6707 S 2ND AVE 90043

Certificate Information: 6707 S 2ND AVE 90043

Application / Permit
19014-20000-06553
Plan Check / Job No.
B19VN20922
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADD IRREGULAR SHAPE 20.83' X 21.07'FOR 2 BEDROOMS AND 1 BATHROOM PER DESIGN
Permit Issued
Issued on 1/31/2020
Issuing Office
South Los Angeles
Current Status
CofO Issued on 3/24/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/3/2019 APPLICANT
Assigned to Plan Check Engineer 12/3/2019 ALDOUS CHIC
Corrections Issued 12/3/2019 ALDOUS CHIC
Plan Check Approved 12/30/2019 ALDOUS CHIC
Issued 1/31/2020 LADBS
CofO in Progress 1/26/2022 FREDDIE RIVERA
CofO Issued 3/24/2022 DEROLD HAUFF
Permit Finaled 3/24/2022 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 12/3/2019 ADRIAN CASTRO
Sewer availability Cleared 12/3/2019 ADRIAN CASTRO
Low Impact Development Cleared 12/30/2019 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 12/30/2019 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,
Engineer Gallardo,, Samuel Pigao; Lic. No.: C68174 23013 BERENDO AVE      TORRANCE, CA 90502

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/3/2020 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 6/16/2020 Partial Approval FREDDIE RIVERA
PLUMBING-Rough 6/16/2020 Partial Approval FREDDIE RIVERA
BUILDING-Rough-Frame 8/24/2020 Corrections Issued FREDDIE RIVERA
ELECTRICAL-Rough 8/24/2020 Approved FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 8/24/2020 Partial Approval FREDDIE RIVERA
Green Building Rough 8/24/2020 Approved FREDDIE RIVERA
PLUMBING-Rough 8/24/2020 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 8/31/2020 Approved FREDDIE RIVERA
Interior/Exterior Lathing 10/14/2020 Approved FREDDIE RIVERA
Insulation 10/28/2020 Approved FREDDIE RIVERA
Drywall Nailing 11/2/2020 Approved FREDDIE RIVERA
Interior/Exterior Lathing 11/2/2020 Approved FREDDIE RIVERA
Shower Pan 11/2/2020 Approved FREDDIE RIVERA
Final 5/10/2021 Corrections Issued FREDDIE RIVERA
Green Building Final 5/10/2021 Approved FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 5/10/2021 SGSOV Approved FREDDIE RIVERA
Smoke Detectors 5/10/2021 Approved FREDDIE RIVERA
Final 1/10/2022 Conditional Approval FREDDIE RIVERA