4073 N WILKINSON AVE 91604

Certificate Information: 4073 N WILKINSON AVE 91604

Application / Permit
19014-20000-06594
Plan Check / Job No.
B19VN21063
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADD 20'-0"X 18'-25" SECOND FLOOR TO & CONVERT 20'-0"X 18'-08" GARAGE TO ACCESSORY DWELLING UNIT PER AB 494 & SB 229. ALL WORL PER ENGINEERING.
Permit Issued
Issued on 6/4/2020
Issuing Office
Current Status
CofO Issued on 3/23/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/4/2019 APPLICANT
Assigned to Plan Check Engineer 1/2/2020 PARISA ZAHABI
Corrections Issued 1/8/2020 PARISA ZAHABI
Quality Review Completed 1/17/2020 OMID HEDAYAT
Building Plans Picked Up 2/21/2020 APPLICANT
Green Plans Picked Up 2/21/2020 APPLICANT
Plan Check Approved 5/22/2020 PARISA ZAHABI
Issued 6/4/2020 APPLICANT
CofO in Progress 8/23/2021 ARAM AVEDISIAN
Permit Finaled 3/23/2022 DANIEL ORRANTE
CofO Issued 3/23/2022 DANIEL ORRANTE
Permit Finaled 3/23/2022 DANIEL ORRANTE

Permit Application Clearance Information

Hydrant and Access approval Cleared 3/2/2020 GEORGE SUCHAND
Construction near power lines Cleared 5/3/2020 RIDWAN HARDY
Green Code Cleared 5/14/2020 AARON COSTA
Address approval Cleared 5/15/2020 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 5/15/2020 JOHN TRIANTAFYLLOS
Roof/Waste drainage to street Cleared 5/15/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 5/15/2020 JOHN TRIANTAFYLLOS
ZI Cleared 5/19/2020 LAUREN PADICK

Contact Information

Contractor J M Construction; Lic. No.: 772804-B 11726 RIVERSIDE DR      VALLEY VILLAGE, CA 91607
Engineer Garcia,, Francisco Diaz; Lic. No.: C88029 7333 RANCHITO AVE      VAN NUYS, CA 91405

Inspector Information

CHRISTOPHE COCHRAN, (818) 374-1165 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/17/2020 Approved ARAM AVEDISIAN
PLUMBING-Rough 6/25/2020 Partial Approval ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 7/16/2020 Partial Approval RAYMOND KEHOE
BUILDING-Rough-Frame 9/9/2020 Partial Approval ARAM AVEDISIAN
ELECTRICAL-Rough 9/9/2020 Approved ARAM AVEDISIAN
Green Building Rough 9/9/2020 Approved ARAM AVEDISIAN
PLUMBING-Rough 9/9/2020 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 9/18/2020 Partial Approval ARAM AVEDISIAN
Insulation 9/22/2020 Approved ARAM AVEDISIAN
Drywall Nailing 9/24/2020 Approved ARAM AVEDISIAN
Shower Pan 11/2/2020 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 11/9/2020 Partial Approval ARAM AVEDISIAN
Gas Test 4/1/2021 Approved ARAM AVEDISIAN
BUILDING-Rough-Frame 7/14/2021 Approved ARAM AVEDISIAN
Final 7/14/2021 Corrections Issued ARAM AVEDISIAN
Green Building Final 7/14/2021 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 7/14/2021 SGSOV Approved ARAM AVEDISIAN
Smoke Detectors 7/14/2021 Not Ready for Inspection ARAM AVEDISIAN
ELECTRICAL-Final 8/23/2021 Approved ARAM AVEDISIAN
Final 8/23/2021 OK to Issue CofO ARAM AVEDISIAN
HVAC-Final 8/23/2021 Approved ARAM AVEDISIAN
PLUMBING-Final 8/23/2021 Approved ARAM AVEDISIAN
Smoke Detectors 8/23/2021 Approved ARAM AVEDISIAN