6360 W DREXEL AVE 90048
Certificate Information: 6360 W DREXEL AVE 90048
- Application / Permit
- 19014-20000-06601
- Plan Check / Job No.
- B19VN21085
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- MAJOR REMODEL & 2ND STORY ADDITION TO (E) SINGLE FAMILY DWELLING; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 1/30/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 6/11/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/4/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/12/2019 | SELLA BENYAMIN |
| Corrections Issued | 12/16/2019 | SELLA BENYAMIN |
| Green Plans Picked Up | 12/17/2019 | APPLICANT |
| Quality Review Completed | 12/19/2019 | STEVEN KIM |
| Building Plans Picked Up | 12/30/2019 | APPLICANT |
| Plan Check Approved | 1/28/2020 | SELLA BENYAMIN |
| Issued | 1/30/2020 | LADBS |
| CofO in Progress | 5/26/2021 | EVAN COOPER |
| Permit Finaled | 6/11/2021 | KENNETH NAGLE |
| CofO Issued | 6/11/2021 | KENNETH NAGLE |
| Permit Finaled | 6/11/2021 | KENNETH NAGLE |
Permit Application Clearance Information
| Low Impact Development | Cleared | 1/13/2020 | ORVAL HERNANDEZ-MARCIAL |
| Roof/Waste drainage to street | Cleared | 1/13/2020 | CARL MILLS |
| Eng Process Fee Ord 176,300 | Cleared | 1/27/2020 | LEE GUILBEAUX |
| Sewer availability | Cleared | 1/27/2020 | LEE GUILBEAUX |
| Green Code | Cleared | 1/28/2020 | MICHAEL AYERS |
| ZI | Cleared | 1/28/2020 | HERMINIGILDO AGUSTIN |
Contact Information
| Contractor | Caliwood Development Inc; Lic. No.: 1016617-B | 11304 SANTA MONICA BLVD LOS ANGELES, CA 90025 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/20/2020 | Not Ready for Inspection | EVAN COOPER |
| METHANE-Barrier | 2/20/2020 | Not Ready for Inspection | EVAN COOPER |
| METHANE-Subgrade | 2/20/2020 | Not Ready for Inspection | EVAN COOPER |
| Footing/Foundation/Slab | 2/26/2020 | Corrections Issued | EVAN COOPER |
| METHANE-Barrier | 2/26/2020 | Approved | EVAN COOPER |
| METHANE-Subgrade | 2/26/2020 | Approved | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 3/12/2020 | Not Ready for Inspection | EVAN COOPER |
| BUILDING-Rough-Frame | 3/24/2020 | Partial Approval | EVAN COOPER |
| PLUMBING-Rough | 3/24/2020 | Partial Approval | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 4/16/2020 | Partial Approval | EVAN COOPER |
| Shower Pan | 4/16/2020 | Not Ready for Inspection | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 4/23/2020 | Partial Approval | OGANES TARAKHCHYAN |
| Deck | 4/28/2020 | No Access for Inspection | EVAN COOPER |
| Deputy Wood Construction | 5/13/2020 | Conditional Approval | EVAN COOPER |
| BUILDING-Rough-Frame | 5/26/2020 | Partial Approval | EVAN COOPER |
| ELECTRICAL-Rough | 5/26/2020 | Approved | EVAN COOPER |
| Green Building Rough | 5/26/2020 | Not Ready for Inspection | EVAN COOPER |
| HVAC-Rough | 5/26/2020 | Not Ready for Inspection | EVAN COOPER |
| METHANE-Rough | 5/26/2020 | Approved | EVAN COOPER |
| PLUMBING-Rough | 5/26/2020 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 6/3/2020 | Approved | CRAIG DAVIS |
| Interior/Exterior Lathing | 6/23/2020 | Partial Approval | EVAN COOPER |
| Insulation | 6/26/2020 | Approved | EVAN COOPER |
| Drywall Nailing | 6/30/2020 | Approved | EVAN COOPER |
| Green Building Rough | 6/30/2020 | Approved | EVAN COOPER |
| Service/Power Release | 2/18/2021 | Not Ready for Inspection | EVAN COOPER |
| ELECTRICAL-Final | 3/22/2021 | Not Ready for Inspection | EVAN COOPER |
| HVAC-Final | 3/22/2021 | Not Ready for Inspection | EVAN COOPER |
| PLUMBING-Final | 3/22/2021 | Not Ready for Inspection | EVAN COOPER |
| Service/Power Release | 3/22/2021 | Corrections Issued | EVAN COOPER |
| Service/Power Release | 4/8/2021 | Approved | EVAN COOPER |
| ELECTRICAL-Final | 4/22/2021 | Approved | EVAN COOPER |
| HVAC-Final | 4/22/2021 | Approved | EVAN COOPER |
| PLUMBING-Final | 4/22/2021 | Approved | EVAN COOPER |
| BUILDING-Rough-Frame | 5/24/2021 | Approved | EVAN COOPER |
| Final | 5/24/2021 | No Access for Inspection | EVAN COOPER |
| Footing/Foundation/Slab | 5/24/2021 | Approved | EVAN COOPER |
| Green Building Final | 5/24/2021 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 5/24/2021 | SGSOV Approved | EVAN COOPER |
| Smoke Detectors | 5/24/2021 | Approved | EVAN COOPER |
| Final | 5/26/2021 | OK to Issue CofO | EVAN COOPER |