12413 W OTSEGO ST 91607
Certificate Information: 12413 W OTSEGO ST 91607
- Application / Permit
- 19014-20000-06610
- Plan Check / Job No.
- B19VN21107
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Remodel kitchen, reconfigure interior, replace all doors/windows (same location/size, dual glazing certified by NFRC with existing header remains) and add irregular shape 24.75' x 19.5' for new bedroom/bathroom per design
- Permit Issued
- Issued on 5/29/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 2/23/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/5/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/5/2019 | ALDOUS CHIC |
| Corrections Issued | 12/5/2019 | ALDOUS CHIC |
| Applicant returned to address corrections | 1/29/2020 | SARKIS HARABEDIAN |
| Plan Check Approved | 2/28/2020 | JEFFREY TANGONAN |
| Issued | 5/29/2020 | LADBS |
| CofO in Progress | 2/11/2022 | CHRISTOPHE COCHRAN |
| Permit Finaled | 2/23/2022 | MICHAEL SMITH |
| CofO Issued | 2/23/2022 | MICHAEL SMITH |
| Permit Finaled | 2/23/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 12/12/2019 | ADRIAN CASTRO |
| Roof/Waste drainage to street | Cleared | 12/12/2019 | ADRIAN CASTRO |
| Sewer availability | Cleared | 12/12/2019 | ADRIAN CASTRO |
| ZI | Cleared | 1/29/2020 | OLGA AYALA |
| Specific Plan | Cleared | 1/30/2020 | OLGA AYALA |
| Low Impact Development | Cleared | 2/27/2020 | SARAH YOUSSEF |
Contact Information
| Architect | Salcedo,, Glen Charles; Lic. No.: C33143 | P O BOX 14202 VAN NUYS, CA 91409 |
| Contractor | B D R Inc; Lic. No.: 735996-B | P O BOX 410 AGOURA HILLS, CA 91376 |
| Engineer | Samadzadeh,, Ali Reza; Lic. No.: C87661 | 20655 SHERMAN WAY #5 LOS ANGELES, CA 91306 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/22/2020 | Conditional Approval | BEAU COLLINS |
| PLUMBING-Rough | 8/14/2020 | Approved | BRENDAN LOONEY |
| Insulation | 9/4/2020 | Corrections Issued | BRENDAN LOONEY |
| Insulation | 9/11/2020 | Partial Approval | BRENDAN LOONEY |
| Drywall Nailing | 10/16/2020 | Not Ready for Inspection | BRENDAN LOONEY |
| Floor/Roof Diaphrgm/Shear Wall | 10/16/2020 | Corrections Issued | BRENDAN LOONEY |
| Green Building Rough | 10/16/2020 | Not Ready for Inspection | BRENDAN LOONEY |
| Floor/Roof Diaphrgm/Shear Wall | 10/23/2020 | Conditional Approval | BRENDAN LOONEY |
| HVAC-Rough | 11/2/2020 | Corrections Issued | BEAU COLLINS |
| PLUMBING-Rough | 11/2/2020 | Not Ready for Inspection | BEAU COLLINS |
| HVAC-Rough | 11/17/2020 | Not Ready for Inspection | BRENDAN LOONEY |
| PLUMBING-Rough | 11/17/2020 | Corrections Issued | BRENDAN LOONEY |
| Insulation | 11/24/2020 | No Access for Inspection | BRENDAN LOONEY |
| Interior/Exterior Lathing | 11/24/2020 | No Access for Inspection | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 1/14/2021 | Partial Approval | BRENDAN LOONEY |
| ELECTRICAL-Rough | 1/14/2021 | Corrections Issued | BRENDAN LOONEY |
| HVAC-Rough | 1/14/2021 | Partial Approval | BRENDAN LOONEY |
| Insulation | 1/22/2021 | Partial Inspection | BRENDAN LOONEY |
| Drywall Nailing | 2/3/2021 | Partial Approval | BRENDAN LOONEY |
| Green Building Rough | 2/3/2021 | Not Ready for Inspection | BRENDAN LOONEY |
| PLUMBING-Rough | 2/3/2021 | Not Ready for Inspection | BRENDAN LOONEY |
| Shower Pan | 2/3/2021 | Approved | BRENDAN LOONEY |
| Interior/Exterior Lathing | 2/8/2021 | Partial Approval | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 11/9/2021 | Approved | JACK KARGODORIAN |
| Drywall Nailing | 11/9/2021 | Approved | JACK KARGODORIAN |
| Final | 11/9/2021 | Corrections Issued | JACK KARGODORIAN |
| Footing/Foundation/Slab | 11/9/2021 | Approved | JACK KARGODORIAN |
| Green Building Final | 11/9/2021 | Not Ready for Inspection | JACK KARGODORIAN |
| Green Building Rough | 11/9/2021 | Approved | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 11/9/2021 | SGSOV Not Ready | JACK KARGODORIAN |
| Smoke Detectors | 11/9/2021 | Approved | JACK KARGODORIAN |
| Final | 11/23/2021 | Conditional Approval | CHRISTOPHE COCHRAN |
| Green Building Final | 11/23/2021 | Approved | CHRISTOPHE COCHRAN |
| SGSOV-Seismic Gas S/O Valve | 11/23/2021 | SGSOV Approved | CHRISTOPHE COCHRAN |
| Final | 1/25/2022 | Conditional Approval | CHRISTOPHE COCHRAN |
| Final | 2/10/2022 | OK to Issue CofO | CHRISTOPHE COCHRAN |