4427 W GAINSBOROUGH AVE 90027
Certificate Information: 4427 W GAINSBOROUGH AVE 90027
- Application / Permit
- 19014-20000-06463
- Plan Check / Job No.
- B19VN20733
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 2ND FLOOR 23'-10"X 26'-6" IRREGULAR SHAPED ADDITION WITH BALCONY TO (E) SINGLE FAMILY DWELLING ALL WORK PER ENG
- Permit Issued
- Issued on 1/24/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/24/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/26/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/26/2019 | SEWADA ZADOORIAN MILAGARDI |
| Green Plans Picked Up | 12/30/2019 | APPLICANT |
| Corrections Issued | 12/31/2019 | SEWADA ZADOORIAN MILAGARDI |
| Quality Review Completed | 1/9/2020 | OMID HEDAYAT |
| Building Plans Picked Up | 1/9/2020 | APPLICANT |
| Plan Check Approved | 1/24/2020 | SEWADA ZADOORAN MILAGARDI |
| Issued | 1/24/2020 | LADBS |
| CofO in Progress | 9/1/2020 | JOSEPH MCGARRY |
| Permit Finaled | 9/24/2020 | DEROLD HAUFF |
| CofO Issued | 9/24/2020 | DEROLD HAUFF |
| Permit Finaled | 9/24/2020 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/16/2020 | JOHN LIN |
| Sewer availability | Cleared | 1/16/2020 | JOHN LIN |
| Green Code | Cleared | 1/22/2020 | MICHAEL AYERS |
| GPI Written Notices | Cleared | 1/24/2020 | SEWADA ZADOORAN MILAGARDI |
| Grading Pre-Inspection | Cleared | 1/24/2020 | SEWADA ZADOORAN MILAGARDI |
| Low Impact Development | Cleared | 1/24/2020 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 1/24/2020 | CELINA MORENO |
Contact Information
| Contractor | Doobek Inc; Lic. No.: 980653-B | 5308 DERRY AVE I-101, 102 AGOURA HILLS, CA 91301 |
| Engineer | Rhee,, Kyle; Lic. No.: C78215 | 2753 WAVERLY DR 403 LOS ANGELES, CA 90039 |
Inspector Information
| ENRIQUE MIRELES, (213) 202-3438 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 2/24/2020 | Partial Approval | JOSEPH MCGARRY |
| HVAC-Rough | 2/24/2020 | Partial Approval | JOSEPH MCGARRY |
| PLUMBING-Rough | 2/24/2020 | Partial Approval | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 2/26/2020 | Approved | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 4/1/2020 | Partial Approval | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 4/22/2020 | Partial Approval | JOSEPH MCGARRY |
| Shower Pan | 4/22/2020 | Partial Approval | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 4/27/2020 | Partial Approval | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Rough | 4/29/2020 | Partial Approval | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 4/29/2020 | Partial Inspection | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 5/8/2020 | Conditional Approval | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 5/8/2020 | Corrections Issued | JOSEPH MCGARRY |
| Green Building Rough | 5/8/2020 | Approved | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 5/15/2020 | Approved | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 5/15/2020 | Approved | JOSEPH MCGARRY |
| HVAC-Rough | 5/15/2020 | Approved | JOSEPH MCGARRY |
| Insulation | 5/15/2020 | Approved | JOSEPH MCGARRY |
| PLUMBING-Rough | 5/15/2020 | Approved | JOSEPH MCGARRY |
| Drywall Nailing | 5/21/2020 | Partial Approval | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 5/21/2020 | Approved | JOSEPH MCGARRY |
| Shower Pan | 5/21/2020 | Approved | JOSEPH MCGARRY |
| Drywall Nailing | 6/3/2020 | Approved | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 6/3/2020 | Corrections Issued | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 6/8/2020 | Partial Approval | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Final | 8/18/2020 | Approved | CHRIS CHRISTENSEN |
| Final | 8/18/2020 | Corrections Issued | CHRIS CHRISTENSEN |
| Green Building Final | 8/18/2020 | Approved | CHRIS CHRISTENSEN |
| HVAC-Final | 8/18/2020 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Final | 8/18/2020 | Approved | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 8/18/2020 | SGSOV Approved | CHRIS CHRISTENSEN |
| Smoke Detectors | 8/18/2020 | Approved | CHRIS CHRISTENSEN |
| Final | 9/1/2020 | OK to Issue CofO | JOSEPH MCGARRY |