19125 W WELBY WAY 91335

Certificate Information: 19125 W WELBY WAY 91335

Application / Permit
19014-20000-06509
Plan Check / Job No.
B19VN20826
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) GARAGE AND ADD 12' X 19'2" TO NEW ADU PER AB 494 AND SB 229.
Permit Issued
Issued on 2/5/2020
Issuing Office
Valley
Current Status
CofO Issued on 7/31/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/2/2019 APPLICANT
Assigned to Plan Check Engineer 12/2/2019 PINANK PATEL
Corrections Issued 12/2/2019 PINANK PATEL
Plan Check Approved 2/4/2020 ARTIN ZARUKIAN
Issued 2/5/2020 LADBS
CofO in Progress 7/29/2020 VINCENT HANLEY
CofO Issued 7/31/2020 DONALD SUNSERI
Permit Finaled 7/31/2020 DONALD SUNSERI

Permit Application Clearance Information

Address approval Cleared 12/2/2019 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 12/2/2019 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 12/2/2019 LEE GUILBEAUX
Sewer availability Cleared 12/2/2019 LEE GUILBEAUX
Construction near power lines Cleared 2/4/2020 OSCAR CASTRO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 2/25/2020 Partial Approval VINCENT HANLEY
Deputy Drilled-In Anchors 2/27/2020 Approved VINCENT HANLEY
Excavation/Setback/Form/Re-Bar 3/2/2020 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 4/17/2020 Partial Approval VINCENT HANLEY
Green Building Rough 4/17/2020 Not Ready for Inspection VINCENT HANLEY
PLUMBING-Rough 4/22/2020 Partial Approval VINCENT HANLEY
Sewer 4/22/2020 Approved VINCENT HANLEY
BUILDING-Rough-Frame 5/12/2020 Approved VINCENT HANLEY
ELECTRICAL-Rough 5/12/2020 Approved VINCENT HANLEY
Green Building Rough 5/12/2020 Approved VINCENT HANLEY
HVAC-Rough 5/12/2020 Approved VINCENT HANLEY
PLUMBING-Rough 5/12/2020 Approved VINCENT HANLEY
Underground Mechanical 5/12/2020 Partial Approval VINCENT HANLEY
Insulation 5/19/2020 Approved VINCENT HANLEY
Interior/Exterior Lathing 5/19/2020 Partial Approval VINCENT HANLEY
Drywall Nailing 5/27/2020 Approved VINCENT HANLEY
Interior/Exterior Lathing 5/27/2020 Approved VINCENT HANLEY
PLUMBING-Rough 5/27/2020 Approved VINCENT HANLEY
Final 7/24/2020 Corrections Issued VINCENT HANLEY
Footing/Foundation/Slab 7/24/2020 Approved VINCENT HANLEY
Green Building Final 7/24/2020 Approved VINCENT HANLEY
HVAC-Final 7/24/2020 Approved VINCENT HANLEY
PLUMBING-Final 7/24/2020 Corrections Issued VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 7/24/2020 SGSOV Approved VINCENT HANLEY
Smoke Detectors 7/24/2020 Approved VINCENT HANLEY
ELECTRICAL-Final 7/29/2020 Approved VINCENT HANLEY
Final 7/29/2020 OK to Issue CofO VINCENT HANLEY
PLUMBING-Final 7/29/2020 Approved VINCENT HANLEY