV-Seismic Gas S/O Valve 6/8/2020 SGSOV Not Ready GREGG CUMMINGS
Smoke Detectors 6/8/2020 Not Ready for Inspection GREGG CUMMINGS
Special/Order Compliance 6/8/2020 Approved PIERRE VEGA
ELECTRICAL-Final 6/19/2020 Approved JENNIFER RABUCHIN
Final 6/19/2020 OK to Issue CofO JENNIFER RABUCHIN
Footing/Foundation/Slab 6/19/2020 Approved JENNIFER RABUCHIN
Green Building Final 6/19/2020 Approved JENNIFER RABUCHIN
HVAC-Final 6/19/2020 Approved JENNIFER RABUCHIN
MERV13>=Final 6/19/2020 Approved JENNIFER RABUCHIN
PLUMBING-Final 6/19/2020 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 6/19/2020 SGSOV Approved JENNIFER RABUCHIN
Service/Power Release 6/19/2020 Approved JENNIFER RABUCHIN
Smoke Detectors 6/19/2020 Approved JENNIFER RABUCHIN
Final 8/7/2020 Partial Inspection JENNIFER RABUCHIN
Final 9/3/2020 OK to Issue CofO JENNIFER RABUCHIN