3058 1/2 S VINEYARD AVE 90016

Certificate Information: 3058 1/2 S VINEYARD AVE 90016

Application / Permit
19014-20000-06437
Plan Check / Job No.
B19VN20652
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 10'-0" X 18'-0" DETACHED GARAGE AND ADD IRREGULAR 21'-11" X 22'-8" FOR (N) ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. ALL WORK PER WFPP.
Permit Issued
Issued on 2/14/2020
Issuing Office
Valley
Current Status
CofO Issued on 10/24/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/26/2019 APPLICANT
Assigned to Plan Check Engineer 12/2/2019 JENNIFER LEE
Corrections Issued 12/2/2019 JENNIFER LEE
Applicant returned to address corrections 12/5/2019 ANGELICA DAVE
Plan Check Approved 2/14/2020 JEFFREY TANGONAN
Issued 2/14/2020 LADBS
CofO in Progress 10/23/2023 CALEB MEISTER
Permit Finaled 10/24/2023 DEROLD HAUFF
CofO Issued 10/24/2023 DEROLD HAUFF
Permit Finaled 10/24/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 12/2/2019 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 12/2/2019 ADRIAN CASTRO
Roof/Waste drainage to street Cleared 12/2/2019 ADRIAN CASTRO
Sewer availability Cleared 12/2/2019 ADRIAN CASTRO
Flood clearance Cleared 2/12/2020 RAYMOND LAM

Contact Information

No Data Available.

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/21/2020 Approved CHARLENE BUSTAMANTE
Insulation 3/12/2020 Corrections Issued RUBEN SALAS
PLUMBING-Rough 3/12/2020 Corrections Issued RUBEN SALAS
Floor/Roof Diaphrgm/Shear Wall 3/16/2020 Partial Approval DAVID CHAN
Insulation 3/16/2020 Partial Approval DAVID CHAN
PLUMBING-Rough 3/16/2020 Partial Approval DAVID CHAN
BUILDING-Rough-Frame 4/1/2020 Partial Inspection SCOTT FINNILA
FLOOD-Proofing Certificate 4/1/2020 Partial Inspection SCOTT FINNILA
Green Building Rough 4/1/2020 Corrections Issued SCOTT FINNILA
BUILDING-Rough-Frame 4/21/2020 Partial Approval STUART CHAPMAN
ELECTRICAL-Rough 4/21/2020 Approved STUART CHAPMAN
FLOOD-Proofing Certificate 4/21/2020 Not Ready for Inspection STUART CHAPMAN
Green Building Rough 4/21/2020 Not Ready for Inspection STUART CHAPMAN
PLUMBING-Rough 4/21/2020 Approved STUART CHAPMAN
Insulation 4/29/2020 Approved SABAS ALONSO
Interior/Exterior Lathing 4/29/2020 Approved SABAS ALONSO
Drywall Nailing 5/7/2020 Approved STUART CHAPMAN
Green Building Rough 5/7/2020 Approved STUART CHAPMAN
Interior/Exterior Lathing 5/7/2020 Approved STUART CHAPMAN
BUILDING-Rough-Frame 7/1/2020 Conditional Approval STUART CHAPMAN
ELECTRICAL-Final 7/1/2020 Corrections Issued STUART CHAPMAN
FLOOD-Elevation Certificate 7/1/2020 Not Ready for Inspection STUART CHAPMAN
FLOOD-Proofing Certificate 7/1/2020 Not Ready for Inspection STUART CHAPMAN
Final 7/1/2020 Corrections Issued STUART CHAPMAN
Footing/Foundation/Slab 7/1/2020 Conditional Approval STUART CHAPMAN
Green Building Final 7/1/2020 Approved STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 7/1/2020 SGSOV Approved STUART CHAPMAN
Smoke Detectors 7/1/2020 Approved STUART CHAPMAN
BUILDING-Rough-Frame 7/9/2020 Not Ready for Inspection STUART CHAPMAN
FLOOD-Elevation Certificate 7/9/2020 Not Ready for Inspection STUART CHAPMAN
FLOOD-Proofing Certificate 7/9/2020 Not Ready for Inspection STUART CHAPMAN
Final 7/9/2020 Corrections Issued STUART CHAPMAN
Footing/Foundation/Slab 7/9/2020 Not Ready for Inspection STUART CHAPMAN
BUILDING-Rough-Frame 7/23/2020 Approved STUART CHAPMAN
FLOOD-Elevation Certificate 7/23/2020 Approved STUART CHAPMAN
FLOOD-Proofing Certificate 7/23/2020 Approved STUART CHAPMAN
Final 7/23/2020 Conditional Approval STUART CHAPMAN
Footing/Foundation/Slab 7/23/2020 Approved STUART CHAPMAN
Final 10/2/2023 Conditional Approval CALEB MEISTER