10335 N BARTEE AVE 91331

Certificate Information: 10335 N BARTEE AVE 91331

Application / Permit
19014-20000-06624
Plan Check / Job No.
B19VN21125
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED 36' 6" X 20' 1-STORY IRR.-SHAPE ACCESSORY DWELLING UNIT WITH 3' X 6' PORCH. ALL WORK DONE PER WFPP.
Permit Issued
Issued on 1/5/2021
Issuing Office
Current Status
CofO Issued on 10/25/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/5/2019 APPLICANT
Assigned to Plan Check Engineer 12/12/2019 GURUNATH NESARAJAH
Green Plans Picked Up 12/20/2019 APPLICANT
Corrections Issued 12/21/2019 GURUNATH NESARAJAH
Quality Review Completed 12/23/2019 GUANG MIN TUNG
Building Plans Picked Up 12/27/2019 APPLICANT
Plan Check Approved 12/24/2020 GURUNATH NESARAJAH
Issued 1/5/2021 APPLICANT
CofO in Progress 7/15/2024 JENNIFER RABUCHIN
Permit Finaled 10/25/2024 DANIEL ORRANTE
CofO Issued 10/25/2024 DANIEL ORRANTE
Permit Finaled 10/25/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 2/13/2020 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 2/24/2020 JUAN ASHTON
Sewer availability Cleared 2/24/2020 JUAN ASHTON
Green Code Cleared 2/27/2020 AARON COSTA
Low Impact Development Cleared 3/12/2020 ORVAL HERNANDEZ-MARCIAL
Roof/Waste drainage to street Cleared 3/12/2020 EMIL KYUPELYAN
Construction near power lines Cleared 5/13/2020 RIDWAN HARDY
Hydrant and Access approval Cleared 8/19/2020 MATTHEW CRAIG

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/25/2021 Partial Approval JENNIFER RABUCHIN
Footing/Foundation/Slab 6/25/2021 Partial Approval JENNIFER RABUCHIN
METHANE-Barrier 6/25/2021 Approved JENNIFER RABUCHIN
METHANE-Subgrade 6/25/2021 Approved JENNIFER RABUCHIN
Footing/Foundation/Slab 6/30/2021 Approved DAVID MATSON
BUILDING-Rough-Frame 7/26/2021 Partial Approval JENNIFER RABUCHIN
PLUMBING-Rough 7/26/2021 Partial Approval JENNIFER RABUCHIN
Insulation 7/29/2021 Approved JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 8/5/2021 Partial Approval MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 9/27/2021 Partial Approval MICHEL ABAJAN
BUILDING-Rough-Frame 10/19/2021 Partial Approval JENNIFER RABUCHIN
Green Building Rough 10/19/2021 Not Ready for Inspection JENNIFER RABUCHIN
MERV13>=Rough 10/19/2021 Not Ready for Inspection JENNIFER RABUCHIN
METHANE-Rough 10/19/2021 Approved JENNIFER RABUCHIN
PLUMBING-Rough 10/19/2021 Corrections Issued JENNIFER RABUCHIN
Verify Sprinkler Sign Off 10/19/2021 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 11/1/2021 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 11/1/2021 Not Ready for Inspection JENNIFER RABUCHIN
BUILDING-Rough-Frame 12/9/2021 Partial Approval JENNIFER RABUCHIN
ELECTRICAL-Rough 12/9/2021 Corrections Issued JENNIFER RABUCHIN
Green Building Rough 12/9/2021 Partial Approval JENNIFER RABUCHIN
Interior/Exterior Lathing 12/9/2021 Partial Approval JENNIFER RABUCHIN
MERV13>=Rough 12/9/2021 Approved JENNIFER RABUCHIN
PLUMBING-Rough 12/9/2021 Approved JENNIFER RABUCHIN
Insulation 12/21/2021 Corrections Issued GREGG CUMMINGS
Insulation 12/28/2021 Approved JENNIFER RABUCHIN
Drywall Nailing 1/7/2022 Approved JENNIFER RABUCHIN
Green Building Rough 1/7/2022 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 1/7/2022 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 5/16/2024 Approved JENNIFER RABUCHIN
Final 5/16/2024 Corrections Issued JENNIFER RABUCHIN
Green Building Final 5/16/2024 Corrections Issued JENNIFER RABUCHIN
MERV13>=Final 5/16/2024 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 5/16/2024 SGSOV Not Ready JENNIFER RABUCHIN
Service/Power Release 5/16/2024 Not Ready for Inspection JENNIFER RABUCHIN
Smoke Detectors 5/16/2024 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 7/8/2024 Approved JENNIFER RABUCHIN
Final 7/8/2024 Not Ready for Inspection JENNIFER RABUCHIN
Green Building Final 7/8/2024 Corrections Issued JENNIFER RABUCHIN
HVAC-Final 7/8/2024 Approved JENNIFER RABUCHIN
PLUMBING-Final 7/8/2024 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 7/8/2024 SGSOV Approved JENNIFER RABUCHIN
Service/Power Release 7/8/2024 Not Ready for Inspection JENNIFER RABUCHIN
Final 7/15/2024 OK to Issue CofO JENNIFER RABUCHIN
Green Building Final 7/15/2024 Approved JENNIFER RABUCHIN
Service/Power Release 7/15/2024 Approved JENNIFER RABUCHIN