13516 W RANGOON ST 91331
Certificate Information: 13516 W RANGOON ST 91331
- Application / Permit
- 19014-20000-06554
- Plan Check / Job No.
- B19VN20925
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 28'-7" X 16'-9" ADDITION & CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. ALL WORK DONE PER WFPP.
- Permit Issued
- Issued on 6/25/2020
- Issuing Office
- Current Status
- CofO Issued on 5/11/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/3/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/3/2019 | ARTIN ZARUKIAN |
| Corrections Issued | 12/3/2019 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 12/6/2019 | APPLICANT |
| Plan Check Approved | 6/25/2020 | ARTIN ZARUKIAN |
| Issued | 6/25/2020 | APPLICANT |
| CofO in Progress | 2/23/2021 | CHRISTOPHE COCHRAN |
| CofO in Progress | 2/23/2021 | CHRISTOPHE COCHRAN |
| CofO Issued | 5/11/2021 | MICHAEL SMITH |
| Permit Finaled | 5/11/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Construction near power lines | Cleared | 1/14/2020 | RIDWAN HARDY |
| Address approval | Cleared | 3/16/2020 | LEE GUILBEAUX |
| Low Impact Development | Cleared | 6/9/2020 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 6/10/2020 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 6/16/2020 | GABRIEL ROBLES |
| Sewer availability | Cleared | 6/16/2020 | GABRIEL ROBLES |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/29/2020 | Not Ready for Inspection | WILLIAM KUEHN |
| PLUMBING-Rough | 6/29/2020 | Partial Inspection | WILLIAM KUEHN |
| Sewer | 6/29/2020 | Approved | WILLIAM KUEHN |
| Footing/Foundation/Slab | 7/6/2020 | Approved | WILLIAM KUEHN |
| BUILDING-Rough-Frame | 7/28/2020 | Not Ready for Inspection | GREGG CUMMINGS |
| Green Building Rough | 7/28/2020 | Not Ready for Inspection | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 8/7/2020 | Corrections Issued | GREGG CUMMINGS |
| ELECTRICAL-Rough | 8/7/2020 | Corrections Issued | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 8/7/2020 | Approved | GREGG CUMMINGS |
| Green Building Rough | 8/7/2020 | Not Ready for Inspection | GREGG CUMMINGS |
| HVAC-Rough | 8/7/2020 | Approved | GREGG CUMMINGS |
| PLUMBING-Rough | 8/7/2020 | Corrections Issued | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 8/17/2020 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Rough | 8/17/2020 | Approved | GREGG CUMMINGS |
| Green Building Rough | 8/17/2020 | Approved | GREGG CUMMINGS |
| PLUMBING-Rough | 8/17/2020 | Approved | GREGG CUMMINGS |
| Insulation | 8/25/2020 | Approved | GREGG CUMMINGS |
| Interior/Exterior Lathing | 8/25/2020 | Approved | GREGG CUMMINGS |
| Drywall Nailing | 8/28/2020 | Approved | GREGG CUMMINGS |
| Interior/Exterior Lathing | 8/28/2020 | Approved | GREGG CUMMINGS |
| PLUMBING-Rough | 9/1/2020 | Corrections Issued | GREGG CUMMINGS |
| Shower Pan | 9/1/2020 | Approved | GREGG CUMMINGS |
| Final | 11/19/2020 | Corrections Issued | GREGG CUMMINGS |
| Green Building Final | 11/19/2020 | Corrections Issued | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 11/19/2020 | SGSOV Approved | GREGG CUMMINGS |
| Smoke Detectors | 11/19/2020 | Approved | GREGG CUMMINGS |
| Final | 11/25/2020 | Not Ready for Inspection | JOHN HAYES |
| Green Building Final | 11/25/2020 | Not Ready for Inspection | JOHN HAYES |
| Final | 12/4/2020 | Partial Inspection | GREGG CUMMINGS |
| Green Building Final | 12/4/2020 | Approved | GREGG CUMMINGS |
| Final | 2/23/2021 | OK to Issue CofO | CHRISTOPHE COCHRAN |