12526 W BESSEMER ST 91606

Certificate Information: 12526 W BESSEMER ST 91606

Application / Permit
19014-20000-06631
Plan Check / Job No.
B19VN21157
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED NEW 1/2 BATH & LAUNDRY RM WITHIN EXISTING ATT GARAGE. AND NEW PATIO COVER (20'X20') ADDN PER CITY STD DETAIL, TO THE REAR OF THE GARAGE. ALL WORK PER WFPP ; "COMPLY WITH DEPARTMENT ORDER effective date 11/15/2019. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
Permit Issued
Issued on 12/9/2019
Issuing Office
Valley
Current Status
CofO Issued on 4/3/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/6/2019 APPLICANT
Assigned to Plan Check Engineer 12/6/2019 RARES BODEA
Plan Check Approved 12/6/2019 RARES BODEA
Issued 12/9/2019 LADBS
CofO in Progress 12/23/2025 SCOTT SHUSTER
Permit Finaled 4/3/2026 DAVID JAMES
CofO Issued 4/3/2026 DAVID JAMES
Permit Finaled 4/3/2026 DAVID JAMES

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 12/6/2019 GUILLERMO PETRA
Roof/Waste drainage to street Cleared 12/6/2019 GUILLERMO PETRA
ZA Case Cleared 12/6/2019 HERMINIGILDO AGUSTIN
ZA Case Cleared 12/6/2019 HERMINIGILDO AGUSTIN

Contact Information

Contractor Vg&V Construction Inc; Lic. No.: 1034103-B 534 N LOUISE STREET #_B      GLENDALE, CA 91206

Inspector Information

ARA SINANIAN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
HASANTHA WEERASEKARA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
SCOTT SHUSTER, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOEL GUARDADO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARIYA MIHALEVA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOSE RUBIO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
DAVID JAMES, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
DAVID HICKMAN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOHN HAMILTON, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOHN STEPHENS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
PIERRE VEGA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARK VAN SLOOTEN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MICKEY YAMASHITA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
RICHARD ROBLES, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
HAGOP BADOSSIAN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
KIM BEAUCHAMP, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARK DOVICO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
THOMAS WOODS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
RAUL VASQUEZ, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
AUGUSTUS ALBAS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
FELIPE PENICHE, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
LEO MILBAUER, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Floor/Roof Diaphrgm/Shear Wall 12/12/2019 Not Ready for Inspection BRYAN MEYER
PLUMBING-Rough 12/12/2019 Not Ready for Inspection BRYAN MEYER
ELECTRICAL-Rough 12/20/2019 Not Ready for Inspection RICHARD DOCKUS
PLUMBING-Rough 12/20/2019 Not Ready for Inspection RICHARD DOCKUS
ELECTRICAL-Rough 3/5/2020 Not Ready for Inspection BRYAN MEYER
Footing/Foundation/Slab 3/5/2020 Corrections Issued BRYAN MEYER
PLUMBING-Rough 3/5/2020 Not Ready for Inspection BRYAN MEYER
Footing/Foundation/Slab 4/15/2020 Corrections Issued BRYAN MEYER
Footing/Foundation/Slab 6/29/2020 Not Ready for Inspection BRYAN MEYER
Footing/Foundation/Slab 7/2/2020 Approved BRYAN MEYER
PLUMBING-Rough 7/2/2020 Partial Approval BRYAN MEYER
ELECTRICAL-Rough 12/22/2020 Partial Inspection BRYAN MEYER
PLUMBING-Rough 12/22/2020 Approved BRYAN MEYER
Wood Frame 12/22/2020 Partial Approval BRYAN MEYER
Deputy Wood Construction 12/28/2020 Partial Approval BRYAN MEYER
ELECTRICAL-Rough 1/5/2021 Approved BRYAN MEYER
Wood Frame 1/5/2021 Approved BRYAN MEYER
Insulation 1/14/2021 Approved BRYAN MEYER
Interior/Exterior Lathing 1/14/2021 Approved BRYAN MEYER
Drywall Nailing 1/21/2021 Approved BRYAN MEYER
Green Building Rough 1/21/2021 Approved BRYAN MEYER
BUILDING-Rough-Frame 8/22/2023 Approved BRYAN MEYER
Final 8/22/2023 Partial Inspection BRYAN MEYER
Green Building Final 8/22/2023 Approved BRYAN MEYER
SGSOV-Seismic Gas S/O Valve 8/22/2023 SGSOV Approved BRYAN MEYER
Smoke Detectors 8/22/2023 Partial Inspection BRYAN MEYER
Final 12/22/2025 Partial Approval SCOTT SHUSTER
Smoke Detectors 12/22/2025 Approved SCOTT SHUSTER
Final 12/23/2025 OK to Issue CofO SCOTT SHUSTER