8322-8324 S RAMSGATE AVE 90045

Certificate Information: 8322-8324 S RAMSGATE AVE 90045

Application / Permit
19014-20000-06455
Plan Check / Job No.
B19VN20718
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
16' X 25'6" IRR. SHAPE ADD TO SFD ALSO CONVERT GARAGE TO ACCESSORY DWELLING UNIT PER AB 494 & SB 229. ALL WORK PER ENGINEER.
Permit Issued
Issued on 12/17/2019
Issuing Office
Metro
Current Status
CofO Issued on 3/30/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/26/2019 APPLICANT
Assigned to Plan Check Engineer 11/27/2019 PINANK PATEL
Corrections Issued 12/2/2019 PINANK PATEL
Building Plans Picked Up 12/3/2019 APPLICANT
Plan Check Approved 12/17/2019 PINANK PATEL
Issued 12/17/2019 LADBS
CofO in Progress 1/5/2021 DAVID HEINE
Permit Finaled 3/30/2022 DANIEL ORRANTE
CofO Issued 3/30/2022 DANIEL ORRANTE
Permit Finaled 3/30/2022 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 12/9/2019 APEKSHYA BAJRACHARYA
Eng Process Fee Ord 176,300 Cleared 12/9/2019 APEKSHYA BAJRACHARYA
Grading Pre-Inspection Cleared 12/9/2019 BARTON HOLMES
Roof/Waste drainage to street Cleared 12/9/2019 APEKSHYA BAJRACHARYA
Sewer availability Cleared 12/9/2019 APEKSHYA BAJRACHARYA

Contact Information

Contractor Unlimited Construction & Remodeling Inc; Lic. No.: 1047565-B 8500 WILSHIRE BLVD STE 829      BEVERLY HILLS, CA 90211
Engineer Gosen,, James W; Lic. No.: C43590 15315 BLEDSOE ST      SYLMAR, CA 91342

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/21/2020 Corrections Issued JUAN VALENZUELA
Excavation/Setback/Form/Re-Bar 1/29/2020 Partial Approval JUAN VALENZUELA
Footing/Foundation/Slab 2/3/2020 Partial Approval CRAIG DAVIS
PLUMBING-Rough 2/3/2020 Corrections Issued CRAIG DAVIS
BUILDING-Rough-Frame 2/11/2020 Partial Approval JUAN VALENZUELA
Insulation 2/11/2020 Partial Approval JUAN VALENZUELA
PLUMBING-Rough 2/11/2020 Partial Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 2/12/2020 Partial Approval JUAN VALENZUELA
Green Building Rough 2/12/2020 Not Ready for Inspection JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 3/5/2020 Partial Approval DAVID HEINE
Rough-Elec/Plmb/HVAC 3/5/2020 Not Ready for Inspection DAVID HEINE
Wood Frame 3/5/2020 Partial Approval DAVID HEINE
BUILDING-Rough-Frame 3/16/2020 Not Ready for Inspection JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 3/16/2020 Partial Approval JUAN VALENZUELA
Green Building Rough 3/16/2020 Not Ready for Inspection JUAN VALENZUELA
HVAC-Rough 3/16/2020 Corrections Issued JUAN VALENZUELA
Rough-Elec/Plmb/HVAC 3/16/2020 Corrections Issued JUAN VALENZUELA
ELECTRICAL-Rough 3/18/2020 Approved DAVID HEINE
HVAC-Rough 3/18/2020 Approved DAVID HEINE
PLUMBING-Rough 3/18/2020 Approved DAVID HEINE
Wood Frame 3/18/2020 Partial Approval DAVID HEINE
BUILDING-Rough-Frame 3/23/2020 Conditional Approval JUAN VALENZUELA
Green Building Rough 3/23/2020 Approved JUAN VALENZUELA
Interior/Exterior Lathing 3/23/2020 Conditional Approval JUAN VALENZUELA
Insulation 4/2/2020 Approved JUAN VALENZUELA
Interior/Exterior Lathing 4/2/2020 Partial Approval JUAN VALENZUELA
Drywall Nailing 4/6/2020 Partial Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 4/6/2020 Approved JUAN VALENZUELA
Special/Order Compliance 4/6/2020 Approved JUAN VALENZUELA
Interior/Exterior Lathing 4/8/2020 Approved JUAN VALENZUELA
Shower Pan 4/8/2020 Approved JUAN VALENZUELA
Drywall Nailing 4/9/2020 Approved JUAN VALENZUELA
Sewer 5/1/2020 Approved JUAN VALENZUELA
BUILDING-Rough-Frame 8/12/2020 Approved JUAN VALENZUELA
Final 8/12/2020 Corrections Issued JUAN VALENZUELA
Footing/Foundation/Slab 8/12/2020 Approved JUAN VALENZUELA
Green Building Final 8/12/2020 Corrections Issued JUAN VALENZUELA
SGSOV-Seismic Gas S/O Valve 8/12/2020 SGSOV Not Ready JUAN VALENZUELA
Smoke Detectors 8/12/2020 Approved JUAN VALENZUELA
Final 9/8/2020 Not Ready for Inspection JUAN VALENZUELA
Green Building Final 9/8/2020 Approved JUAN VALENZUELA
SGSOV-Seismic Gas S/O Valve 9/8/2020 SGSOV Not Ready JUAN VALENZUELA
Final 9/28/2020 Corrections Issued JOHNNY MIRANDA
SGSOV-Seismic Gas S/O Valve 9/28/2020 SGSOV Not Ready JOHNNY MIRANDA
Final 10/22/2020 Corrections Issued JUAN VALENZUELA
SGSOV-Seismic Gas S/O Valve 10/22/2020 SGSOV Approved JUAN VALENZUELA
ELECTRICAL-Final 1/5/2021 Approved DAVID HEINE
Final 1/5/2021 OK to Issue CofO DAVID HEINE
Green Building Final 1/5/2021 Approved DAVID HEINE
HVAC-Final 1/5/2021 Approved DAVID HEINE
PLUMBING-Final 1/5/2021 Approved DAVID HEINE
Service/Power Release 1/5/2021 Approved DAVID HEINE