1554 N LABAIG AVE 90028
Certificate Information: 1554 N LABAIG AVE 90028
- Application / Permit
- 19014-20000-06543
- Plan Check / Job No.
- B19VN20896
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADD 13' X 5'-6" TO EXISTING SINGLE FAMILY DWELLING; INTERIOR REMODEL; RECONFIGURE FLOOR PLAN
- Permit Issued
- Issued on 2/4/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 2/6/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/2/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/3/2019 | SELLA BENYAMIN |
| Corrections Issued | 12/4/2019 | SELLA BENYAMIN |
| Building Plans Picked Up | 12/6/2019 | APPLICANT |
| Plan Check Approved | 2/4/2020 | SELLA BENYAMIN |
| Issued | 2/4/2020 | LADBS |
| CofO in Progress | 11/18/2020 | BRIAN SULLIVAN |
| Permit Finaled | 2/6/2021 | DEROLD HAUFF |
| CofO Issued | 2/6/2021 | DEROLD HAUFF |
| Permit Finaled | 2/6/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| "Q" conditions | Cleared | 12/10/2019 | DAISY BENICIA |
| Address approval | Cleared | 12/10/2019 | JOHN LIN |
| Eng Process Fee Ord 176,300 | Cleared | 12/10/2019 | JOHN LIN |
| Sewer availability | Cleared | 12/10/2019 | JOHN LIN |
| Historic monument | Cleared | 12/13/2019 | LAMBERT GIESSINGER |
| ZI | Cleared | 1/23/2020 | GISELLE CORELLA |
| ZI | Cleared | 1/23/2020 | VINCENT QUITORIANO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Helou,, Dawn Renee; Lic. No.: C52361 | 22701 ERWIN ST WOODLAND HILLS, CA 91367 |
Inspector Information
| CRAIG VAUGHAN, (213) 202-3250 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/5/2020 | Approved | RAUL BARAJAS |
| PLUMBING-Rough | 3/11/2020 | Corrections Issued | ROBERT CORNELL |
| Floor/Roof Diaphrgm/Shear Wall | 3/17/2020 | Approved | ROBERT CORNELL |
| BUILDING-Rough-Frame | 3/25/2020 | Partial Approval | ROBERT CORNELL |
| Deputy Wood Construction | 3/25/2020 | Approved | ROBERT CORNELL |
| Green Building Rough | 3/25/2020 | Approved | ROBERT CORNELL |
| ELECTRICAL-Rough | 4/13/2020 | Approved | BRIAN SULLIVAN |
| Shower Pan | 4/13/2020 | Approved | BRIAN SULLIVAN |
| ELECTRICAL-Final | 4/27/2020 | Corrections Issued | RAUL BARAJAS |
| Interior/Exterior Lathing | 5/11/2020 | Partial Approval | CHRISTOPHER DELLEFIELD |
| HVAC-Rough | 5/21/2020 | Approved | RAUL BARAJAS |
| Sewer | 5/27/2020 | Approved | RAUL BARAJAS |
| Insulation | 6/3/2020 | Approved | BRIAN SULLIVAN |
| Drywall Nailing | 6/8/2020 | Approved | BRIAN SULLIVAN |
| Underground Mechanical | 6/8/2020 | Approved | BRIAN SULLIVAN |
| ELECTRICAL-Rough | 6/15/2020 | Not Ready for Inspection | BRIAN SULLIVAN |
| Interior/Exterior Lathing | 6/15/2020 | Approved | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 10/30/2020 | Approved | BRIAN SULLIVAN |
| Final | 10/30/2020 | Corrections Issued | BRIAN SULLIVAN |
| Green Building Final | 10/30/2020 | Approved | BRIAN SULLIVAN |
| SGSOV-Seismic Gas S/O Valve | 10/30/2020 | SGSOV Not Ready | BRIAN SULLIVAN |
| Smoke Detectors | 10/30/2020 | Approved | BRIAN SULLIVAN |
| Final | 11/18/2020 | OK to Issue CofO | BRIAN SULLIVAN |
| SGSOV-Seismic Gas S/O Valve | 11/18/2020 | SGSOV Approved | BRIAN SULLIVAN |