5248 N SYLMAR AVE 91401

Certificate Information: 5248 N SYLMAR AVE 91401

Application / Permit
19014-20000-06496
Plan Check / Job No.
B19VN20798
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION to include a new 18'5"x40'2" second story, a 12'1"x18'5" patio cover (second story overhang). ALTERATION to relocate master bedroom, create a new bedroom, two full bathrooms, and a half bathroom.
Permit Issued
Issued on 1/16/2020
Issuing Office
Valley
Current Status
CofO Issued on 12/26/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/27/2019 APPLICANT
Green Plans Picked Up 12/10/2019 APPLICANT
Assigned to Plan Check Engineer 12/12/2019 LUIS RINCON
Corrections Issued 12/14/2019 LUIS RINCON
Quality Review Completed 12/19/2019 CHON CHIO KUO
Building Plans Picked Up 12/23/2019 APPLICANT
Plan Check Approved 1/16/2020 LUIS RINCON
Issued 1/16/2020 LADBS
CofO in Progress 9/10/2020 MICHAEL SMITH
CofO Issued 12/26/2020 MICHAEL SMITH
Permit Finaled 12/26/2020 MICHAEL SMITH

Permit Application Clearance Information

Green Code Cleared 12/30/2019 DAVID MATSON
Eng Process Fee Ord 176,300 Cleared 1/8/2020 EMIL KYUPELYAN
Low Impact Development Cleared 1/8/2020 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 1/8/2020 EMIL KYUPELYAN
Sewer availability Cleared 1/8/2020 EMIL KYUPELYAN

Contact Information

Contractor Owner-Builder       ,
Engineer Karapetian,, Arbi; Lic. No.: C79953 21520 BURBANK BLVD APT 219      WOODLAND HILLS, CA 91367

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/26/2020 Conditional Approval MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 3/9/2020 Partial Approval MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 3/24/2020 Partial Approval MISAEL ESPARZA
BUILDING-Rough-Frame 4/14/2020 Corrections Issued MISAEL ESPARZA
Green Building Rough 4/14/2020 Not Ready for Inspection MISAEL ESPARZA
PLUMBING-Rough 4/14/2020 Approved MISAEL ESPARZA
Rough-Elec/Plmb/HVAC 4/14/2020 Partial Approval MISAEL ESPARZA
Special/Order Compliance 4/14/2020 Approved GREGG CUMMINGS
BUILDING-Rough-Frame 4/16/2020 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Rough 4/16/2020 Approved MISAEL ESPARZA
HVAC-Rough 4/16/2020 Approved MISAEL ESPARZA
Interior/Exterior Lathing 4/16/2020 Partial Approval MISAEL ESPARZA
Shower Pan 4/16/2020 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 4/17/2020 Approved MISAEL ESPARZA
Interior/Exterior Lathing 4/17/2020 Partial Approval MISAEL ESPARZA
Insulation 4/21/2020 Approved MISAEL ESPARZA
Interior/Exterior Lathing 4/21/2020 Approved MISAEL ESPARZA
Drywall Nailing 4/27/2020 Approved MISAEL ESPARZA
Green Building Rough 4/27/2020 Approved MISAEL ESPARZA
ELECTRICAL-Final 9/9/2020 Approved WILLIAM KUEHN
Final 9/9/2020 OK to Issue CofO WILLIAM KUEHN
Footing/Foundation/Slab 9/9/2020 Approved WILLIAM KUEHN
Green Building Final 9/9/2020 Approved WILLIAM KUEHN
HVAC-Final 9/9/2020 Approved WILLIAM KUEHN
PLUMBING-Final 9/9/2020 Approved WILLIAM KUEHN
SGSOV-Seismic Gas S/O Valve 9/9/2020 SGSOV Approved WILLIAM KUEHN
Smoke Detectors 9/9/2020 Approved WILLIAM KUEHN