6350 W MARYLAND DR 90048

Certificate Information: 6350 W MARYLAND DR 90048

Application / Permit
19014-20000-06451
Plan Check / Job No.
B19VN20706
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Remove all on grade structures except portion of exterior walls, rebuild with additions of 19'11" x 9'7" and attached trellises/patio cover on ground floor and new irregular shape 36' x 46.5' 2nd floor
Permit Issued
Issued on 3/5/2020
Issuing Office
Valley
Current Status
CofO Issued on 10/15/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/26/2019 APPLICANT
Assigned to Plan Check Engineer 12/5/2019 ALDOUS CHIC
Corrections Issued 12/9/2019 ALDOUS CHIC
Quality Review Completed 12/10/2019 ABDUL CHEGENI
Building Plans Picked Up 12/10/2019 APPLICANT
Green Plans Picked Up 12/10/2019 APPLICANT
Applicant returned to address corrections 2/27/2020 ALDOUS CHIC
Applicant returned to address corrections 2/28/2020 ALDOUS CHIC
Plan Check Approved 3/2/2020 ALDOUS CHIC
Plan Check Approved 3/2/2020 ALDOUS CHIC
Issued 3/5/2020 LADBS
CofO in Progress 9/24/2024 ARAM AVEDISIAN
Permit Finaled 10/15/2024 RICHARD STEINBACH
CofO Issued 10/15/2024 RICHARD STEINBACH
Permit Finaled 10/15/2024 RICHARD STEINBACH

Permit Application Clearance Information

CPC Cleared 2/10/2020 VINCENT QUITORIANO
Eng Process Fee Ord 176,300 Cleared 2/10/2020 LEE GUILBEAUX
Sewer availability Cleared 2/10/2020 LEE GUILBEAUX
ZI Cleared 2/10/2020 VINCENT QUITORIANO
Green Code Cleared 2/13/2020 MICHAEL AYERS
Low Impact Development Cleared 2/19/2020 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 2/27/2020 JOHN TRIANTAFYLLOS

Contact Information

Architect Gilliam,, Jonathan; Lic. No.: C33995 15017 ARCHWOOD STREET      VAN NUYS, CA 91405
Contractor Rimon Adam; Lic. No.: 935565-B 444 N KILKEA      LOS ANGELES, CA 90048
Engineer Sivushenka,, Mikita; Lic. No.: C87698 5525 CANOGA AVE APT 208      WOODLAND HILLS, CA 91367

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Special/Order Compliance 4/17/2020 Corrections Issued KENNETH NAGLE
Special/Order Compliance 4/20/2020 Partial Inspection KENNETH NAGLE
BUILDING-Rough-Frame 4/22/2020 Not Ready for Inspection JOHNNY MIRANDA
Excavation/Setback/Form/Re-Bar 4/22/2020 Partial Approval JOHNNY MIRANDA
Footing/Foundation/Slab 4/22/2020 Partial Approval JOHNNY MIRANDA
Green Building Rough 4/22/2020 Not Ready for Inspection JOHNNY MIRANDA
METHANE-Barrier 4/22/2020 Approved JOHNNY MIRANDA
METHANE-Rough 4/22/2020 Approved JOHNNY MIRANDA
METHANE-Subgrade 4/22/2020 Approved JOHNNY MIRANDA
Underground Mechanical 4/22/2020 Approved JOHNNY MIRANDA
Special/Order Compliance 4/27/2020 Partial Inspection KENNETH NAGLE
Excavation/Setback/Form/Re-Bar 4/28/2020 Approved EVAN COOPER
Wood Frame 5/4/2020 Partial Approval EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 5/15/2020 Partial Approval EVAN COOPER
Wood Frame 5/15/2020 Partial Approval EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 6/29/2020 Partial Approval EVAN COOPER
PLUMBING-Rough 6/29/2020 Approved EVAN COOPER
Wood Frame 6/29/2020 Partial Approval EVAN COOPER
ELECTRICAL-Rough 7/27/2020 Approved EVAN COOPER
HVAC-Rough 7/27/2020 Corrections Issued EVAN COOPER
HVAC-Rough 8/5/2020 Approved EVAN COOPER
Shower Pan 8/5/2020 Approved EVAN COOPER
Interior/Exterior Lathing 8/13/2020 Partial Approval EVAN COOPER
Interior/Exterior Lathing 8/24/2020 Approved EVAN COOPER
Insulation 8/31/2020 Approved EVAN COOPER
Drywall Nailing 9/4/2020 Approved EVAN COOPER
Green Building Rough 9/4/2020 Approved EVAN COOPER
Sewer 3/11/2021 Approved EVAN COOPER
Underground Mechanical 3/11/2021 Partial Approval EVAN COOPER
Footing/Foundation/Slab 3/24/2021 Partial Approval KEVIN SARGSYAN
Masonry Wall/Backfill 3/24/2021 Partial Approval KEVIN SARGSYAN
Masonry Wall/Backfill 4/1/2021 Corrections Issued EVAN COOPER
Masonry Wall/Backfill 4/7/2021 Partial Approval EVAN COOPER
ELECTRICAL-Final 4/13/2021 Not Ready for Inspection EVAN COOPER
HVAC-Final 4/13/2021 Not Ready for Inspection EVAN COOPER
PLUMBING-Final 4/13/2021 Not Ready for Inspection EVAN COOPER
Service/Power Release 4/13/2021 Not Ready for Inspection EVAN COOPER
ELECTRICAL-Final 4/23/2021 Approved EVAN COOPER
Final 4/23/2021 Corrections Issued EVAN COOPER
HVAC-Final 4/23/2021 Approved EVAN COOPER
PLUMBING-Final 4/23/2021 Approved EVAN COOPER
Service/Power Release 4/23/2021 Approved EVAN COOPER
Gas Test 5/4/2021 Not Ready for Inspection EVAN COOPER
Service/Power Release 5/4/2021 Approved EVAN COOPER
Gas Test 5/11/2021 Approved EVAN COOPER
BUILDING-Rough-Frame 6/26/2024 Approved MICHAEL PELHAM
Final 6/26/2024 Corrections Issued MICHAEL PELHAM
Footing/Foundation/Slab 6/26/2024 Approved MICHAEL PELHAM
Green Building Final 6/26/2024 Approved MICHAEL PELHAM
SGSOV-Seismic Gas S/O Valve 6/26/2024 SGSOV Approved MICHAEL PELHAM
Smoke Detectors 6/26/2024 Approved MICHAEL PELHAM
Special/Order Compliance 7/2/2024 Approved MEL KHACHATOURIAN
Final 9/24/2024 OK to Issue CofO ARAM AVEDISIAN