1629 N KILBOURN ST 90065

Certificate Information: 1629 N KILBOURN ST 90065

Application / Permit
19014-20000-06449
Plan Check / Job No.
B19VN20704
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
ADD 15' X 6' TO EXPAND (E) DETACHED GARAGE AND REFRAME ROOF. ALL WORK PER WFPP.
Permit Issued
Issued on 6/1/2020
Issuing Office
Current Status
CofO Issued on 8/23/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/26/2019 APPLICANT
Assigned to Plan Check Engineer 11/26/2019 ROSENDO MEDINA
Corrections Issued 11/26/2019 ROSENDO MEDINA
Plan Check Approved 1/31/2020 RARES BODEA
No Progress 1/31/2020 RARES BODEA
Plan Check Approved 5/21/2020 JEROME MAGAT PALMA
Issued 6/1/2020 APPLICANT
CofO in Progress 8/13/2022 OSVALDO PARAMO
CofO in Progress 8/13/2022 OSVALDO PARAMO
Permit Finaled 8/23/2022 DEROLD HAUFF
CofO Issued 8/23/2022 DEROLD HAUFF
Permit Finaled 8/23/2022 DEROLD HAUFF

Permit Application Clearance Information

Grading Pre-Inspection Cleared 11/27/2019 KIRK LINKLATER
Eng Process Fee Ord 176,300 Cleared 1/31/2020 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 1/31/2020 LEE GUILBEAUX
Specific Plan Cleared 1/31/2020 OLGA RUANO

Contact Information

Contractor Preferred Home Builders Inc; Lic. No.: 773147-B 21204 VANOWEN STREET      CANOGA PARK, CA 91303

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/15/2020 Approved OSVALDO PARAMO
Grading Pre-Inspection 6/17/2020 Corrections Issued OSVALDO PARAMO
Footing/Foundation/Slab 8/16/2021 Not Ready for Inspection WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 9/28/2021 Partial Approval OSVALDO PARAMO
Wood Frame 9/28/2021 Partial Inspection OSVALDO PARAMO
Reinforced Masonry Frame 10/4/2021 Approved OSVALDO PARAMO
BUILDING-Rough-Frame 3/17/2022 Approved OSVALDO PARAMO
Drywall Nailing 3/17/2022 Not Ready for Inspection OSVALDO PARAMO
Final 3/17/2022 Not Ready for Inspection OSVALDO PARAMO
Footing/Foundation/Slab 3/17/2022 Approved OSVALDO PARAMO
Green Building Final 3/17/2022 Not Ready for Inspection OSVALDO PARAMO
Green Building Rough 3/17/2022 Approved OSVALDO PARAMO
Smoke Detectors 3/17/2022 Not Ready for Inspection OSVALDO PARAMO
Drywall Nailing 7/7/2022 Approved ALIZAH MAYAGOITIA
Final 7/7/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
Green Building Final 7/7/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
Smoke Detectors 7/7/2022 Approved ALIZAH MAYAGOITIA
Final 7/21/2022 Not Ready for Inspection HAMIK HARTOUNIAN
Green Building Final 7/21/2022 Not Ready for Inspection HAMIK HARTOUNIAN
Final 8/10/2022 OK to Issue CofO OSVALDO PARAMO
Green Building Final 8/10/2022 Approved OSVALDO PARAMO