10325 N SILVERTON AVE 91042
Certificate Information: 10325 N SILVERTON AVE 91042
- Application / Permit
- 19014-20000-06590
- Plan Check / Job No.
- B19VN21055
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED (33'-3" X 38'-5") IRREGULAR SHAPED ADDITION TO (E) SFD. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 2/7/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/15/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/4/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/12/2019 | RAPHAEL ROSAS |
| Corrections Issued | 12/14/2019 | RAPHAEL ROSAS |
| Green Plans Picked Up | 12/17/2019 | APPLICANT |
| Quality Review Completed | 12/18/2019 | CHON CHIO KUO |
| Building Plans Picked Up | 12/18/2019 | APPLICANT |
| Applicant returned to address corrections | 1/15/2020 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 2/3/2020 | RAPHAEL ROSAS |
| Plan Check Approved | 2/7/2020 | RAPHAEL ROSAS |
| Issued | 2/7/2020 | LADBS |
| CofO in Progress | 1/27/2021 | MATTHEW NELSON |
| Permit Finaled | 5/15/2021 | MICHAEL SMITH |
| CofO Issued | 5/15/2021 | MICHAEL SMITH |
| Permit Finaled | 5/15/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/13/2020 | GABRIEL ROBLES |
| Green Code | Cleared | 1/13/2020 | RAPHAEL ROSAS |
| Low Impact Development | Cleared | 1/13/2020 | AMMAR ELTAWIL |
| Roof/Waste drainage to street | Cleared | 1/13/2020 | GABRIEL ROBLES |
| Private sewage disp. approval | Cleared | 1/24/2020 | PATRICK MISCHLICH |
| GPI Written Notices | Cleared | 2/7/2020 | RAPHAEL ROSAS |
| Grading Pre-Inspection | Cleared | 2/7/2020 | PATRICK MISCHLICH |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Basma,, Ali J; Lic. No.: C53080 | 21500 WYANDOTTE ST 106 CANOGA PARK, CA 91303 |
Inspector Information
| NICHOLAS TROWBRIDGE, (818) 374-1174 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/2/2020 | Corrections Issued | MATTHEW NELSON |
| Footing/Foundation/Slab | 3/2/2020 | Corrections Issued | MATTHEW NELSON |
| Special/Order Compliance | 3/2/2020 | Approved | PIERRE VEGA |
| Footing/Foundation/Slab | 3/4/2020 | Partial Inspection | MATTHEW NELSON |
| Special/Order Compliance | 3/4/2020 | Approved | PIERRE VEGA |
| Deputy Drilled-In Anchors | 3/18/2020 | Partial Approval | PIERRE VEGA |
| Footing/Foundation/Slab | 3/19/2020 | Partial Inspection | MATTHEW NELSON |
| BUILDING-Rough-Frame | 5/6/2020 | Not Ready for Inspection | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 5/6/2020 | Approved | MATTHEW NELSON |
| Green Building Rough | 5/6/2020 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 5/27/2020 | Approved | MATTHEW NELSON |
| ELECTRICAL-Rough | 5/27/2020 | Approved | MATTHEW NELSON |
| HVAC-Rough | 5/27/2020 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 5/27/2020 | Approved | MATTHEW NELSON |
| Special/Order Compliance | 5/27/2020 | Approved | BEAU COLLINS |
| Insulation | 6/3/2020 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 6/3/2020 | Approved | MATTHEW NELSON |
| Drywall Nailing | 6/9/2020 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 7/14/2020 | Approved | MATTHEW NELSON |
| Final | 8/21/2020 | Corrections Issued | MATTHEW NELSON |
| Footing/Foundation/Slab | 8/21/2020 | Corrections Issued | MATTHEW NELSON |
| Green Building Final | 8/21/2020 | Corrections Issued | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 8/21/2020 | SGSOV Not Ready | MATTHEW NELSON |
| Smoke Detectors | 8/21/2020 | Corrections Issued | MATTHEW NELSON |
| ELECTRICAL-Final | 9/8/2020 | Partial Inspection | MATTHEW NELSON |
| PLUMBING-Final | 9/8/2020 | Partial Inspection | MATTHEW NELSON |
| ELECTRICAL-Final | 1/26/2021 | Approved | MATTHEW NELSON |
| Final | 1/26/2021 | OK to Issue CofO | MATTHEW NELSON |
| Footing/Foundation/Slab | 1/26/2021 | Approved | MATTHEW NELSON |
| Green Building Final | 1/26/2021 | Approved | MATTHEW NELSON |
| HVAC-Final | 1/26/2021 | Approved | MATTHEW NELSON |
| PLUMBING-Final | 1/26/2021 | Approved | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 1/26/2021 | SGSOV Approved | MATTHEW NELSON |
| Smoke Detectors | 1/26/2021 | Approved | MATTHEW NELSON |