14232 W HAMLIN ST 91401

Certificate Information: 14232 W HAMLIN ST 91401

Application / Permit
19014-20000-06541
Plan Check / Job No.
B19VN20888
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
MAJOR REMODEL TO REBUILD 40' X 63'-10" SINGLE FAMILY DWELLING W/ 18'-7" X 20'5" ATTACHED 2-CAR GARAGE & MAINTAIN 9' OF (E) WALL & FOOTING ON EAST SIDE. FIRE SPRINKLER REQUIRED NFPA-13R.
Permit Issued
Issued on 9/30/2020
Issuing Office
Current Status
CofO Issued on 12/17/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/2/2019 APPLICANT
Permit Expired 12/5/2019 ANTHONY GIANNINI
Assigned to Plan Check Engineer 12/26/2019 SERGIO MUNIZ
Green Plans Picked Up 12/30/2019 APPLICANT
Corrections Issued 1/2/2020 SERGIO MUNIZ
Quality Review Completed 1/13/2020 OMID HEDAYAT
Building Plans Picked Up 1/23/2020 APPLICANT
Applicant returned to address corrections 7/28/2020 SERGIO MUNIZ
Applicant returned to address corrections 8/27/2020 SERGIO MUNIZ
Plan Check Approved 9/2/2020 SERGIO MUNIZ
Issued 9/30/2020 APPLICANT
CofO in Progress 11/10/2022 RICHARD DOCKUS
Permit Finaled 12/17/2022 MICHAEL SMITH
CofO Issued 12/17/2022 MICHAEL SMITH
Permit Finaled 12/17/2022 MICHAEL SMITH

Permit Application Clearance Information

Green Code Cleared 2/24/2020 AARON COSTA
Eng Process Fee Ord 176,300 Cleared 2/25/2020 APEKSHYA BAJRACHARYA
Sewer availability Cleared 2/25/2020 APEKSHYA BAJRACHARYA
Low Impact Development Cleared 6/26/2020 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 6/30/2020 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Special/Order Compliance 12/6/2019 Permit Expired ARAM AVEDISIAN
Pre-Inspection 2/10/2021 Approved VINCENT HANLEY
PLUMBING-Rough 5/17/2021 Partial Approval ARTHUR SARGSYAN
Footing/Foundation/Slab 6/1/2021 Approved JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 7/26/2021 Not Ready for Inspection CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 7/29/2021 Approved JENNIFER RABUCHIN
Green Building Rough 7/29/2021 Not Ready for Inspection JENNIFER RABUCHIN
ELECTRICAL-Rough 9/9/2021 Approved RICHARD DOCKUS
HVAC-Rough 9/9/2021 Approved RICHARD DOCKUS
PLUMBING-Rough 9/9/2021 Approved RICHARD DOCKUS
BUILDING-Rough-Frame 10/4/2021 Partial Approval RICHARD DOCKUS
Green Building Rough 10/4/2021 Approved RICHARD DOCKUS
Interior/Exterior Lathing 10/25/2021 No Access for Inspection ALAN MORELOS
Special/Order Compliance 10/25/2021 No Access for Inspection JESUS RODRIGUEZ
Interior/Exterior Lathing 10/28/2021 Partial Approval ALAN MORELOS
Special/Order Compliance 10/28/2021 Not Ready for Inspection ALAN MORELOS
BUILDING-Rough-Frame 11/5/2021 Approved RICHARD DOCKUS
Insulation 11/5/2021 Approved RICHARD DOCKUS
Drywall Nailing 11/22/2021 Conditional Approval JESUS RODRIGUEZ
Shower Pan 12/23/2021 Approved RICHARD DOCKUS
Drywall Nailing 12/28/2021 Corrections Issued ALAN MORELOS
Interior/Exterior Lathing 12/28/2021 Approved ALAN MORELOS
Drywall Nailing 12/30/2021 Approved RICHARD DOCKUS
Gas Test 6/22/2022 Approved RICHARD DOCKUS
ELECTRICAL-Final 10/3/2022 Corrections Issued RICHARD DOCKUS
ELECTRICAL-Final 10/11/2022 Approved RICHARD DOCKUS
PLUMBING-Final 10/11/2022 Approved RICHARD DOCKUS
HVAC-Final 10/19/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Final 11/9/2022 OK to Issue CofO RICHARD DOCKUS
Green Building Final 11/9/2022 Approved RICHARD DOCKUS
SGSOV-Seismic Gas S/O Valve 11/9/2022 SGSOV Approved RICHARD DOCKUS
Smoke Detectors 11/9/2022 Approved RICHARD DOCKUS