10081 N TELFAIR AVE 91331

Certificate Information: 10081 N TELFAIR AVE 91331

Application / Permit
19014-20000-06452
Plan Check / Job No.
B19VN20709
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADD (23'-4 1/4"x 18'-8 1/2") IRR SHAPE MASTER BED AND BATH & LAUNDRY TO (E) SINGLE FAMILY DWELLING. WORK PER LA STD WFPP.
Permit Issued
Issued on 7/29/2020
Issuing Office
Current Status
CofO Issued on 5/3/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/26/2019 APPLICANT
Assigned to Plan Check Engineer 12/26/2019 TROY DEGUZMAN
Green Plans Picked Up 12/30/2019 APPLICANT
Corrections Issued 1/2/2020 TROY DEGUZMAN
Quality Review Completed 1/2/2020 CHON CHIO KUO
Building Plans Picked Up 1/2/2020 APPLICANT
Applicant returned to address corrections 7/1/2020 TROY DEGUZMAN
Plan Check Approved 7/29/2020 TROY DEGUZMAN
Issued 7/29/2020 APPLICANT
CofO in Progress 4/27/2022 MICHEL ABAJAN
CofO Issued 5/3/2022 RONALD MYRICK
Permit Finaled 5/3/2022 RONALD MYRICK

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/27/2020 LEE GUILBEAUX
Sewer availability Cleared 1/27/2020 LEE GUILBEAUX
Low Impact Development Cleared 1/31/2020 MITESH PATEL
Roof/Waste drainage to street Cleared 1/31/2020 JEANIE LAM
Green Code Cleared 3/6/2020 DAVID MATSON

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/10/2021 Partial Inspection MICHEL ABAJAN
Deputy Drilled-In Anchors 5/5/2021 No Access for Inspection MICHEL ABAJAN
Footing/Foundation/Slab 6/2/2021 Approved MICHEL ABAJAN
METHANE-Barrier 6/2/2021 Approved MICHEL ABAJAN
METHANE-Subgrade 6/2/2021 Approved MICHEL ABAJAN
PLUMBING-Rough 8/2/2021 Partial Approval MICHEL ABAJAN
Sewer 8/2/2021 Partial Approval MICHEL ABAJAN
BUILDING-Rough-Frame 8/10/2021 Partial Inspection MICHEL ABAJAN
Green Building Rough 8/10/2021 Not Ready for Inspection MICHEL ABAJAN
METHANE-Rough 8/10/2021 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 8/26/2021 Corrections Issued MICHEL ABAJAN
ELECTRICAL-Rough 8/26/2021 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 8/26/2021 Corrections Issued MICHEL ABAJAN
Green Building Rough 8/26/2021 Not Ready for Inspection MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 9/17/2021 Partial Approval MICHEL ABAJAN
Green Building Rough 9/17/2021 Partial Inspection MICHEL ABAJAN
Insulation 9/22/2021 Approved MICHEL ABAJAN
Drywall Nailing 9/30/2021 Approved MICHEL ABAJAN
Interior/Exterior Lathing 9/30/2021 Approved MICHEL ABAJAN
Interior/Exterior Lathing 11/18/2021 Approved MICHEL ABAJAN
Pre-Inspection 12/10/2021 Partial Inspection MICHEL ABAJAN
Service/Power Release 2/3/2022 Corrections Issued MICHEL ABAJAN
BUILDING-Rough-Frame 4/27/2022 Approved MICHEL ABAJAN
ELECTRICAL-Final 4/27/2022 Approved MICHEL ABAJAN
Final 4/27/2022 OK to Issue CofO MICHEL ABAJAN
Green Building Final 4/27/2022 Approved MICHEL ABAJAN
Green Building Rough 4/27/2022 Approved MICHEL ABAJAN
HVAC-Final 4/27/2022 Approved MICHEL ABAJAN
PLUMBING-Final 4/27/2022 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 4/27/2022 SGSOV Approved MICHEL ABAJAN
Smoke Detectors 4/27/2022 Approved MICHEL ABAJAN