6643 N TAMPA AVE 91335
Certificate Information: 6643 N TAMPA AVE 91335
- Application / Permit
- 19014-20000-06609
- Plan Check / Job No.
- B19VN21106
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 18'-4" X 20'-5" DETACHED GARAGE AND ADD IRREGULAR 20'-3" X 25'-8" FOR (N) ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. ALL WORK PER WFPP.
- Permit Issued
- Issued on 2/14/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/27/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/5/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/12/2019 | JENNIFER LEE |
| Corrections Issued | 12/12/2019 | JENNIFER LEE |
| Applicant returned to address corrections | 2/13/2020 | ALYSSA N NARCISO |
| Plan Check Approved | 2/14/2020 | ANGELICA MARTINEZ |
| Issued | 2/14/2020 | LADBS |
| CofO in Progress | 9/14/2021 | VINCENT HANLEY |
| Permit Finaled | 9/27/2021 | JOHN JANSON |
| CofO Issued | 9/27/2021 | JOHN JANSON |
| Permit Finaled | 9/27/2021 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 2/4/2020 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 2/4/2020 | LEE GUILBEAUX |
| Sewer availability | Cleared | 2/4/2020 | LEE GUILBEAUX |
| Construction near power lines | Cleared | 2/10/2020 | RIDWAN HARDY |
| Low Impact Development | Cleared | 2/12/2020 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 2/13/2020 | GABRIEL ROBLES |
Contact Information
| Contractor | Best Remodeling And Development; Lic. No.: 988425-B | 17609 VENTURA BLVD #LL08 ENCINO, CA 91316 |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/10/2020 | Approved | VINCENT HANLEY |
| Footing/Foundation/Slab | 3/11/2020 | Corrections Issued | VINCENT HANLEY |
| Excavation/Setback/Form/Re-Bar | 3/27/2020 | Approved | VINCENT HANLEY |
| Footing/Foundation/Slab | 3/27/2020 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 3/27/2020 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 4/22/2020 | No Access for Inspection | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 4/23/2020 | Not Ready for Inspection | VINCENT HANLEY |
| HVAC-Rough | 5/26/2020 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 9/23/2020 | Approved | VINCENT HANLEY |
| ELECTRICAL-Rough | 9/23/2020 | Approved | VINCENT HANLEY |
| Green Building Rough | 9/23/2020 | Approved | VINCENT HANLEY |
| Insulation | 9/23/2020 | Approved | VINCENT HANLEY |
| Shower Pan | 9/23/2020 | Approved | VINCENT HANLEY |
| Drywall Nailing | 10/6/2020 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 10/6/2020 | Partial Approval | VINCENT HANLEY |
| Final | 8/17/2021 | Corrections Issued | STEVEN BACK |
| Green Building Final | 8/17/2021 | Not Ready for Inspection | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 8/17/2021 | SGSOV Approved | STEVEN BACK |
| Smoke Detectors | 8/17/2021 | Approved | STEVEN BACK |
| ELECTRICAL-Final | 9/14/2021 | Approved | VINCENT HANLEY |
| Final | 9/14/2021 | OK to Issue CofO | VINCENT HANLEY |
| Gas Test | 9/14/2021 | Approved | VINCENT HANLEY |
| Green Building Final | 9/14/2021 | Approved | VINCENT HANLEY |
| HVAC-Final | 9/14/2021 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 9/14/2021 | Approved | VINCENT HANLEY |